Loading...
Chaplain Schmitt Island Trail Connection Project- Iowa DOT Funding AgreementCity of Dubuque City Council Meeting Consent Items # 011. Copyrighted November 7, 2022 ITEM TITLE: Chaplain Schmitt Island Trail Connection Project- Iowa DOT Funding Agreement SUMMARY: City Manager recommending City Council adopt a resolution authorizing the Mayor to execute the Iowa Department of Transportation Federal Aid Agreement for Community Project Funding / Congressionally Directed Spending (Agreement No. 23-EDP-1 02) for the Chaplain Schmitt Island Trail Connection Project. RESOLUTION Approving a Funding Agreement (23-EDP-102) with the Iowa Department of Transportation for Community Project Funding/Congressionally Directed Spending for the Chaplain Schmitt Island Trail Connection Project SUGGESTED Suggested Disposition: Receive and File; Adopt Resolution(s) DISPOSITION: ATTACHMENTS: Description Type Chaplain Schmitt Island Trail Connection Project Iowa City Manager Memo DOT Funding Agreement-MVM Memo Staff Memo Resolution Staff Memo Resolutions Funding Agreement Supporting Documentation THE C DUj!BQTE Masterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Chaplain Schmitt Island Trail Connection Project Iowa DOT Funding Agreement No. 23-EDP-102 DATE: October 31, 2022 Dubuque WAWca 914 ii 2007-2012.2013 2017*2019 City Engineer Gus Psihoyos is recommending City Council adopt a resolution authorizing the Mayor to execute the Iowa Department of Transportation Federal Aid Agreement for Community Project Funding / Congressionally Directed Spending (Agreement No. 23-EDP-102) for the Chaplain Schmitt Island Trail Connection Project. I concur with the recommendation and respectfully request Mayor and City Council approval. Micl4ael C. Van Milligen MCVM:sv Attachment cc: Crenna Brumwell, City Attorney Cori Burbach, Assistant City Manager Teri Goodmann, Director of Strategic Partnerships Gus Psihoyos, City Engineer Jon Dienst, Civil Engineer II Alex Dixon, President and Chief Executive Officer Dubuque Racing Association Kevin Lynch, Board Chair - Dubuque Racing Association THE CITY OF DUB E Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer DATE: October 20, 2022 SUBJECT: Chaplain Schmitt Island Trail Connection Project Iowa DOT Funding Agreement No. 23-EDP-102 Dubuque MI-Ameflu Mly 2007-2012.2013 2017*2019 INTRODUCTION The enclosed resolution authorizes the Mayor to execute the Iowa Department of Transportation (Iowa DOT) Funding Agreement for the Chaplain Schmitt Island Trail Connection. BACKGROUND The Chaplain Schmitt Island Trail Connection would provide installation of a 10-foot-wide multi -use trail along Admiral Sheehy Drive from 16t" street to the Veteran's Memorial on Chaplain Schmitt Island and would include the following elements: — Excavation to allow for the installation of the trail — Installation of base stone for the trail — Installation of a 10 foot -wide 6" thick PCC trail — Installation of retaining walls where needed due to topography to accommodate the trail. — Installation of a 6" thick trail head plaza — Installation of parking to accommodate ADA parking near the trail and trailhead — Restoration of disturbed area with topsoil and seed. As a result of going through the federal aid process, engineering costs and construction costs are expected to increase. This increase in construction costs is due to federal auditing requirements, required paperwork and Davis -Bacon wages. The higher engineering costs are due to the increased workload to provide federal aid plans, administer the project and the auditing process afterwards. DISCUSSION The attached funding agreement will allow the City of Dubuque to use $615,000 in Community Project Funding earmarked by US Congresswoman Ashley Hinson. The project construction documents will follow the Iowa DOT Standard Specifications. The project will follow the elements of the improvements as part of the Veteran's Memorial on Chaplain Schmitt Island. Engineering staff are coordinating with Leisure Services, DRA staff and Ryan Peterson with RDG on the design of the trail and trailhead. Engineering staff will do all construction document development, survey and inspection. The estimate for the costs includes the trail, trailhead, parking improvement costs, retaining wall costs, engineering costs and contingency costs. These costs are estimated as follows: Items Total Costs Grant Applied Net Costs Chaplain Schmitt Trail $740,000 $592,000 $148,000 Contingency $70,000 23,000 $47,000 Engineering $80,000 0.00 $80,000 Total $890,000 $615,000 $275,000 The City's portion of funds in the amount of $275,000 is currently budgeted in FY 2022 Schmitt Island Connector Trail funds. SCHEDULE Due to the federal funding, the project will need to be bid and let through the Iowa DOT in Ames. We anticipate the bid letting would occur in June of 2023 based on the project development critical paths for the Iowa DOT. Construction of the trail and trailhead would occur in the summer