April 18, 2022
ITEM TITLE: Northwest Arterial - State of Good Repair Project: US Highway 20 to
John F. Kennedy Road
SUMMARY: Proof of publication on notice of public hearing to consider City Council
adoption of a resolution approving the plans, specifications, form of
contract and estimated cost in the amount of $8,852,000 for the
Northwest Arterial - State of Good Repair Project from US20 to John F.
Kennedy Road, and City Manager recommending approval.
RESOLUTION Approval of plans, specifications, form of contract, and
estimated cost for the Northwest Arterial — State of Good Repair Project
from US20 to John F. Kennedy Road (Iowa DOT Project No. STBG-
SWAP-2100 (702)—SG-31)
SUGGESTED Suggested Disposition: Receive and File; Adopt Resolution(s)
DISPOSITION:
FIN ik[91:ILyil21zIII l+]
Description Type
Northwest Arterial State of Good Repair Project - US City Manager Memo
Highway 20 to John F. Kennedy Road-MVM Memo
Staff Memo Staff Memo
Resolution Resolutions
THE C
DUj!BQTE
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Northwest Arterial - State of Good Repair Project
US Highway 20 to John F. Kennedy Road
Iowa DOT Project No. STBG-SWAP-2100 (702)--SG-31
DATE: April 12, 2022
Dubuque
WAWca 914
ii
2007-2012.2013
2017*2019
Assistant City Engineer Robert Schiesl is recommending City Council adopt a resolution
approving the plans, specifications, form of contract and estimated cost in the amount of
$8,852,000 for the Northwest Arterial - State of Good Repair Project from US20 to John
F. Kennedy Road.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Robert Schiesl, Assistant City Engineer
THE CITY OF
DUB-
E
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
Gus Psihoyos, City Engineer
FROM: Robert Schiesl, Assistant City Engineer
DATE: April 12, 2022
SUBJECT: Northwest Arterial - State of Good Repair Project
US Highway 20 to John F. Kennedy Road
Iowa DOT Project No. STBG-SWAP-2100 (702)--SG-31
INTRODUCTION
Dubuque
All -America M4
2007.2012.2013
2017*2019
The enclosed resolution is in reference to the public hearing for the Northwest Arterial -
State of Good Repair Project from US20 to John F. Kennedy Road, Iowa DOT Project
No. STBG-SWAP-2100 (702)--SG-31.
BACKGROUND
Dubuque County was awarded a BUILD Grant to make capacity and safety improvements
to John Deere Road. The Northwest Arterial - State of Good Repair Project was added to
the BUILD grant project because it is a critical freight route that connects to South John
Deere Road. The Northwest Arterial - State of Good Repair Project will provide the non-
federal local match to the Dubuque County BUILD Grant.
The Northwest Arterial project was originally anticipated to be completed by the Iowa
DOT, however as part of the executed Transfer of Jurisdiction Agreement (TOJ), the City
agreed to be the lead local agency responsible for completing the Northwest Arterial -
State of Good Repair improvements.
Effective January 29, 2021, the TOJ of the Northwest Arterial was completed from the
State of Iowa to the City as part of the Southwest Arterial project. As part of the roadway
transfer, the Iowa DOT has issued a state of good repair payment to the City in the amount
of $5,672,000 to complete pavement rehabilitation and reconstruction of the Northwest
Arterial from US20 to Central Ave / IA3.
DISCUSSION
The project work limits for the Northwest Arterial - State of Good Repair will be from US20
to John F. Kennedy Road, and will include pavement rehabilitation of the southbound
lanes, reconstruction of the northbound lanes, and the reconstruction of both the
Pennsylvania Ave. and Asbury Rd. intersections.
The work on the southbound lanes will include 4 ft. wide asphalt shoulders and 1.5-inch
milling and resurfacing with an asphalt overlay. The work on the northbound lanes will
include the removal of the existing concrete pavement, excavation for new stone base,
installation of pavement subdrains, new 12-inch stone base and new 13.5-inch asphalt
pavement. The Pennsylvania Ave. intersection will be fully reconstructed with asphalt
pavement and the east half of the Asbury Rd. intersection will be reconstructed with
asphalt pavement.
In August 2019, the City was awarded an Iowa DOT Traffic Safety Improvement Program
(TSIP) Grant (Iowa DOT Project No. CS-TSF-2100 (700)--85-31) to assist with the
construction to extend the existing eastbound left -turn lane on Northwest Arterial at John
F. Kennedy Road. Northwest Arterial — State of Good Repair Project will include this left
turn lane improvement that will extend the existing eastbound Northwest Arterial
dedicated left turn lane onto JFK Road to an approximate 400' storage length.
