Wilbricht Lane Detention Basin ProjectCity of Dubuque City Council Meeting Consent Items # 012. Copyrighted May 2, 2022 ITEM TITLE: Wilbricht Lane Detention Basin Project SUMMARY: City Manager recommending City Council adopt a resolution awarding the construction contract for the Wilbricht Lane Detention Basin Project to McDermott Excavating in the low bid amount of $327,121.00. SUGGESTED DISPOSITION: ATTACHMENTS: Description RESOLUTION Awarding the Public Improvement Contract for the Wilbricht Lane Detention Basin Project Suggested Disposition: Receive and File; Adopt Resolution(s) Wilbricht Lane Detention Basin Project-MVM Memo Staff Memo Type City Manager Memo Staff Memo Resolution Resolutions THE C DUj!BQTE Masterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Wilbricht Lane Detention Basin Project C I P# 7202722 DATE: April 26, 2022 Dubuque WAWca 914 ii 2007-2012.2013 2017*2019 City Engineer Gus Psihoyos is recommending City Council adopt a resolution awarding the construction contract for the Wilbricht Lane Detention Basin Project to McDermott Excavating in the low bid amount of $327,121.00. I concur with the recommendation and respectfully request Mayor and City Council approval. v Mic ael C. Van Milligen MCVM:sv Attachment cc: Crenna Brumwell, City Attorney Cori Burbach, Assistant City Manager Gus Psihoyos, City Engineer THE C DUUB--'&-FE Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer SUBJECT: Wilbricht Lane Detention Basin Project CIP# 7202722 DATE: April 20, 2022 INTRODUCTION Dubuque All -Americo City 2007-2012.2013 2017*2019 The attached resolution authorizes the award of the construction contract for the Wilbricht Lane Detention Basin Project. BACKGROUND With the adoption of the FY18 CIP Budget, the City Council established $50,000 for the Wilbricht Detention Basin Project. Through the budget amendment process, the City Council allocated additional funding for the project establishing $457,993.00 for the project in FY22. The proposed Wilbricht Lane Detention Basin will address the localized flooding that has occurred along Glendale Court. And while additional drainage improvements may be in order, the proposed improvements will reduce the flow of runoff to downstream facilities, alleviating the flooding issues at Marmora Avenue and behind the houses on McPoland Avenue. On April 4, 2022 the City Council adopted Resolution 124-22 approving the plans, specifications, form of contract and estimated cost for the Wilbricht Lane Detention Basin Project, in the estimated amount $ 448,323.50. DISCUSSION The City received bids on April 18, 2022 for the Wilbricht Lane Detention Basin Project. McDermott Excavating of Dubuque, Iowa submitted the low bid in the amount of $327,121.00, which is 27.03% below the engineer's estimate. A summary of the bid proposals received is as follows: Contractor Bid Amount McDermott Excavating $327,121.00 Gansen Excavating $335,643.73 Mainline Excavating $335,948.08 Connolly Construction, Inc. $345,712.07 Tschiggfrie Excavating Co. $402,174.30 Eastern Iowa Excavating & Concrete, LLC $423,634.35 RECOMMENDATION I recommend awarding the contract for the for the Wilbricht Lane Detention Basin Project to McDermott Excavating in the low bid amount of $327,121.00. BUDGETIMPACT The estimated cost for the Wilbricht Lane Detention Basin Project is as follows: Description Estimate Award Construction Contract $448,096.00 $327,121.00 Contingency 5% 25,125.00 25,125.00 Engineering 26,380.00 26,380.00 [Total Project Cost $554,001.00 $378,626.00 The funding summary is as follows: CIP No. Fund Description Fund Amount 7202722 Wilbricht Lane Detention Basin $457,993.00 Funding Source Stormwater Utility Construction Funds $457,993.00 ACTION TO BE TAKEN I recommend that the City Council adopt the attached resolution awarding the construction contract for the Wilbricht Lane Detention Basin Project to McDermott Excavating in the low bid amount of $327,121.00. Prepared by Deron Muehring CC' Crenna Brumwell, City Attorney Jenny Larson, Director of Finance and Budget Deron Muehring, Civil Engineer E Prepared by Deron Muehring City of Dubuque Engineering 50 W 13" St Dubuque Iowa 52001 (563)589-4270 Return to Adrienne N. Breitfelder City of Dubuque City Clerk 50 W 131" St Dubuque, Iowa 52001 (563)589-4100 RESOLUTION NO. 172-22 AWARDING THE PUBLIC IMPROVEMENT CONTRACT FOR THE WILBRICHT LANE DETENTION BASIN PROJECT Whereas, sealed proposals have been submitted by contractors for the Wilbricht Lane Detention Basin Project (the Project) pursuant to Resolution No. 91-22 and Notice to Bidders published on the City of Dubuque, Iowa website and plan room service with statewide circulation on the 22nd day of March 2022; and Whereas, said sealed proposals were opened and read on the 14th day of April 2022 and it has been determined that McDermott Excavating of Dubuque, Iowa, with a low bid in the amount of $327,121.00 is the lowest responsive, responsible bidder for the Project. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That a Public Improvement Contract for the Project is hereby awarded to McDermott Excavating and the City Manager is hereby directed to execute a Public Improvement Contract on behalf of the City of Dubuque for the Project. Passed, approved, and adopted this 2nd day of May 2022. i Attest: &1 v �w /7 42�t ,9, Adrienne N. Breitfelder, City Clerk