of 2023. RECOMMENDATION I recommend that the Mayor be authorized to execute the Iowa Department of Transportation Federal Aid Agreement for Community Project Funding / Congressionally Directed Spending (Agreement No. 23-EDP-102) for the Chaplain Schmitt Island Trail Connection Project. Prepared By: Jon Dienst, P.E. Cc: Jenny Larson, Director of Finance and Budget Bob Schiesl, Assistant City Engineer Steve Brown, Project Manager Marie Ware, Leisure Services Manager Prepared by Jon Dienst City of Dubuque 50 W. 1 V Street Dubuque IA 52001 (563) 5894270 Return to Adrienne Breitfelder, City Clerk, City of Dubuque, 50 W. 13th Street, Dubuque, IA 52001 (563) 589-4100 RESOLUTION NO. 346-22 RESOLUTION APPROVING A FUNDING AGREEMENT (23-EDP-102) WITH THE IOWA DEPARTMENT OF TRANSPORTATION FOR COMMUNITY PROJECT FUNDING/CONGRESSIONALLY DIRECTED SPENDING FOR THE CHAPLAIN SCHMITT ISLAND TRAIL CONNECTION PROJECT Whereas, the City of Dubuque desires to proceed with the Chaplain Schmitt Island Connector Trail Project; and Whereas, the trail will extend from near 16th Street along Admiral Sheehy Drive to the Chaplain Schmitt Veteran's Memorial and include a trailhead with ADA parking; and Whereas, Chaplain Schmitt Island Connector Trail Project will involve the construction of a 10-foot-wide paved multi -use trail. The project is planned to be constructed in 2023 and will incorporate the alignment and design of the trailhead plaza RDG developed as an alternate in the Chaplain Schmitt Veterans Memorial; and Whereas, the Iowa Department of Transportation (Iowa DOT) has authorized the use of federal funds for eligible costs for the Chaplain Schmitt Island Connector Trail Project. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That the Mayor be authorized and directed to execute the Iowa DOT Transportation Federal -Aid Agreement for a Congressionally Directed Funding Project Agreement (23-EDP-102) between the City of Dubuque and the Iowa Department of Transportation be hereby approved for the Chaplain Schmitt Island Connector Trail Project: along Admiral Sheehy Drive from near 16th street to the Chaplain Schmitt Veterans Memorial. Passed, approved, and adopted this 7th day of November 2022. 111161:� .. Attest: % Adrienne N. Breitfelder, City Clerk October 2022 IOWA DEPARTMENT OF TRANSPORTATION Federal -Aid Agreement for a Congressionally Directed Funding Project Subrecipient: City of Dubuque Subrecipient Unique Entity Identifier: TLJMHPVMMUD3 Project Number(s): EDP-2100(704)--7Y-31 Iowa DOT Agreement Number: 23-EDP-102 This agreement, made as of the date of the last party's signature below, is between the city of Dubuque (hereinafter referred to as Subrecipient) and the Iowa Department of Transportation, the federal pass - through entity (hereinafter referred to as the Department). Iowa Code Sections 306A.7 and 307.44 provide for the Subrecipient and the Department to enter into agreements with each other for the purpose of financing transportation improvement projects in Iowa with federal funds. Federal regulations require federal funds to be administered by the Department. The federal -aid highway funds included in this agreement are jointly implemented by the Federal Highway Administration (FHWA) and the Department. The United States Congress has provided Federal funding for the project described below from Division L of the Consolidated Appropriations Act, 2022, as specified in the table entitled "Community Project Funding / Congressionally Directed Spending" included in the explanatory statement that accompanied this Act. Pursuant to the terms of this agreement, applicable statutes, and administrative rules, the Department agrees to provide the funding named above to the Subrecipient for the authorized and approved costs for eligible items associated with the project. Under this agreement, the parties further agree as follows: 1. The Subrecipient shall be responsible for carrying out the provisions of this agreement. 2. All notices required under this agreement shall be made in writing to the appropriate contact person. The Department's contact person shall be Troy Schroeder, Systems Planning Bureau, 800 Lincoln Way, Ames, Iowa 50010, 515-239-1861. The Subrecipient's contact person shall be Jon Dienst, City of Dubuque, 50 W 13t" Street, Dubuque, Iowa 52001, 563-589-4270. 3. The Subrecipient shall be responsible for the development and completion of the following described project: Chaplain Schmitt Island Trail Connection 4. Division L of the Consolidated Appropriations Act, 2022, as specified in the table entitled "Community Project Funding / Congressionally Directed Spending," set a total upper limit of $615,000 for this project (Demo I.D. IA252). The Subrecipient shall receive reimbursement for costs of authorized and approved eligible project activities. The portion of the project costs reimbursed October 2022 with these funds shall be limited to a maximum of either 80% of eligible costs (other than those costs reimbursed with other federal funds) or the total amount allocated, whichever is less. 5. Eligible project costs in excess of the amount reimbursed by the Department above will be considered the local contribution and may include cash, non -cash or approved state fund contributions, subject to Department approval. The local contribution must equal a minimum of 20 percent of eligible project costs. The subrecipient shall certify to the Department the value of any non -cash contribution to the project prior to it being incurred and in accordance with the procedures outlined in the applicable Instructional Memorandum to Local Public Agencies (I.M.