7 6 09 Riverfront Marina Worksession JJR Presentation_FINALPort of Dubuque, Iowa
Riverfront Marina Project
City Council Working Meeting -Marina Alternatives July 6, 2009
Railroad BridgeRailroad Bridge
Star BreweryStar Brewery
Grand River CenterGrand River Center
Existing Existing
transient dockstransient docks
IHbIHbceceararoror
IIHHbb
Existing Sites
1
Main Channel AlternativeMain Channel Alternative
Ice Harbor AlternativeIce Harbor Alternative
Alternative Marina Locations
585
580
575
575
570
590
590
565
560
585
585
550
580
580
575
570
575
565
560
555
570
565
560
Flat Pool = 592.07 MSL12
Main Channel Existing Bathymetry
2
Star BreweryStar Brewery
River walkRiver walk
Grand River CenterGrand River Center
Minimum 100ftMinimum 100ft
Debris Debris
Deflection Deflection
StructureStructure
Railroad Railroad
BridgeBridge
River FlowRiver Flow
Marina Alternative 1: Main Channel
Design ConsiderationsDesign Considerations
Minimum 100’ Set Back From Railroad Bridge
•
River Velocities 2.5fps to 4.5fps
•
Wave Heights up to 2’ and Boat Wakes (Long Period
•
W)aves
W)
Ice
•
Debris
•
Water Depths –Range from 6’ to 40’ (From Flat Pool)
•
Access From River Walk –Grade Issues
•
Utilities
•
Utiliti
Parking
•
Eagle Roosting Habitat
•
Main Channel Alternative
3
AdvantagesAdvantages
Boat Access Directly from Main Channel
•
Minimal Amount of Initial Dredging
•
DisadvantagesDisadvantages
DisadvantagesDisadvantages
Navigability Issues Near Railroad Bridge
•
Wave Conditions
•
Requires Diversion Structure for Ice Flows and Debris
•
Water Depth and Open Channel Environment Increase Construction
•
Costs
No Amenities or Utilities
•
Maintenance Dredging
•
Main Channel -Pros and Cons
Conceptual Cost SummaryConceptual Cost Summary
1.Marina Improvements (Approximately 67 slips) = $
2,800,000
2.Amenities and Utilities = None
3.Deflection Structures
$2,500,000 (Stone Dike)
•
$2,000,000 (Sheet Pile)
•
$1,500,000 (Caisson Piling)
•
$1,200,000 (Floating Concrete)
•
4.Total Estimated Cost Range = $4,000,000 to $5,300,000
Main Channel –Conceptual Costs
4
585
585
580
580
580
585
Ice Harbor Existing Bathymetry
Ice Harbor Alternative
5
Design ConsiderationsDesign Considerations
National Mississippi River Museum Campus Shared Use
•
Coordination
Mississippi River Rides Location and Configuration
•
Requirements
Requirements
Newt Marine Barge Turning Requirements
•
Coast Guard Space Requirements
•
Ice Harbor Alternative
AdvantagesAdvantages
•Protected Harbor
No Debris
•
No Ice
•
Limited Wake
•
Minimal Water Level Fluctuations
•
•Ease of Access
•Central Location
•True ADA Accessibility
•Amenities and Utilities
•Adjacent Utility Service
•Adjacent Space for Fuel Tank Locations
•Achieve All Programming Elements within Budget
•Grant Transferable to this Location
•Space for a Marina Services Building
DisadvantagesDisadvantages
•Possible Minor Initial Dredging
•Competing Adjacent Uses
Ice Harbor -Pros and Cons
6
Conceptual Cost SummaryConceptual Cost Summary
1.Marina Improvements = $
(Approximately 59 additional slips)
2,400,000
2.Amenities and Utilities = $1,500,000
3.Total Estimated Cost Range = $3,900,000
Ice Harbor –Conceptual Costs
Bettendorf, IA
Deflection Structures and Promenades
7
Portland, OR
Deflection Structures and Promenades
Design Features: Gangways
8
ADA Accessible
Design Features: Gangways
Design Features: Docks
9
Design Features: Fuel Docks
Port of Dubuque, Iowa
Riverfront Marina Project
City Council Working Meeting -Marina Alternatives July 6, 2009
10