2022 Asphalt Overlay Ramp Project 2_HearingCopyrighted
April 4, 2022
City of Dubuque Public Hearings # 1.
City Council Meeting
ITEM TITLE: 2022 Asphalt Overlay Ramp Project 2
SUMMARY: Proof of publication on notice of public hearing to consider City Council
approval of the plans, specifications, form of contract and estimated cost
for the 2022 Asphalt Overlay Ramp Project 2 through the adoption of a
resolution, and City Manager recommending approval.
SUGGESTED
DISPOSITION:
ATTACHMENTS:
Description
RESOLUTION Approval of plans, specifications, form of contract, and
estimated cost for the 2022 Asphalt Overlay Ramp Project 2
Suggested Disposition: Receive and File; Adopt Resolution(s)
2022 Asphalt Overlay Ramp Project 2-MVM Memo
Staff Memo
Type
City Manager Memo
Staff Memo
Resolution Resolutions
THE C
DUj!BQTE
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 2022 Asphalt Overlay Ramp Project 2
DATE: March 30, 2022
Dubuque
WAWca 914
ii
2007-2012.2013
2017*2019
City Engineer Gus Psihoyos is recommending City Council approve the plans,
specifications, form of contract and estimated cost for the 2022 Asphalt Overlay Ramp
Project 2 through the adoption of a resolution.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
v
Mic ael C. Van Milligen
MCVM:sv
Attachment
CC' Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
THE C
DUUB--*--FE
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
DATE: March 28, 2022
RE: 2022 Asphalt Overlay Ramp Project 2
INTRODUCTION
Dubuque
AIIā¢Ameriea M
1 I
I I
2007-2012.2013
2017*2019
The purpose of this memorandum is to provide the City Council with information related
to the public hearing for the 2022 Asphalt Overlay Ramp Project 2.
BACKGROUND
Since 1990, the City of Dubuque has installed pedestrian access ramps around the City
of Dubuque to conform with the American with Disabilities Act (ADA). The pedestrian
access ramps allow people with mobility difficulties to access the City's sidewalk system.
The design standards for these ramps have evolved over time as more ramps have been
installed and standards have changed.
Since 2011, The City of Dubuque has followed the "Proposed Accessibility Guidelines for
Pedestrian Facilities in the Public Right -of -Way." These are updated standards to use for
facilities in the public right-of-way and addressed issues brought up since the original
ADA standards were developed. The Iowa Department of Transportation has adopted the
PROWAG standards. The Federal Highway Administration (FHWA) has also adopted the
standards and requires all cities that receive federal funding to follow these standards.
DISCUSSION
This project includes the replacement of twenty-eight (28) access ramps, two (2) intake
replacements and curb and sidewalk repairs at 12 intersections in conjunction with the
Public Works Asphalt Overlay program at the following locations:
1. Auburn Street at University Ave, one single ramp.
2. Auburn Street alley between University Ave and Grace Street, two single ramps.
3. Grace Street at Griggs Street, two single ramps.
4. Grace Street at Ida Street, two single ramps.
5. Grace Street at alley East of 1819 Grace Street, two single ramps.
6. Bennett Street at alley East of 1755 Bennett Street, two single ramps.
7. Bennett Street at alley East of 1854 Bennett Street, two single ramps.
8. Bennett Street at Griggs Street, two single ramps.
9. Bennett Street at McCormick Street, one single ramp.
10. Bennet Street at N. Algona Street, curb, and sidewalk replacement.
11. Chaney Street at St. Anne Drive, two single and 2 double ramps.
12. Chaney Street at Hillcrest Road, two single and two double ramps.
PUBLIC ENGAGEMENT
The Public Works Department will mail letters to property owners and the Engineering
Department has developed door hangers for residents notifying residents of the overlay
and ramp project.
PROJECT SCHEDULE
The schedule for the Project is as follows:
Initiate Public Bidding Process
March 21, 2022
Publish Notice to Bidders, Advertise for Bids
March 22, 2022
Publish Public Hearing Notice on Plans & Specs
March 22, 2022
Public Hearing on Plans & Specifications
April 4, 2022
Receipt of Bids (Bid Letting)
April 7, 2022
Award Construction Contract
April 18, 2022
Final Project Completion
July 1, 2022
RECOMMENDATION
I recommend that the City Council approve the plans, specifications, form of contract and
estimated cost for the 2022 Asphalt Overlay Ramp Project 2.
BUDGETIMPACT
The preliminary estimate of probable costs for the 2022 Asphalt Overlay Ramp Project 2
is as follows:
Description
Cost Estimate
Construction
$ 177,750.40
Contingency
$ 17,775.40
Engineering Design and Administration
$ 19,552.54
Total Construction Cost Estimate
$ 215,077.98
The funding summary is as follows:
CIP
Fund Description
Fund Amount
3001227
Curb Ramp Program
$ 215,077.98
ACTION TO BE TAKEN
The City Council is requested to approve the plans, specifications, form of contract and
estimated cost for the 2022 Asphalt Overlay Ramp Project 2 through the adoption of the
attached resolution.