$). The Department retains the sole authority to determine the eligibility and value of the Subrecipient's non -cash contribution for the purposes of this agreement. If the Subrecipient's total cash and non - cash contribution is determined by the Department to be less than that required by this agreement, the Subrecipient shall increase its cash contribution or the grant amount associated with this project shall be reduced accordingly. 6. The Subrecipient must have let the contract by September 30, 2025. If the Subrecipient does not do this, they will be in default for which the Department can revoke funding commitments. 7. All claims for reimbursement shall be submitted by August 1, 2030, or the amount not yet reimbursed by the Department will be deobligated by September 30, 2030. 8. If the Subrecipient fails to perform any obligation under this agreement, the Department shall have the right, after first giving thirty (30) days written notice to the Subrecipient by certified mail return receipt requested, to declare any part or all of this agreement in default. The Subrecipient shall have thirty (30) days from date of mailing of the notice to cure the default. If the Recipient cures the default, the Subrecipient shall notify Department no later than five (5) days after cure or before the end of said thirty (30) day period given to cure the default. The Department may thereafter determine whether the default has, in fact, been cured, or whether the Subrecipient remains in default. 9. This agreement maybe declared to be in default by the Department if the Department determines that the Subrecipient's application for funding contained inaccuracies, omissions, errors or misrepresentations; or if the Department determines that the project is not developed as described in the application and according to the requirements of this agreement. 10. In the event a default is not cured the Department may do any of the following: a) revoke funding commitments of funds loaned or granted by this agreement; b) seek repayment of funds loaned or granted by this agreement; or c) revoke funding commitments of funds loaned or granted by this agreement and also seek repayment of funds loaned or granted by this agreement. By signing this agreement the Subrecipient agrees to repay said funding if they are found to be in default. Repayment methods may include cash repayment, installment repayments with negotiable interest rates, or other methods as approved by the Department. 11. The Subrecipient shall comply with Exhibit 1, General Agreement Provisions for use of Federal Highway Funds on Non -primary Highways, which is attached hereto and by this reference is incorporated into this agreement. October 2022 12. The Subrecipient shall maintain, or cause to be maintained for the intended public use, the improvement for twenty (20) years from the completion date in a manner acceptable to the Department. 13. This agreement is not assignable without the prior written consent of the Department. 14. If any part of this agreement is found to be void and unenforceable, the remaining provisions of this agreement shall remain in effect. 15. It is the intent of both parties that no third -party beneficiaries be created by this agreement. 16. This agreement and the attached exhibit constitute the entire agreement between the Department and the Subrecipient concerning this project. Representations made before the signing of this agreement are not binding, and neither party has relied upon conflicting representations in entering into this agreement. Any change or alteration to the terms of this agreement shall be made in the form of an addendum to this agreement. The addendum shall become effective only upon written approval of the Department and the Subrecipient. October 2022 IN WITNESS WHEREOF, each of the parties hereto has executed this agreement as of the date shown opposite its signature below. SUBRECIPIENT: City of Dubuque BY: Date November 8 aoa Title: I ' lava!' CERTIFICATION I, Adrienne Bre i Q I der certify that I am the Clerk of the city, and that (Name of City Clerk) P rad Cavanagh who signed said Agreement for and on behalf of (Name of Mayor/Signer Above) the city was duly authorized to execute the same by virtue of a formal resolution duly passed and adopted by the city, on the day of_ NrJyem6er