ITEM TITLE: Acceptance of North Cascade Road Reconstruction Project
SUMMARY: City Manager recommending City Council adopt the resolution accepting
the Public Improvement Construction Contract and to authorize the
payment of the contract amount of $1,617,366.68 to Top Grade
Excavating, Inc. for the North Cascade Road Reconstruction Project,
Phase 1 from the bridge over Catfish Creek to Edval Lane, Iowa DOT
Project No. STBG-SWAP-2100 (669)--SG-31.
RESOLUTION Accepting the North Cascade Road Reconstruction
Project, Phase 1 from the bridge over Catfish Creek to Edval Lane, Iowa
DOT Project No. STBG-SWAP-2100 (669)--SG-31 and authorizing the
final payment to the contractor
SUGGESTED Suggested Disposition: Receive and File; Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
Description Type
MVM Memo City Manager Memo
Staff Memo Staff Memo
Resolution Resolutions
Engineer's Certificate of Completion Supporting Documentation
THE CITY
DUOF
B TEE
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: North Cascade Road Reconstruction Project
Phase 1 - Bridge over Catfish Creek to Edval Lane
Acceptance of Public Improvement Construction Contract
Iowa DOT Project No. STBG-SWAP-2100 (669)--SG-31
DATE: April 12, 2023
Dubuque
All -America City
IN
2007.2012.2013
2017*2019
Assistant City Engineer Robert Schiesl is recommending City Council adopt the
attached resolution to accept the Public Improvement Construction Contract and to
authorize the payment of the contract amount of $1,617,366.68 to Top Grade
Excavating, Inc. for the North Cascade Road Reconstruction Project, Phase 1 from the
bridge over Catfish Creek to Edval Lane, Iowa DOT Project No. STBG-SWAP-2100
(669)--SG-31.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Robert Schiesl, Assistant City Engineer
THE CITY OF
DUB E
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
Gus Psihoyos, City Engineer
FROM: Robert Schiesl, Assistant City Engineer
SUBJECT: North Cascade Road Reconstruction Project
Phase 1 - Bridge over Catfish Creek to Edval Lane
Acceptance of Public Improvement Construction Contract
Iowa DOT Project No. STBG-SWAP-2100 (669)--SG-31
DATE: April 11, 2023
INTRODUCTION
Dubuque
All•Merin City
2007-2012.2013
2017*2019
The enclosed resolution provides for the acceptance of the Public Improvement
Construction Contract for the North Cascade Road Reconstruction Project, Phase 1
from the bridge over Catfish Creek to Edval Lane, Iowa DOT Project No. STBG-SWAP-
2100 (669)--SG-31.
BACKGROUND
With the completion of the Southwest Arterial (US 52) and the location of the Middle
Interchange at North Cascade / English Mill Road, traffic volumes are expected to
increase on North Cascade Road. The original roadway was narrow, substandard in
design and was inadequate to accommodate future traffic and development growth.
The Timber Hyrst residential subdivision connects Creekwood Drive to North Cascade
Road between Edval Lane and the Catfish Creek bridge. The original development
agreement for this subdivision between the City of Dubuque and North Cascade Road
Developers, LLC., in addition to a pre -annexation development agreement with Gary
Valentine stipulated that the City was responsible for completing safety related
improvement to North Cascade Road.
DISCUSSION
The North Cascade Road Reconstruction improvement included the reconstruction of
North Cascade Road from the bridge over Catfish Creek to Edval Lane. The previous
24-foot rural roadway was widened to a 35-foot urban "complete street" section with 5-
foot paved shoulders / bike lanes on each side of the road. The previous curves on
North Cascade Road were substandard and were realigned to improve safety and allow
for better sight distance. The project also included grading for future sidewalk and a 10-
foot-wide bike / pedestrian shared use path. The installation of the sidewalk and shared
use path is being deferred to a future date when development occurs along the corridor
and the trail network connects to the bike / pedestrian trail along the Southwest Arterial.
Additionally, the City does not have authority to require sidewalks for the segments of
North Cascade which are within Dubuque County jurisdiction.
WATER MAIN EXTENSION
As part of the North Cascade Road Reconstruction project, the city installed a new 12-
inch water main along North Cascade to Edval Lane. The water main was originally
planned to only be extended to Creekwood Drive; however, the City received very
favorable bid prices for the construction of new water main from the Catfish Creek to
Creekwood Drive. As a result, the City issued a change order (added $160,000) and
amended the construction contract to provide for the extension of the new water main
from Creekwood to Edval Lane with available funds.
Description
Estimate
Awarded
Amended
Contract
Contract
Construction - North Cascade Road
$ 1,851,000
$ 1,324,638.24
$ 1,484,638.24
The newly installed water main now provides a critical distribution loop connection to
serve the Creekwood Drive Timber Hyrst residential subdivision and is now in a position
to be extended from Edval Lane to the Southwest Arterial corridor to support future
expansion and growth. The additional cost to extend water main to Edval Lane is
summarized below.
Description
Estimate
Award
Final
Construction - Water Main Extension
$ 145,000.00
$ 153,000.00
$ 143,023.90
(Catfish Creek to Creekwood Drive)
Construction - Water Main Extension
$ 133,045.48
(Creekwood Drive to Edval Lane)
Total Construction Cost
$ 145,000.00
$ 153,000.00
$ 276,069.38
The water main funding is summarized as follows:
Project Code
Funding Source
Amount
4281000039
North Cascade Water Main Extension
276,069.38
Total Water Main Funding
$ 776,069.38
NORTH CASCADE ROAD CONSTRUCTION
The North Cascade Road Reconstruction Project, Phase 1 from the bridge over Catfish
Creek to Edval Lane was completed by Top Grade Excavating, Inc. of Farley, Iowa in
the final contract amount of $1,617,366.68 which is an 8.9% increase from the amended
contract amount of $1,484,638.24. The added costs incurred were a result of additional
excavation needed to create a stable rock cut embankment near Miner's Lane
($159,682.96).