The Northwest Arterial — State of Good Repair Project will be packaged and bid as part
of Dubuque County's John Deere Road Build project, which is scheduled for letting on
April 19, 2022, through the Iowa DOT in Ames. The City and County projects were moved
by the Iowa DOT from the March 2022 letting due to the large number of projects
submitted state-wide for the March bid letting.
PROJECT SCHEDULE
The project development schedule for the Northwest Arterial - State of Good Repair
Project from US20 to JF Kennedy Road is as follows:
Iowa DOT Advertisement for Bids
March 16, 2022
City Initiate Concurrence in Public Bidding Process
April 4, 2022
City Publish Public Hearing Notice on Plans &Specifications
April 8, 2022
City Public Hearing on Plans & Specifications
April 18, 2022
Iowa DOT Receipt of Bid Proposals (Bid -Letting)
April 19, 2022
City Award Construction Contract (Subject to Iowa DOT Approval)
May 2, 2022
Project Intermediate Completion Date
Completion of Pennsylvania & Asbury Intersections
August 22, 2022
2022 Construction Season End Date (Approx.)
November 15, 2022
2023 Construction Season Start Date (Approx.)
April 15, 2023
Project Final Completion Date
August 18, 2023
The project construction schedule has been developed in a manner which allows for the
safety of the traveling public and contractor as well as provides multiple construction
phases to reduce traffic delay and minimize impact to schools and businesses through
the corridor. The first phase of the project will require the contractor to complete the
Pennsylvania and Asbury intersection reconstruction work before school starts in August
of 2022. The pavement rehabilitation of the southbound lanes requires the contractor to
work at night between 7 pm and 7 am.
Due to the magnitude and scope of the work, and the multiple construction sequencing
stages required to maintain traffic flow through the NW Arterial corridor, the project will
not be to be fully completed this construction season. The contract specified completion
date is August 18, 2023.
CENTRAL AVENUE / WHITE STREET TRUCK ROUTE
Prior to the TOJ of the Northwest Arterial from the State of Iowa to the City and the re -
designation and rerouting of US52, the city ordinance regulating commercial motor
vehicles was amended to allow motor trucks to continue to use the Central Avenue and
White Street corridor as an authorized truck route through December 31, 2022. This date
was established prior to the full scope of work was known for the Northwest Arterial -
State of Good Repair Project, which now has a completion date of August 2023.
City staff will be meeting to discuss the Central Avenue and White Street corridor and if
the city ordinance regulating commercial motor vehicles will need to be amended to
accommodate the Northwest Arterial project extending into 2023.
RECOMMENDATION
I recommend City Council approve the plans, specifications, form of contract and
estimated cost for the Northwest Arterial - State of Good Repair Project.
BUDGETIMPACT
The estimate of probable cost for the Northwest Arterial - State of Good Repair Project is
as follows:
Description
Estimate
Construction Contract
$ 8,172,000
Contingency
200,000
Engineering Design / NEPA Environmental Clearance
250,000
Contract Admin / Construction Engineering
230,000
Total Project Cost
$ 8,852,000
The anticipated project funding is summarized as follows:
CIP No.
Fund Description
Fund
Amount
DMATS STBG SWAP Funds
$ 4,431,420
3002876
Local - NWA TOJ Rehab Reconstruction
4,240,580
TSIP Grant
105,000
3002850
Local - NW Arterial JFK Left Turn
75,000
Total Project Funding
$ 8,852,000
** The local funding portion comes from the Iowa DOT state of good repair
payment to the City for the Northwest Arterial segment from US20 to John
F. Kennedy Road which will be used as the non-federal local match to the
Dubuque County BUILD Grant.
ACTION TO BE TAKEN
The City Council is requested to approve the plans, specifications, form of contract and
estimated cost for the Northwest Arterial - State of Good Repair Project from US20 to
John F. Kennedy Road through adoption of the enclosed resolution.