aoaa /" Signed: ,922 AI City Clerk of Dubuque, Iowa. IOWA DEPARTMENT OF TRANSPORTATION Transportation Development Division 800 Lincoln Way, Ames, Iowa 50010 Tel. 515-239-1664 as Craig Markley Director Systems Planning Bureau October 2022 EXHIBIT 1 General Agreement Provisions for use of Federal Highway Funds on Non -primary Projects Unless otherwise specified in this agreement, the Subrecipient shall be responsible for the following: 1. General Requirements. a. The Subrecipient shall take the necessary actions to comply with applicable state and federal laws and regulations. To assist the Subrecipient, the Department has provided guidance in the Federal -aid Project Development Guide (Guide) and the Instructional Memorandums to Local Public Agencies (I.M.$) that are referenced by the Guide. Both are available on-line at: https:Hiowadot.gov/local_systems/im/lpa-ims. The Subrecipient shall follow the applicable procedures and guidelines contained in the Guide and I.M.s in effect at the time project activities are conducted. b. In accordance with Title VI of the Civil Rights Act of 1964 and associated subsequent nondiscrimination laws, regulations, and executive orders, the Subrecipient shall not discriminate against any person on the basis of race, color, national origin, sex, age, or disability. In accordance with Iowa Code Chapter 216, the Subrecipient shall not discriminate against any person on the basis of race, color, creed, age, sex, sexual orientation, gender identity, national origin, religion, pregnancy, or disability. The Subrecipient agrees to comply with the requirements outlined in I.M. 1.070, Title VI and Nondiscrimination Requirements which includes the requirement to provide a copy of the Subrecipient's Title VI Plan or Agreement and Standard DOT Title VI Assurances to the Department. c. The Subrecipient shall comply with the requirements of Title II of the Americans with Disabilities Act of 1990 (ADA), Section 504 of the Rehabilitation Act of 1973 (Section 504), the associated Code of Federal Regulations (CFR) that implement these laws, and the guidance provided in I.M. 1.080, ADA Requirements. When bicycle and/or pedestrian facilities are constructed, reconstructed, or altered, the Subrecipient shall make such facilities compliant with the ADA and Section 504, which includes following the requirements set forth in Chapter 12A for sidewalks and Chapter 12B for Bicycle Facilities of the Iowa DOT Design Manual. d. To the extent allowable by law, the Subrecipient agrees to indemnify, defend, and hold the Department harmless from any claim, action or liability arising out of the design, construction, maintenance, placement of traffic control devices, inspection, or use of this project. This agreement to indemnify, defend, and hold harmless applies to all aspects of the Department's application review and approval process, plan and construction reviews, and funding participation. As required by 2 CFR 200.501 "Audit Requirements," a non-federal entity expending $750,000 or more in federal awards in a year shall have a single or program -specific audit conducted for that year in accordance with the provision of that part. Auditee responsibilities are addressed in Subpart F of 2 CFR 200. The federal funds provided by this agreement shall be reported on the appropriate Schedule of Expenditures of Federal Awards (SEFA) using the Catalog of Federal Domestic Assistance (CFDA) number and title as shown in this agreement. If the Subrecipient will October 2022 pay initial project costs and request reimbursement from the Department, the Subrecipient shall report this project on its SEFA. If the Department will pay initial project costs and then credit those accounts from which initial costs were paid, the Department will report this project on its SEFA. In this case, the Subrecipient shall not report this project on its SEFA. f. The Subrecipient shall supply the Department with all information required by the Federal Funding Accountability and Transparency Act of 2006 and 2 CFR Part 170. g. The Subrecipient shall comply with the following Disadvantaged Business Enterprise (DBE) requirements: i. The Subrecipient shall not discriminate on the basis of race, color, national origin, or sex in the award and performance of any Department -assisted contract or in the administration of its DBE program or the requirements of 49 CFR Part 26. The Subrecipient shall take all necessary and reasonable steps under 49 CFR Part 26 to ensure nondiscrimination in the award and administration of Department -assisted contracts. ii. The Subrecipient shall comply with the requirements of I.M. 5.010, DBE Guidelines. iii. The Department's DBE program, as required by 49 CFR Part 26 and as approved by the Federal Highway Administration (FHWA), is incorporated by reference in this agreement. Implementation of this program is a legal obligation and failure to carry out its terms shall be treated as a violation of this agreement. Upon