SUM MARY: City Manager recommending City Council adopt a resolution accepting
the public improvements and authorize the final payment of the contract
amount of$816,201.42 to Rink-Tec I nternational, I nc. for the Mystique
Ice Center- Rink Ice System Removal and Replacement Project.
RESOLUTIONAccepting the Mystique Ice Center- Rink Ice System
Removal and Replacement Project and authorizing the payment to the
contractor
SUGGESTED Suggested Disposition: Receive and File;Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
Description Type
MVM Memo City Manager Memo
Staff Memo Staff Memo
Resolution Resolutions
Engineer's Certificate of Completion Supporting Documentation
Dubuque
THE CITY QF �
All-Meriea Ciry
DLT B E ; . � . �
�� � �
MaSt� Z�C� aYd t�Q Mt55ZSSZ Z zoa�•zoiz•�ai3
YP pp za��*zai�
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Mystique Community Ice Center
Rink Ice System Removal and Replacement Project
Acceptance of Public Improvement Construction Contract
DATE: April 26, 2023
Assistant City Engineer Robert Schiesl is recommending City Council adopt a resolution
accepting the public improvements and authorize the final payment of the contract
amount of $816,201.42 to Rink-Tec International, Inc. for the Mystique Ice Center - Rink
Ice System Removal and Replacement Project.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
v
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Robert Schiesl, Assistant City Engineer
Jenny Larson, Chief Financial Officer
Marie Ware, Leisure Services Manager
Dubuque
THE CITY OF �
All•America Cip�
D B E � , �,:..�.
U '�I I ►
� �
Masterpiece on the Mississippi 2oi�*2oi�
TO: Michael C. Van Milligen, City Manager
Gus Psihoyos, City Engineer
FROM: Robert Schiesl, Assistant City Engineer
SUBJECT: Mystique Community Ice Center
Rink Ice System Removal and Replacement Project
Acceptance of Public Improvement Construction Contract
DATE: April 24, 2023
INTRODUCTION
The attached resolution provides for the acceptance of the public improvement
construction contract for the Mystique Ice Center - Rink Ice System Removal and
Replacement Project.
BACKGROUND
The mitigation work for the ice arena settlement remediation has been successfully
completed. The first phase of work began on June 1 st with the removal of the original
existing rink dasher boards and shielding, the rink ice system, and bleachers to allow for
the installation of a non-destructive deep foundation system under the rink area and
throughout the lower-level main floor interior finished building space. Once the settlement
and foundation system were completed, a concrete subfloor was installed and supported
on the deep foundation system. Once the concrete subfloor was in-place, a new
refrigerated ice rink concrete floor was installed which is now supported by the subfloor
slab and foundation. Once the refrigerated ice rink floor was operational, the arena
bleachers and seating were reinstalled along with installation of new dasher boards, and
the installation of new rubber sport flooring on the lower-level main floor. All this work was
successfully completed, and the Dubuque Ice Arena was reopened to the public on
November 2, 2022.
The Mystique Ice Center - Rink Ice System Removal and Replacement Project provided
for the complete removal of the original rink and ice system to allow for the installation of
a deep foundation system under the rink area. Once the settlement and foundation
system was completed (by others) and a reinforced concrete subfloor was constructed
(by others), a new rink ice system was installed. The new rink ice system included the
installation of a subfloor heating system, the installation of new coolant piping, and the
installation of a new refrigerated concrete rink floor. The rink ice system projects also
included restarting the ice plant cooling system and the installation of the ice sheet
surface.
DISCUSSION
The Mystique Ice Center - Rink Ice System Removal and Replacement Project was
completed by Rink-Tec International, Inc. of Vodnais Heights, MN in the final contract
amount of $816,201.42. This is a 13.2% increase from the original contract amount of
$720,950.00.