Prepared by Nathan Steffen, P.E., Civil Engineer
cc: Jenny Larson, Director of Finance and Budget
Kent Ellis, P.E., Iowa DOT
F:\PROJECTS\NW Arterial - State of Good Repair - US 20 to JFK\Council & Staff Documents
Prepared by Robert Schiesl City of Dubuque Engineering 50 W. 1311 St. Dubuque IA 52001 (563)589-4270
Return to Adrienne N. Breitfelder City Clerk City of Dubuque, 50 W. 1311 St. Dubuque, IA 52001 (563)589-4100
RESOLUTION NO. 148-22
APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND
ESTIMATED COST FOR THE NORTHWEST ARTERIAL — STATE OF GOOD REPAIR
PROJECT FROM US20 TO JOHN F. KENNEDY ROAD (IOWA DOT PROJECT NO.
STBG-SWAP-2100 (702)—SG-31)
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the proposed plans, specifications, form of contract and estimated cost for
the Northwest Arterial - State of Good Repair Project from US 20 to John F. Kennedy
Road (Iowa DOT Project No. STBG-SWAP-2100 (702)—SG-31), in the estimated amount
$8,852,000, are hereby approved.
Passed, adopted, and approved this this 18th day of April 2022.
MINE,
Attest:
Adrienne N. Breitfelder, City Clerk
STATE OF IOWA SS:
DUBUQUE COUNTY
CERTIFICATE OF PUBLICATION
I, Kathy Goetzinger, a Billing Clerk for Woodward
Communications, Inc., an Iowa corporation, publisher
of the Telegraph Herald, a newspaper of general
circulation published in the City of Dubuque, County
of Dubuque and State of Iowa; hereby certify that the
attached notice was published in said newspaper on the
following dates:
04/08/2022
and for which the charge is 43.83
Subscribed to before me, a Notary Public in and for
Dubuque County, Iowa,
this 8th day of April, 2022
Notary Public in and for Dubuque County, Iowa.
Skl,4.RO ' VW''B!2,2174"'04
' �: Ca�maruuea;Ww NwInber
p, HICY 12023
Ad text : CITY OF DUBUQUE, IOWA
OFFICIAL NOTICE
NOTICE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST FOR NORTHWEST ARTERIAL STATE OF
GOOD REPAIR PROJECT, US20 TO JOHN F. KENNEDY ROAD, IOWA DOT
PROJECT NO. STBG-SWAP-2100 (702)--SG-31
NOTICE IS HEREBY GIVEN: The City Council of the City of
Dubuque, Iowa will hold a public hearing on the proposed
plans, specifications, form of contract and estimated cost for
the Northwest Arterial State of Good Repair Project from US20
to John F. Kennedy Road, Iowa DOT Project No. STBG-SWAP-2100
(702)--SG-31, in accordance with the provisions of Chapter 26,
Code of Iowa, at 6:30 p.m., on the 18th day of April, 2022, in
the Historic Federal Building Council Chambers (second floor),
350 West 6th Street, Dubuque, Iowa. Said proposed plans,
specifications, form of contract and estimated cost are now on
file in the office of the City Clerk. At said hearing any
interested person may appear and file objections thereto.
The scope of the Project is as follows:
- The project will provide for the pavement rehabilitation
of the southbound lanes, reconstruction of the northbound
lanes and reconstruction of the Pennsylvania Avenue and Asbury
Road intersections along the Northwest Arterial corridor from
US Highway 20 to John F. Kennedy Road.
At the meeting, the City Council will receive oral and
written comments from any resident or property owner of said
City to the above action. The official agenda will be posted
the Friday before the meeting and will contain public input
options. The City Council agenda can be accessed at
https://cityofdubuque.novusagenda.com/AgendaPublic/ or by
contacting the City Clerks Office at 563-589-4100,
ctyclerk@cityofdubuque.org.
Written comments regarding the above public hearings may be
submitted to the City Clerks Office via email at
ctyclerk@cityofdubuque.org or by mail to City Clerk's Office,
City Hall, 50 W. 13th St., Dubuque, IA 52001, before said
time of public hearing. At said time and place of public
hearings the City Council will receive any written comments.
Copies of supporting documents for the public hearings are
on file in the City Clerk's Office and may be viewed Monday
through Friday between 8:00 a.m. and 5:00 p.m.
Individuals with limited English proficiency, vision,
hearing, or speech impairments requiring special assistance
should contact the City Clerks Office at (563) 589-4100,
ctyclerk@cityofdubuque.org as soon as feasible. Deaf or
hard -of -hearing individuals can use Relay Iowa by dialing 711
or (800) 735-2942.
Published by order of the City Council given on the 4th day
of April 2022.
Adrienne N. Breitfelder, City Clerk