notification to the Subrecipient of its failure to carry out its approved program, the Department may impose sanctions as provided for under Part 26 and may, in appropriate cases, refer the matter for enforcement under 18 U.S.C. 1001 and the Program Fraud Civil Remedies Act of 1986 (31 U.S.C. 3801 et seq.). Termination of funds. Notwithstanding anything in this agreement to the contrary, and subject to the limitations set forth below, the Department shall have the right to terminate this agreement without penalty and without any advance notice as a result of any of the following: 1) The federal government, legislature or governor fail in the sole opinion of the Department to appropriate funds sufficient to allow the Department to either meet its obligations under this agreement or to operate as required and to fulfill its obligations under this agreement; or 2) If funds are de - appropriated, reduced, not allocated, or receipt of funds is delayed, or if any funds or revenues needed by the Department to make any payment hereunder are insufficient or unavailable for any other reason as determined by the Department in its sole discretion; or 3) If the Department's authorization to conduct its business or engage in activities or operations related to the subject matter of this agreement is withdrawn or materially altered or modified. The Department shall provide the Subrecipient with written notice of termination pursuant to this section. October 2022 2. Programming and Federal Authorization. a. The Subrecipient shall be responsible for including the project in the appropriate Regional Planning Affiliation (RPA) or Metropolitan Planning Organization (MPO) Transportation Improvement Program (TIP). The Subrecipient shall also ensure that the appropriate RPA or MPO, through their TIP submittal to the Department, includes the project in the Statewide Transportation Improvement Program (STIP). If the project is not included in the appropriate fiscal year of the STIP, federal funds cannot be authorized. b. Before beginning any work for which federal funding reimbursement will be requested, the Subrecipient shall contact the Department to obtain the procedures necessary to secure FHWA authorization. The Subrecipient shall submit a written request for FHWA authorization to the Department. After reviewing the Subrecipient's request, the Department will forward the request to the FHWA for authorization and obligation of federal funds. The Department will notify the Subrecipient when FHWA authorization is obtained. The cost of work performed prior to FHWA authorization will not be reimbursed with federal funds. c. Upon receiving FHWA authorization, the Subrecipient must show federal aid funding activity to receive the programmed amount authorized for the project. If there is no funding activity for nine or more months after the previous activity, the remaining unused programmed amount will be de -obligated from the project and there will be no further federal aid reimbursement issued for the project. If the Subrecipient knows in advance that funding activity will not occur for the nine months, the Contract Administrator needs to be notified to determine if programming of funds can be adjusted or other options can be explored. d. Upon receipt of Federal Highway Administration (FHWA) authorization a Federal Award Identification Number (FAIN) will be assigned to this project by the FHWA based on a methodology that incorporates identifying information about the federal award such as the federal funding program code and the federal project number. This FAIN will be used to identify this project and award on the federal government's listing of financial assistance awards consistent with the Federal Funding Accountability and Transparency Act of 2006 (FFATA) at usaspending.gov. e. A period of performance for this federal funding award will be established at the time of FHWA authorization. The start date of the period of performance will be the FHWA authorization date. The project end date (PED) will be determined according to the methodology in I.M. 1.200, Federal Funds Management. Costs incurred before the start date or after the PED of the period of performance will not be eligible for reimbursement. 3. Federal Participation in Work Performed by Subrecipient Employees. a. If federal reimbursement will be requested for engineering, construction inspection, right-of-way acquisition or other services provided by employees of the Subrecipient, the Subrecipient shall follow the procedures in I.M. 3.330, Federal -aid Participation in In -House Services. October 2022 b. If federal reimbursement will be requested for construction performed by employees of the Subrecipient, the Subrecipient shall follow the procedures in I.M. 6.010, Federal -aid Construction by Local Agency Forces. c. If the Subrecipient desires to claim indirect costs associated with work performed by its employees, the Subrecipient shall prepare and submit to the Department an indirect cost rate proposal and related documentation in accordance with the requirements of 2 CFR 200. Before incurring any indirect costs, such indirect cost rate proposal shall be certified by the FHWA or the federal agency providing the largest amount of federal funds to the Subrecipient. If approved, the approved indirect cost rate shall be incorporated by means of an addendum to this agreement. 