Kennedy Road Water Main Extension Project 2021 — Project Acceptance and ResolutionCity of Dubuque City Council Meeting Consent Items # 012. Copyrighted October 17, 2022 ITEM TITLE: Kennedy Road Water Main Extension Project 2021 — Project Acceptance and Resolution SUMMARY: City Manager recommending adoption of the resolution for the acceptance and authorization for the final payment of the Kennedy Road Water Main Extension Project 2021 to Drew Cook and Sons Excavating of Dubuque, Iowa in the amount of $26,135.56 for a final contract amount of $767,947.25. RESOLUTION Accepting Public Improvement Contract for the Kennedy Rd Water Main Extension Project 2021 SUGGESTED Suggested Disposition: Receive and File; Adopt Resolution(s) DISPOSITION: ATTACHMENTS: Description Type Kennedy Road Water Main Extension Project 2021 - City Manager Memo Project Acceptance and Resolution-MVM Memo Kennedy Rd Project Acceptance Memo Staff Memo Kennedy Rd Project Acceptance Resolution Resolutions THE C DUj!BQTE Masterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Kennedy Rd Water Main Extension Project 2021 — Project Acceptance and Resolution DATE: October 11, 2022 Dubuque WAWca 914 ii 2007-2012.2013 2017*2019 Water Department Manager Christopher Lester is recommending City Council adopt a resolution for the acceptance and authorization for the final payment of the Kennedy Rd Water Main Extension Project 2021 to Drew Cook and Sons Excavating of Dubuque, Iowa in the amount of $26,135.56 for a final contract amount of $767,947.25. I concur with the recommendation and respectfully request Mayor and City Council approval. Mic ael C. Van Milligen MCVM:sv Attachment cc: Crenna Brumwell, City Attorney Cori Burbach, Assistant City Manager Christopher Lester, Water Department Manager THE CITY OF DUB TE Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Manager FROM: Christopher Lester, Water Department Manager DATE: October 6, 2022 RE: Kennedy Rd Water Main Extension Project 2021 — Project Acceptance and Resolution Dubuque All-Anerin City Ntl kAM1L I. Nt: I � /j.l •i 2007.2012.2013 2017*2019 INTRODUCTION The purpose of this memorandum is to provide discussion and final project summary along with the enclosed resolution for the acceptance and authorization for final payment of the Kennedy Rd Water Main Extension Project 2021. BACKGROUND The FY21 CIP Budget included funding for the John F. Kennedy water main extension — Forest Glen Ct. to Daisy Trail Project. This is commonly known as the Wildflower Ridge Water Main Project. The City of Dubuque was contacted by Vendors Unlimited Corporation which owns, operates, and maintains the private water system serving Wildflower Ridge. The Vendors Unlimited Corporation water distribution system serves 5E lots. City of Dubuque staff and Vendors Unlimited Corporation have had several discussions and meetings over the last few years, which have resulted in the preparation of an MOU between the City of Dubuque and Vendors Unlimited Corporation for the connection of Wildflower Ridge's water distribution system to the City of Dubuque's water system. DISCUSSION The project provided for the installation of approximately 4,250 lineal feet of 12-inch ductile iron pipe (DIP) water main along the north ditch line of John F. Kennedy Road from Forest Glen Court to Daisy Trail. Additionally, four hydrants were to be placed with 8-inch ductile iron pipe (DIP) leads to the south side of John F. Kennedy Road to provide fire protection and future connection to the water main. BUDGETIMPACT Funding for the project will be from Water Department CIP 740-2836 Water Line Extensions to New Developments. The authorized funding source available to cover the projects costs at the time of bidding are: CIP No. Department Project Available Funding 740-2836 Water Kennedy Rd Water Main Extension $1,082,500 The MOU for the Kennedy Road Water Main Extension Project included as part of the agreement to install a PRV Vault at the entrance to the Wildflower Ridge subdivision. The PRV would reduce the incoming