The increase ($95,251.42) was due to additional costs incurred during the restart of the
arena ice plant cooling system. When shutting down the ice plant system and leaving
the system site idle for 6 months while the settlement remediation work was completed,
upon Rink-Tec starting the ice system back up, mechanical issues were discovered with
the compressors. Unfortunately, due to the age of the original compressors and the
operating hours, over 50,000 hours per compressor, the startup process from an
extended idle period was demanding and stressful on the compressors and
components. As a result, of the four (4) ice system compressors, B2 was operating at
approx. 50% and A2 stopped operating on Mar 3�a
Through approved contract change orders, Rink-Tec was authorized to replace all
bearing couplers, shaft seals, procure and install two (2) new ice system compressors,
and install new compressed liquid refrigerant for the ice plant cooling system.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment
of the final contract amount of $816,201.42 to Rink-Tec International, Inc. for the
Mystique Ice Center - Rink Ice System Removal and Replacement Project.
BUDGET IMPACT
The summary of project costs for the Mystique Ice Center - Rink Ice System Removal
and Replacement Project is summarized in the following table:
Description Estimate Award Final
Construction - Rink Ice System Remove & � 650,000.00 $ 720,950.00 $ 816,201.42
Replace
Consultant Services 51,510.00 51,510.00 51,510.00
Engineering Dept. Services and Admin. 20,000.00 20,000.00 20,000.00
Total Construction Cost $ 721,510.00 $ 792,460.00 $ 887,711.42
The project funding is summarized as follows:
Project Code Fund Description Fund Amount
3449900001-304-67990 Ice Center Settling Remediation (FY23) $ 887,711.42
Total Project Funding $ 887,711.42
REQUESTED ACTION
The City Council is requested to adopt the attached resolution accepting the public
improvements and authorize the final payment of the contract amount of $816,201.42 to
Rink-Tec International, Inc. for the Mystique Ice Center - Rink Ice System Removal and
Replacement Project.
2
cc: Jenny Larson, Chief Financial Officer
Marie Ware, Leisure Services Manager
F:\PROJECTS\Mystique Community Ice Center\2022 Settlement Remediation Project\Rink Ice System Project\Council
&Staff DocumentsWcceptance
3
Prepared by: Bob Schiesl, City of Dubuque Enqineer]nq,50 W. 13th Street, Dubuque, IA 52001 (563)589-4270
Return to:Adreinne N.Breitfelder,City Clerk, 50W 13'h Street, Dubuque, IA 52001 (563)589-4100
RESOLUTION NO. 122-23
ACCEPTING THE MYSTIQUE ICE CENTER - RINK ICE SYSTEM REMOVAL AND
REPLACEMENT PROJECT AND AUTHORIZING THE PAYMENT TO THE
CONTRACTOR
Whereas, the public improvement contract for the Mystique Ice Center - Rink Ice
System Removal and Replacement Project (the Project) has been completed by the
Contractor, Rink-Tec International, Inc., (Contractor), and the City Engineer has
examined the work and recommends that the Project be accepted; and
Whereas, the final contract amount for the Project is $816,201.42; and
Whereas, the Contractor has previously been paid $795,796.38, leaving a balance of
$20,405.04; and
Whereas, the City Council finds that the recommendation of the City Engineer should
be accepted.
NOW, THEREFORE, BE 1T RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved, and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of$20,405.04 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa Code
chapter 26.13.
Passed, approved, and adopted this 1st day of May, 2023.
Brad M. Ca a g , Mayor
Attest:
Trish Gleason, Assistant City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE MYSTIQUE ICE
CENTER - RINK ICE SYSTEM REMOVAL AND REPLACEMENT PROJECT
The undersigned City Engineer of the City of Dubuque, lowa, hereby certifies that he has
inspected the Mystique Ice Center - Rink Ice System Removal and Replacement Project
has been performed in compliance with the terms of the Public Improvement Contract,
and that the total cost of the completed work is $816,201.42.
Dated this 24t" day of April 2023.
Gus Psihoyos, City Engineer