4. Design and Consultant Services a. The Subrecipient shall be responsible for the design of the project, including all necessary plans, specifications, and estimates (PS&E). The project shall be designed in accordance with the design guidelines provided or referenced by the Department in the Guide and applicable I.M.s. b. If the Subrecipient requests federal funds for consultant services, the Subrecipient and the Consultant shall prepare a contract for consultant services in accordance with 23 CFR Part 172. These regulations require a qualifications -based selection process. The Subrecipient shall follow the procedures for selecting and using consultants outlined in I.M. 3.310, Federal -aid Participation in Consultant Costs. c. If Preliminary Engineering (PE) work is federally funded, and if right-of-way acquisition or actual construction of the project is not started by the close of the tenth fiscal year following the fiscal year in which the federal funds were authorized, the Subrecipient shall repay to the Department the amount of federal funds reimbursed to the Subrecipient for such PE work. PE includes work that is part of the development of the PS&E for a construction project. This includes environmental studies and documents, preliminary design, and final design up through and including the preparation of bidding documents. PE does not include planning or other activities that are not intended to lead to a construction project. Examples include planning, conceptual, or feasibility studies. 5. Environmental Requirements and other Agreements or Permits. a. The Subrecipient shall take the appropriate actions and prepare the necessary documents to fulfill the FHWA requirements for project environmental studies including historical/cultural reviews and location approval. The Subrecipient shall complete any mitigation agreed upon in the FHWA approval document. These procedures are set forth in I.M. 3.020, Concept Statement Instructions; 4.020, NEPA Process; 4.110, Threatened and Endangered Species; and 4.120, Cultural Resource Regulations. b. If farmland is to be acquired, whether for use as project right-of-way or permanent easement, the Subrecipient shall follow the procedures in I.M. 4.170, Farmland Protection Policy Act. October 2022 c. The Subrecipient shall obtain project permits and approvals, when necessary, from the Iowa Department of Cultural Affairs (State Historical Society of Iowa; State Historic Preservation Officer), Iowa Department of Natural Resources, U.S. Coast Guard, U.S. Army Corps of Engineers, the Department, or other agencies as required. The Subrecipient shall follow the procedures in I.M. 4.1301 404 Permit Process; 4.140, Storm Water Permits; 4.150, Iowa DNR Floodplain Permits and Regulations; 4.160, Asbestos Inspection, Removal and Notification Requirements; and 4.190, Highway Improvements in the Vicinity of Airports or Heliports. In all contracts entered into by the Subrecipient, and all subcontracts, in connection with this project that exceed $100,000, the Subrecipient shall comply with the requirements of Section 114 of the Clean Air Act and Section 308 of the Federal Water Pollution Control Act, and all their regulations and guidelines. In such contracts, the Subrecipient shall stipulate that any facility to be utilized in performance of or to benefit from this agreement is not listed on the Environmental Protection Agency (EPA) List of Violating Facilities or is under consideration to be listed. 6. Right -of -Way, Railroads and Utilities. a. The Subrecipient shall acquire the project right-of-way, whether by lease, easement, or fee title, and shall provide relocation assistance benefits and payments in accordance with the procedures set forth in I.M. 3.600, Right -of -Way Acquisition, and the Department's Right of Way Bureau Local Public Agency Manual. The Subrecipient shall contact the Department for assistance, as necessary, to ensure compliance with the required procedures, even if no federal funds are used for right-of-way activities. The Subrecipient shall obtain environmental concurrence before acquiring any needed right-of-way. With prior approval, hardship and protective buying is possible. If the Subrecipient requests federal funding for right-of-way acquisition, the Subrecipient shall also obtain FHWA authorization before purchasing any needed right-of-way. b. If the project right-of-way is federally funded and if the actual construction is not undertaken by the close of the twentieth fiscal year following the fiscal year in which the federal