Flora Pool Filter Tanks and Recirculation Pump Replacement — Award Public Improvement ContractCopyrighted January 3, 2023 City of Dubuque Consent Items # 015. City Council Meeting ITEM TITLE: Flora Pool Filter Tanks and Recirculation Pump Replacement —Award Public Improvement Contract SUMMARY: City Manager recommending City Council adopt a resolution awarding the public improvement contract for the Flora Pool Filter Tank and Recirculation Pump Replacement Project to Carrico Aquatic Resources in the amount of $227,400. RESOLUTION Awarding Public Improvement Construction Contract for the Flora Pool Filter Tanks and Recirculation Pump Replacement Project SUGGESTED Suggested Disposition: Receive and File; Adopt Resolution(s) DISPOSITION: ATTACHMENTS: Description Type Flora Pool Filter Tank and Pump Replacement Project City Manager Memo Award Public Improvement Contract-MVM Memo Staff Memo Resolution Staff Memo Resolutions THE C Dubuque DUj!BQTE WAWca 914 Masterpiece on the Mississippi YP pp aoo�•o 13 z0i7*20*�oi9 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Flora Pool Filter Tanks and Recirculation Pump Replacement — Award Public Improvement Contract DATE: December 21, 2022 Leisure Services Manager Marie Ware is recommending City Council adopt a resolution awarding the public improvement contract for the Flora Pool Filter Tank and Recirculation Pump Replacement Project to Carrico Aquatic Resources in the amount of $227,400. I concur with the recommendation and respectfully request Mayor and City Council approval. v Mic ael C. Van Milligen MCVM:sv Attachment cc: Crenna Brumwell, City Attorney Cori Burbach, Assistant City Manager Marie Ware, Leisure Services Manager Dan Kroger, Recreation Division Manager THE CITY OF DUB Masterpiece are the Mississippi TO: Michael C. Van Milligen, City Manager FROM: Marie L. Ware, Leisure Services Manager Dubuque �ilrrio Gq� I�. 2aa7.2012.2013 017*2019 SUBJECT: Flora Pool Filter Tanks and Recirculation Pump Replacement — Award Public Improvement Contract DATE: December 19, 2022 I' k I:to] 111101lei Z The purpose of this memo it to award the public improvement construction contract for the replacement of the main pool filter tanks and circulation pump at Flora Pool. BACKGROUND Both Flora and Sutton pools have a series of cast iron filter tanks that are original to their renovations back in 1990 (Flora) and 1991 (Sutton). For over 5 years, these tanks at both locations have begun to fail in ways that are becoming more difficult and costly to repair. Just this past season, after spending over $10,000 in repairs in the hope of getting a couple more years out of the tanks, one of the tanks at Flora failed during the last week of the season. In that same week, the main circulation pump also failed at Flora pool. Staff had to scramble in order to just do enough to keep the systems working through the last week. DISCUSSION Due to the condition of the filter tanks at both pools and the circulation pump at Flora, we can no longer rely on their ability to function efficiently or at all through an entire season. For years we have made preseason repairs to try and extend their life as well as dealt with continues issues during the seasons. Based on the current condition of the filters and pump at Flora, it is estimated to cost around $20,000 to $30,000 to attempt repairs that could extend their life another year. Having the pool operational for the season is critical. Each pool is unique in their construction design and requirements based on water volume and location on the site. Plans and bid specs were developed separately for both Sutton and Flora Pools. The project to replace the filter tanks at Sutton pool was previously bid and awarded to Carrico Aquatics Resources. Due to the addition of the recirculation pump and the amount of tanks needed for Flora Pool, the estimated cost for this project at Flora Pool was much higher than Sutton Pool. BID RESULTS The City of Dubuque received the following sealed bids for the for the Flora Pool Filter Tank and Recirculation Pump Replacement project on December 9, 2022: Contractor Bid Results Carrico Aquatic Resources $227,400 Portzen Construction $255,000 The low bid from Carrico Aquatic Resources is $12,000 higher then projected. However, there is sufficient CIP funding within the current FY23 Pool CIP's for cover the project. 0=1401►Y,ILY,l=1zl17_AI[a]►I I recommend that the contract for the Flora Pool Filter Tank and Recirculation Pump Replacement be awarded to Carrico Aquatic Resources. BUDGETIMPACT There is currently $258,076 available in FY23 capital improvement funding (102-34- 0000-76-750-3470-00-02-67500, 102-30-0000-76-750-3070-00-02-67990, 102-34- 0000-76-750-3470-00-02-67990) dedicated to pool projects. ACTION REQUESTED I respectfully request that the City Council award the public improvement contract for the Flora Pool Filter Tank and Recirculation Pump Replacement Project to Carrico Aquatic Resources in the amount of $227,400 through adoption of the attached resolution. Memo prepared by: Dan Kroger, Recreation Division Manager cc: Jenny Larson, Director of Finance & Budget Janna Beau, Recreation Supervisor Return to Adrienne N. Breitfelder, City Clerk, 50 W. 13th St., Dubuque, IA 52001, (563) 589-4100 RESOLUTION NO. 8-23 AWARDING PUBLIC IMPROVEMENT CONSTRUCTION CONTRACT FORTHE FLORA POOL FILTER TANKS AND RECIRCULATION PUMP REPLACEMENT PROJECT WHEREAS, Flora Park pool is an aging popular community amenity in need of repair to ensure availability to the community for years to come; and WHEREAS, the residents of the City of Dubuque will benefit from this operational improvement; and WHEREAS, sealed proposals have been submitted by contractors for the Project pursuant to Resolution No. 376-22 and Notice to Bidders published on the City of Dubuque, Iowa website on the 5th day of December 2022; and WHEREAS, said sealed proposals were opened on the 19th day of December 2022 and it has been determined that Carrico Aquatics Resources, Oelwein, IA submitted the low bid in the amount of $227,400 and is the lowest responsive, responsible bidder for the Project; and NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That the Public Improvement Construction Contract forthe Flora Pool Filter Tanks and Recirculation Pump Replacement Project is hereby awarded to Carrico Aquatic Resources and the City Manager is hereby directed to execute the Public Improvement Contract on behalf of the City of Dubuque for the project. Passed, approved, and adopted this 3rd day of January 2023. .. , .• h, Mayor Attest: Adrienne N. Breitfelder; CIVIC, City Clerk