water pressure from 114 PSI to 80 PSI to serve the subdivision. The Kennedy Road water main extension project as bid did not include the PRV Vault. The reasoning for this was the intent of the owner following discussions with Water Department Staff to install individual PRV's and not include the main line PRV Vault on Daisy Trail. However, upon further review, there was a better understanding as to why the PRV was included in the MOU. The PRV would not only ensure pressures would be acceptable going into the homes but also ensure pressures would not exceed the DNR's design standards, commonly known as the 10 State Standards, of 100 PSI. This protects the existing infrastructure and reduces main breaks and leaks. Therefore, the PRV Vault was recommended and approved to be installed per the MOU on February 3, 2022. McDermott Excavating of Dubuque, Iowa submitted the low bid in the amount of $74,835.00. We received approval to enter a contract with McDermott Excavating for the project on 12/10/21. Final construction costs associated with the PRV Vault totals $76,266.05. The final costs for the Kennedy Rd Water Main Extension Project 2021 are: Description Award Final Construction Cost — Water Main — Drew Cook Excay. $752,852.00 $752,852.00 Contingency (10%) — Water Main — Drew Cook Excay. $75,285.20 $15,095.25 Construction Cost — PRV - McDermott Excavating $74,835.00 $76,266.05 Engineering Design (Preliminary and Final) WHKS $43,000.00 $74,142.07 Engineering Services — City of Dubuque $10,000.00 $7,111.00 Total Estimate Project Cost $955,972.20 $925,466.37 The final project construction costs are $925,466.37, which is 3.2% less than original bid amounts. The contract adjustment is recorded via Change Order No. 2. ACTION TO BE TAKEN The City Council is requested to adopt the attached resolution to accept the improvements and authorize the final payment for the Kennedy Rd Water Main Extension Project 2021. cc: Jenny Larson, Director of Finance & Budget Kerry Leppert, Water Engineering Assistant F:\Users\Water\ENGINEERING\Projects - City Projects\Projects - ACTIVE (City)\Kennedy Rd WM Extension(Daisy Trail) (2021) 740- 2836\Council\Acceptance of Improvements 2 Prepared by: Christopher Lester Water Department Manager, 901 Hawthorn St Dubuque IA 52001 (563) 589 4290 Return to Adrienne N. Breitfelder, City Clerk, 50 W. 1311 St., Dubuque, IA 52001, (563) 589-4100 RESOLUTION NO. 331-22 ACCEPTING PUBLIC IMPROVEMENT CONTRACT FOR THE KENNEDY RD WATER MAIN EXTENSION PROJECT 2021 WHEREAS, the public improvement contract for the Kennedy Rd Water Main Extension Project, (the Project) has been completed by the Contractor, Drew Cook and Sons Excavating of Dubuque, Iowa, (Contractor), the Water Department Manager has examined the work and recommends that the Project be accepted; and WHEREAS, the final contract amount is $767,947.25 of which retainage in the amount $26,135.56 shall be held for 30 days after acceptance and approval, and paid at that time provided no claims from others are filed; and WHEREAS, the City Council finds that the recommendation of the Water Department Manager should be accepted. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the Water Department Manager is approved, and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor the balance of the final payment $26,135.56 as provided in Iowa Code chapter 573.13. Passed, adopted, and approved this 17th day of October, 2022. Bead M Cavanagh, Mayor Attest: Adrienne N. Breitfelder, City Clerk WATER DEPARTMENT MANAGER CERTIFICATE OF FINAL COMPLETION OF THE KENNEDY ROAD WATER MAIN EXTENSION TO DAISY TRAIL The undersigned Water Department Manager of the City of Dubuque, Iowa, hereby certifies that he has inspected the Kennedy Road Water Main Extension to Daisy Trail, that the Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $925,466.37. Dated this 17th day of October 2022. Christopher J. Lester, Water Departme t Manager Filed in the office of the City Clerk on the 17t" day of October, 2022. Adrienne N. Breitfelder, City Clerk