funds were authorized, the Subrecipient shall repay the amount of federal funds reimbursed for right-of-way costs to the Department. c. If a railroad crossing or railroad tracks are within or adjacent to the project limits, the Subrecipient shall obtain agreements, easements, or permits as needed from the railroad. The Subrecipient shall follow the procedures in I.M. 3.670, Work on Railroad Right -of -Way, and I.M. 3.680, Federal -aid Projects Involving Railroads. d. The Subrecipient shall comply with the Policy for Accommodating Utilities on City and County Federal -aid Highway Right of Way for projects on non -primary federal -aid highways. For projects connecting to or involving some work inside the right-of-way for a primary highway, the Subrecipient shall follow the Department's Policy for Accommodating Utilities on Primary Road System. Certain utility relocation, alteration, adjustment, or removal costs to the Subrecipient for the project may be eligible for federal funding reimbursement. The Subrecipient should also use the procedures outlined in I.M. 3.640, Utility Accommodation and Coordination, as a guide to coordinating with utilities. October 2022 e. If the Subrecipient desires federal reimbursement for utility costs, it shall submit a request for FHWA authorization prior to beginning any utility relocation work, in accordance with the procedures outlined in I.M. 3.650, Federal -aid Participation in Utility Relocations. 7. Construction Contract Procurement. The following provisions apply only to projects involving physical construction or improvements to transportation facilities: a. The project plans, specifications, and cost estimate (PS&E) shall be prepared and certified by a professional engineer, architect, or landscape architect, as applicable, licensed in the State of Iowa. b. For projects let through the Department, the Subrecipient shall be responsible for the following: Prepare and submit the PS&E and other contract documents to the Department for review and approval in accordance with I.M. 3.700, Check and Final Plans and I.M. 3.500, Bridge or Culvert Plans, as applicable. ii. The contract documents shall use the Department's Standard Specifications for Highway and Bridge Construction. Prior to their use in the PS&E, specifications developed by the Subrecipient for individual construction items shall be approved by the Department. iii. Follow the procedures in I.M. 5.030, Iowa DOT Letting Process, to analyze the bids received, make a decision to either award a contract to the lowest responsive bidder or reject all bids, and if a contract is awarded, execute the contract documents in Doc Express. c. For projects that are let locally by the Subrecipient, the Subrecipient shall follow the procedures in I.M. 5.120, Local Letting Process, Federal -aid. The Subrecipient shall forward a completed Project Development Certification (Form 730002) to the Department in accordance with I.M. 5.050, Project Development Certification Instructions. The project shall not receive FHWA authorization for construction or be advertised for bids until after the Department has reviewed and approved the Project Development Certification. If the Subrecipient is a city, the Subrecipient shall comply with the public hearing requirements of the Iowa Code section 26.12. The Subrecipient shall not provide the contractor with notice to proceed until after receiving notice in Doc Express that the Department has concurred in the contract award. 8. Construction. a. A full-time employee of the Subrecipient shall serve as the person in responsible charge of the construction project. For cities that do not have any full-time employees, the mayor or city clerk will serve as the person in responsible charge, with assistance from the Department. 10 October 2022 b. Traffic control devices, signing, or pavement markings installed within the limits of this project shall conform to the "Manual on Uniform Traffic Control Devices for Streets and Highways" per 761 IAC Chapter 130. The safety of the general public shall be assured through the use of proper protective measures and devices such as fences, barricades, signs, flood lighting, and warning lights as necessary. c. For projects let through the Department, the project shall be constructed under the Department's Standard Specifications for Highway and Bridge Construction and the Subrecipient shall comply with the procedures and responsibilities for materials testing according to the Department's Materials I.M.s applicable to the letting. Available on-line at: https://www.iowadot.gov/erl/index.html. d. For projects let locally, the Subrecipient shall provide materials testing and certifications as required by the approved specifications. e. If the Department provides any materials testing services to the Subrecipient, the Department will bill the Subrecipient for such testing services according to its normal policy as per Materials I.M. 103, Inspection Services Provided to Counties, Cities, and Other State Agencies. f. The Subrecipient shall follow the procedures in I.M. 6.000, Construction Inspection, and the Department's Construction Manual, as applicable, for conducting construction inspection activities. 