E
GNP/kb
cc: John Klostermann, Public Works Director
Jon Dienst, Civil Engineer II
Prepared by Kerry Bradley City of Dubuque 50 W. 1311 Street Dubuque IA 52001 (563) 589 4270
Return to Adrienne Breitfelder, City Clerk, City of Dubuque, 50 W. 13th Street, Dubuque, IA 52001 (563) 589-4100
RESOLUTION NO. 123-22
APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND
ESTIMATED COST FOR THE 2022 ASPHALT OVERLAY RAMP PROJECT 2
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the proposed plans, specifications, form of contract and estimated cost for
the 2022 Asphalt Overlay Ramp Project 2, in the estimated amount $177,750.40, are
hereby approved.
Passed, adopted, and approved this this 4th day of April 2022.
Attest:
Adrienne N. Breitfelder, City Clerk
STATE OF IOWA SS:
DUBUQUE COUNTY
CERTIFICATE OF PUBLICATION
I, Kathy Goetzinger, a Billing Clerk for Woodward
Communications, Inc., an Iowa corporation, publisher
of the Telegraph Herald, a newspaper of general
circulation published in the City of Dubuque, County
of Dubuque and State of Iowa; hereby certify that the
attached notice was published in said newspaper on the
following dates:
03/25/2022
and for which the charge is 52.60
Subscribed to before me, a Notary Pu 'c in and for
Dubuque County, Iowa,
this 25th day of March, 2022
Notary Public in and for Dubuque County, Iowa.
e SRARON WYELBORN
Cam gii:ssion W mimmber $27408
My Gmmmma. Exp. NOV I01 2023
Ad text : CITY OF DUBUQUE, IOWA
OFFICIAL NOTICE
NOTICE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST FOR THE 2022 ASPHALT OVERLAY RAMP
PROJECT 2
NOTICE IS HEREBY GIVEN: The Dubuque City Council will hold
a public hearing on the proposed plans, specifications, form
of contract and estimated cost for the 2022 Asphalt Overlay
Ramp Project 2 in accordance with the provisions of Chapter
26, Code of Iowa, at 6:30 p.m., on the 4th day of April 2022,
in the Historic Federal Building, 350 West 6th Street, 2nd
Floor, Dubuque, Iowa.
The scope of the Project is as follows:
This project includes the replacement of twenty-eight (28)
access ramps, two (2) intake replacements and curb and
sidewalk repairs at 12 intersections in conjunction with the
Public Works Asphalt Overlay program at the following
locations:
1."Auburn Street at University Ave, one single ramp.
2. "Auburn Street alley between University Ave and Grace
Street, two single ramps.
3."Grace Street at Griggs Street, two single ramps.
4."Grace Street at Ida Street, two single ramps.
5. "Grace Street at alley East of 1819 Grace Street, two single
ramps.
6."Bennett Street at alley East of 1755 Bennett Street, two
single ramps.
7. "Bennett Street at alley East of 1854 Bennett Street, two
single ramps.
8."Bennett Street at Griggs Street, two single ramps.
9. "Bennett Street at McCormick Street, one single ramp.
10."Bennet Street at N. Algona Street, curb, and sidewalk
replacement.
11. "Chaney Street at St. Anne Drive, two single and 2 double
ramps.
12."Chaney Street at Hillcrest Road, two single and two
double ramps.
At the meeting, the City Council will receive oral and
written comments from any resident or property owner of said
City to the above action. The official agenda will be posted
the Friday before the meeting and will contain public input
options. The City Council agenda can be accessed at
https://cityofdubuque.novusagenda.com/AgendaPublic/ or by
contacting the City Clerk's Office at 563-589-4100,
ctyclerk@cityofdubuque.org.
Written comments regarding the above public hearings may be
submitted to the City Clerk's Office via email at
ctyclerk@cityofdubuque.org or by mail to City Clerk's Office,
City Hall, 50 W. 13th St., Dubuque, IA 52001, before said
time of public hearing. At said time and place of public
hearings the City Council will receive any written comments.
Said proposed plans, specifications, form of contract and
estimated cost are now on file in the office of the City Clerk
and may be viewed Monday through Friday between 8:00 a.m. and
5:00 P.M.
Individuals with limited English proficiency, vision,
hearing, or speech impairments requiring special assistance
should contact the City Clerks Office at (563) 589-4100,
ctyclerk@cityofdubuque.org as soon as feasible. Deaf or
hard -of -hearing individuals can use Relay Iowa by dialing 711
or (800) 735-2942.
Published by order of the City Council given on the 21st day
of March 2022.
Adrienne N. Breitfelder, City Clerk
It 3/25