Four Mounds Parking & Accessibility ImprovementsCopyrighted
October 17, 2022
City of Dubuque Consent Items # 013.
City Council Meeting
ITEM TITLE: Four Mounds Parking &Accessibility Improvements
SUMMARY: City Manager recommending adoption of the resolution accepting the
improvements and authorize the payment of the final contract to
McDermott Excavating for the Four Mounds Parking & Accessibility
I mprovements.
RESOLUTION Accepting the Four Mounds Parking & Accessibility
Improvements and authorizing the payment to the contractor
SUGGESTED Suggested Disposition: Receive and File; Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
Description Type
Acceptance of Four Mounds Parking Improvements- City Manager Memo
MVM Memo
Staff Memo
Resolution
Staff Memo
Resolutions
THE C
DUj!BQTE
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Four Mounds Parking & Accessibility Improvements
Project 1315000011
DATE: October 11, 2022
Dubuque
WAWca 914
ii
2007-2012.2013
2017*2019
City Engineer Gus Psihoyos is recommending City Council adopts the resolution
accepting the improvements and authorize the payment of the final contract amount of
$90,143.62 to McDermott Excavating for the Four Mounds Parking & Accessibility
Improvements.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
v
Mic ael C. Van Milligen
MCVM:sv
Attachment
CC' Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Jon Dienst, P.E.
THE C
DUj!B9kFE
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: Four Mounds Parking & Accessibility Improvements
Project 1315000011
DATE: October 7, 2022
INTRODUCTION
Dubuque
AIIā¢Amarica City
2007-2012.2013
2017*2019
The enclosed resolution provides for the acceptance of the construction contract for the
Four Mounds Parking & Accessibility Improvements.
BACKGROUND
The Four Mounds Parking and Accessibility Improvements project provided for the
construction of an additional nine hard surfaced parking spaces with five -inch hot mix
asphalt pavement with concrete historic mix edge bands and ADA accessible sidewalk.
Additionally, historic concrete mix edge bands, subdrains, excavation and special fiber
reinforced turf parking areas were completed.
DISCUSSION
The Four Mounds Parking & Accessibility Improvements was completed by McDermott
Excavating, of Dubuque, IA in the final contract amount of $90,143.62. This is a 78.7%
increase over the original contract amount of $50,443.50. The increase was due to
adding the final fiber turf areas to the project. The original bid project did not include the
reinforced topsoil and turf for the turf parking areas. Since additional funding had been
secured for the project, the turf parking areas were built out so Four Mounds Center
would have additional parking capacity. Additionally, drain tile for the turf areas and
conduit installed to accommodate future utility connections added to the final cost of the
project.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment
of the final contract amount of $90,143.62 to McDermott Excavating for the Four
Mounds Parking & Accessibility Improvements.
BUDGETIMPACT
The summary of project costs for the Four Mounds Parking & Accessibility
Improvements is as follows:
Description
Estimate
Award
Final
Construction Contract
$ 45,760.00
$50,443.50
$ 90,143.62
Contingency
$4,576.00
$5,044.30
0.00
Construction Administration & Inspection
$7,550.40
$8324.00
$13,521.54
Total Construction Cost
$ 57,886.40
$63,811.80
1 $103,665.16
The project funding is summarized below:
CIP No.
Fund Description
Fund
Amount
1022879
FY 22 Four Mounds Parking Imp
$ 68,665.16
1001982
Four Mounds Ecological (REAP
$35,000.00
Grant
Total Project Funding
$ 103,665.16
REQUESTED ACTION
The City Council is requested to adopt the attached resolution accepting the
improvements and authorize the final payment of the contract amount of $90,143.62 to
McDermott Excavating, for the Four Mounds Parking & Accessibility Improvements.
Prepared By: Jon Dienst, P.E.
cc: Marie Ware, Leisure Services Manager
Steve Fehsal, Park Division Manager
Jenny Larson, Finance and Budget Director
Adam Decker, Engineering Technician
Prepared by: Jon Dienst City of Dubuque Engineering 50 W. IP Street Dubuque IA 52001 (563)589-4270
Return to: Adreinne N. Breitbelder, City Clerk, 50W 13°i Street, Dubuque, IA 52001 (563)589-4100
RESOLUTION NO. 332-22
ACCEPTING THE FOUR MOUNDS PARKING & ACCESSIBILITY IMPROVEMENTS
AND AUTHORIZING THE PAYMENT TO THE CONTRACTOR
WHEREAS, the public improvement contract for the Four Mounds Parking &
Accessibility Improvements (the Project) has been completed by the Contractor,
McDermott Excavating, (Contractor), the City Engineer has examined the work and
recommends that the Project be accepted; and
WHEREAS, the final contract amount for the Project is $90,143.62; and
WHEREAS, the Contractor has previously been paid $85,636.44, leaving a
balance of $4,507.18; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved, and the
Project is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of $4,507.18 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa Code
chapter 26.13.
Passed, approved, and adopted this 17th day of October 2022.
Attest:
gALP 7
Adrienne N. Breitfelder, City Clerk
Brad M, CavarSagh, Mayor
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF FOUR MOUNDS
PARKING & ACCESSIBILITY IMPROVEMENTS
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has
inspected the Four Mounds Parking & Accessibility Improvements has been performed in
compliance with the terms of the Public Improvement Contract, and that the total cost of
the completed work is $103,665.16.
Dated this 7t" day of October 2022.
Filed in the office of the City Clerk on the
yam,
Gus Psihoyos, City Engineer
7t" day of October 2022.
Adrienne N. Breitfelder, City Clerk