RECOMMENDATION
I recommend that the City Council accept the Public Improvements and authorize the
payment of the contract amount of $1,617,366.68 to Top Grade Excavating, Inc., for the
North Cascade Road Reconstruction Project, Phase 1 from the bridge over Catfish
Creek to Edval Lane.
BUDGETIMPACT
The project cost for the North Cascade Road Reconstruction Project is summarized in
the following table:
Description
Original
Estimate
Amended
Contract
Final Cost
Construction — North Cascade Road.
$ 1,851,000
$ 1,484,638.24
$ 1,617,366.68
Contingency
278,000
199,000.00
0.00
Right -of -Way Property Acquisition
129,000
129,000.00
166,903.00
Consultant Services
96,664.25
Engineering Design
213,000
153,000.00
150,718.92
Contract Admin / Construction Engineering
160,000
115,000.00
255,196.40
Total Construction Cost
$ 2,631,000
$ 2,080,638.24
$ ,,286,849.25
The final total construction cost of $2,286,849.25 is 13.1 % under the original cost
estimate of $2,631,000.
The project funding is summarized as follows:
Project Code
Funding Source
Amount
5521000024
DMATS SWAP Funding
$ 1,476,874.62
North Cascade Road Reconstruction
533,905.25
4281000039
North Cascade Water Main Extension
276,069.38
Total Project Funding
$ 2,286,849.25
The North Cascade Road Reconstruction Project was the City's first project to be
developed and constructed under the Federal Aid SWAP Policy which will use State
Primary Road funds to reimburse the City for 100% of eligible roadway construction and
property acquisition costs which eliminates the requirement for a 20% local match. All
other associated costs, such as engineering design, contract administration,
construction engineering and inspection are funded solely with City funding.
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolution to accept the Public
Improvement Construction Contract and to authorize the payment of the contract
amount of $1,617,366.68 to Top Grade Excavating, Inc. for the North Cascade Road
Reconstruction Project, Phase 1 from the bridge over Catfish Creek to Edval Lane, Iowa
DOT Project No. STBG-SWAP-2100 (669)--SG-31.
cc: Jenny Larson, Chief Financial Officer
Nathan Steffen, P.E., Civil Engineer
Chris Lester, Brant Schueller, Kerry Leppert, Water Department
Dillon Feldmann, Iowa DOT
F:\PROJECTS\North Cascade Rd Reconstruction (669)\Council & Staff Documents\Acceptance
Prepared by: Robert Schiesl, City of Dubuque Engineering, 50 W. 13tr' Street, Dubuque, IA 52001 (563)589-4270
Return to: Adreinne N. Breitfelder, City Clerk, 50W 1Y1 Street, Dubuque, IA 52001 (563)589-4100
RESOLUTION NO. 107-23
ACCEPTING THE NORTH CASCADE ROAD RECONSTRUCTION PROJECT, PHASE
1 FROM THE BRIDGE OVER CATFISH CREEK TO EDVAL LANE, IOWA DOT
PROJECT NO. STBG-SWAP-2100 (669)--SG-31 AND AUTHORIZING THE FINAL
PAYMENT TO THE CONTRACTOR
WHEREAS, the public improvement contract for the North Cascade Road
Reconstruction Project, Phase 1 from the bridge over Catfish Creek to Edval Lane, Iowa
DOT Project No. STBG-SWAP-2100 (669)--SG-31 (the Project) has been completed by
the Contractor, Top Grade Excavating, Inc. (Contractor), and the City Engineer has
examined the work and signed a certificate stating that the Project has been completed
according to the terms of the Public Improvement Contract and that the City Engineer
recommends that the Project be accepted; and
WHEREAS, the final contract amount for the Project is $1,617,366.68; and
WHEREAS, the Contractor has previously been paid $1,588,648.95, leaving a
balance of $28,717.73; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
SECTION 1. The recommendation of the City Engineer is approved, and the
Project is hereby accepted.
SECTION 2. The Director of Finance and Budget is hereby directed to pay the
balance of the retainage of $28,717.73 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa
chapter 26.13.
Passed, approved, and adopted the 17t" day of April 2023.
Attest:
Adrienne N. Breitfelder, City Clerk
Brad M. Cava n, Mayor
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE NORTH
CASCADE ROAD RECONSTRUCTION PROJECT, PHASE 1 FROM THE BRIDGE
OVER CATFISH CREEK TO EDVAL LANE, IOWA DOT PROJECT NO. STBG-
SWAP-2100(669)--SG-31
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the North Cascade Road Reconstruction Project, Phase 1 from the
bridge over Catfish Creek to Edval Lane, Iowa DOT Project No. STBG-SWAP-2100
(669)--SG-31, and that said Project has been performed in compliance with the terms of
the Public Improvement Construction Contract, and that the total cost of the completed
work is $2,286,849.25.
Dated this the 11th day of April 2023.
Gus Psihoyos, City Engineer
Filed in the office of the City Clerk on the 11th day of April 2023.
Adrienne N. Breitfelder, City Clerk