9. Reimbursements. a. After costs have been incurred, the Subrecipient shall submit to the Department periodic itemized claims for reimbursement for eligible project costs. Requests for reimbursement shall be made at least once every six months but not more than bi-weekly. b. To ensure proper accounting of costs, reimbursement requests for costs incurred prior to June 30 shall be submitted to the Department by August 1. c. Reimbursement claims shall include a certification that all eligible project costs, for which reimbursement is requested, have been reviewed by an official or governing board of the Subrecipient, are reasonable and proper, have been paid in full, and were completed in substantial compliance with the terms of this agreement. d. Reimbursement claims shall be submitted on forms identified by the Department along with all required supporting documentation. The Department will reimburse the Subrecipient for properly documented and certified claims for eligible project costs. The Department may withhold up to 5% of the federal share of construction costs or 5% of the total federal funds available for the project, whichever is less. Reimbursement will be made either by state warrant or by crediting other accounts from which payment was initially made. If, upon final audit or review, the Department determines the Subrecipient has been overpaid, the Subrecipient shall reimburse the overpaid amount to the Department. After the final audit or review is complete 11 October 2022 and after the Subrecipient has provided all required paperwork, the Department will release the federal funds withheld. e. The total funds collected by the Subrecipient for this project shall not exceed the total project costs. The total funds collected shall include any federal or state funds received, any special assessments made by the Subrecipient (exclusive of any associated interest or penalties) pursuant to Iowa Code Chapter 384 (cities) or Chapter 311 (counties), proceeds from the sale of excess right-of-way, and any other revenues generated by the project. The total project costs shall include all costs that can be directly attributed to the project. In the event that the total funds collected by the Subrecipient do exceed the total project costs, the Subrecipient shall either: i. in the case of special assessments, refund to the assessed property owners the excess special assessments collected (including interest and penalties associated with the amount of the excess), or ii. Refund to the Department all funds collected in excess of the total project costs (including interest and penalties associated with the amount of the excess) within 60 days of the receipt of any excess funds. In return, the Department will either credit reimbursement billings to the FHWA or credit the appropriate state fund account in the amount of refunds received from the Subrecipient. 10. Project Close-out. a. Within 30 days of completion of construction or other activities authorized by this agreement, the Subrecipient shall provide written notification to the Department and request a final audit, in accordance with the procedures in I.M. 6.110, Final Review, Audit, and Close-out Procedures for Federal -aid, Federal -aid Swap, and Farm -to -Market Projects. Failure to comply with the procedures will result in loss of federal funds remaining to be reimbursed and the repayment of funds already reimbursed. The Subrecipient may be suspended from receiving federal funds on future projects. b. For construction projects, the Subrecipient shall provide a certification by a professional engineer, architect, or landscape architect as applicable, licensed in the State of Iowa, indicating the construction was completed in substantial compliance with the project plans and specifications. c. Final reimbursement of federal funds shall be made only after the Department accepts the project as complete. d. The Subrecipient shall maintain all books, documents, papers, accounting records, reports, and other evidence pertaining to costs incurred for the project. The Subrecipient shall also make these materials available at all reasonable times for inspection by the Department, FHWA, or any authorized representatives of the federal government. Copies of these materials shall be furnished by the Subrecipient if requested. Such documents shall be retained for at least 3 years from the date of FHWA approval of the final closure document. Upon receipt of FHWA approval 12 October 2022 of the final closure document, the Department will notify the Subrecipient of the record retention date. e. The Subrecipient shall maintain, or cause to be maintained, the completed improvement in a manner acceptable to the Department and the FHWA. 13