Loading...
East-West Corridor Capacity Improvements: Professional Consultant Service Contract - Supplement Agreement No. 1 - Preliminary Engineering Design Enviromental Clearance Phase Copyrighted May 1, 2023 City of Dubuque Consent Items # 06. City Council Meeting ITEM TITLE: East-West Corridor Capacity Improvements: Professional Consultant Services Contract- Supplemental Agreement No.1 - Preliminary Engineering Design and Environmental Clearance Phase SUM MARY: City Manager recommending City Council adopt a resolution which authorizes the City Manager to execute Supplemental Agreement No.1 with HDR, Inc. which approves revisions to the original scope of services to the Consultant Professional Services Contract to complete the Preliminary Engineering Design and Environmental Clearance Phase to advance the development of East-West Corridor Capacity Improvements, subject to the concurrence of the lowa Department of Transportation. RESOLUTION Approving the Consultant Professional Services - Supplemental Agreement No. 1 between HDR I nc. and the City of Dubuque for the East-West Corridor Capacity I mprovements SUGGESTED Suggested Disposition: Receive and File;Adopt Resolution(s) DISPOSITION: ATTACHMENTS: Description Type MVM Memo City Manager Memo Staff Memo Staff Memo Resolution Resolutions Agreement Supporting Documentation Dubuque THE CITY QF � All-Meriea Ciry DLT B E ; . � . � �� � � MaSt� Z�C� aYd t�Q Mt55ZSSZ Z zoa�•zoiz•�ai3 YP pp za��*zai� TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: East-West Corridor Capacity Improvements Professional Consultant Services Contract - Supplemental Agreement No.1 Preliminary Engineering Design and Environmental Clearance Phase lowa DOT Project No. STBG-SWAP-2100 (698)--SG-31 DATE: April 26, 2023 Assistant City Engineer Robert Schiesl is recommending City Council adopt a resolution which authorizes the City Manager to execute Supplemental Agreement No.1 with HDR, Inc. which approves revisions to the original scope of services to the Consultant Professional Services Contract to complete the Preliminary Engineering Design and Environmental Clearance Phase to advance the development of East-West Corridor Capacity Improvements, subject to the concurrence of the lowa Department of Transportation. I concur with the recommendation and respectfully request Mayor and City Council approval. � Mic ael C. Van Milligen MCVM:sv Attachment cc: Crenna Brumwell, City Attorney Cori Burbach, Assistant City Manager Gus Psihoyos, City Engineer Robert Schiesl, Assistant City Engineer Dubuque THE CITY OF � Alk•America Cip� D Y J� til'L�� I I1:tAf. U ' I I�' � � Masterpiece on the Mississippi 2oi�*2oi� TO: Michael C. Van Milligen, City Manager Gus Psihoyos, City Engineer FROM: Robert Schiesl, Assistant City Engineer SUBJECT: East-West Corridor Capacity Improvements Professional Consultant Services Contract - Supplemental Agreement No.1 Preliminary Engineering Design and Environmental Clearance Phase lowa DOT Project No. STBG-SWAP-2100 (698)--SG-31 DATE: April 24, 2023 INTRODUCTION The enclosed resolution authorizes the City Manager to execute Supplemental Agreement No.1 with HDR, Inc. which approves revisions to the original scope of services to the Consultant Professional Services Contract to complete the Preliminary Engineering Design and Environmental Clearance Phase to advance the development of East-West Corridor Capacity Improvements. BACKGROUND In December of 2021, the Mayor and City Council approved the selection of HDR, Inc. as the Consultant to complete the Preliminary Engineering Design and Environmental Clearance Phase to advance the development of East-West Corridor Capacity Improvements along University Avenue. In March of 2022, with the Infrastructure Investment and Jobs Act (IIJA) funding allocation to the State of lowa, the lowa DOT announced the increase in new federal funds will require additional Primary Road Funds (PRF) to be used as the State's local match, which will impact the lowa DOT's ability to provide SWAP funds for Local Public Agency (City) projects. With the reduced SWAP funding capacity, the lowa DOT has informed all Cities that all programs will transition from SWAP to Federal-aid funds, starting in February 2023. Since the East-West Corridor Capacity Improvements are a multi-year, multi-phased project, which transitioned from SWAP (100%) to Federal-aid (80%/20%) in February 2023, the City was required to identify and allocate an additional $2 million as the City's 20% local match as part of the Fiscal Year 2024 - 2027 adopted budget. Based on discussions with lowa DOT staff, the current HDR Contract for the East-West Corridor Capacity Improvements is funded through a SWAP Funding Agreement (Agreement No. 6-19-STBG-SWAP-039) which was executed in December 2019, and lowa DOT staff have agreed that the Preliminary Engineering Design and Environmental Clearance Phase can be completed and funded utilizing SWAP (100%) funding already committed. However, moving forward, the future final design phase, the property acquisition phase, and construction phase(s) will be required to utilize Federal- aid (80%/20%) funding. DISCUSSION Due to the funding shift to Federal-aid, and to ensure that future phases of the project will remain eligible to utilize federal funding, this will require the environmental study phase to be elevated to a National Environmental Policy Act (NEPA) level clearance. The various Phase 1 and Phase 2 elements that are required for federal regulatory compliance are summarized as follows: Environmental Resource Phase 1 Environmental Resource Phase 2 • Regulatory Agency Coordination • Environmental Assessment with • Threatened & Endangered Species Individual Section 4(f) Evaluation & Regulated Materials FHWA Regional � • Office Review T&E Species � Water of the US FAA Notice • FONSI with Individual Section 4(f) � Evaluation • Traffic Noise Study FONSI Concurrence • Low-Income, Minority & Vulnerable � Populations � Cultural Resources • Section 106 Historic Properties • Section 4(f) Evaluation Due to the revised scope of services and the additional level of work to meet the NEPA level regulatory requirements, this will add additional cost ($149,556) to the Consultant design services contract. The Consultant Professional Services - Supplemental Agreement No.1 authorizes HDR to provide the revised NEPA scope of services to continue to advance the completion of the Preliminary Engineering Design and Environmental Clearance Phase and to advance the development of East-West Corridor Capacity Improvements. SCHEDULE IMPACTS Due to the additional level of work to meet the NEPA level regulatory requirements, and coordination with multiple regulatory agencies, this will delay the environmental clearance phase by 8-12 months. As the City and consultant team progress through the preliminary design and NEPA level clearance process over the next year, there will be two (2) public information meetings this summer and fall. These public open house meetings will provide property owners and citizens the opportunity to receive information about the project and allow the public an opportunity to provide input. RECOMMENDATION I recommend that the City Council authorize the City Manager to execute the Consultant Professional Services - Supplemental Agreement No.1 with HDR, Inc. which approves revisions to the original scope of services to complete the Preliminary Engineering Design and Environmental Clearance Phase to advance the development of East-West Corridor Capacity Improvements, subject to the concurrence of the lowa Department of Transportation. BUDGET IMPACT Through Supplemental Agreement No. 1, the professional services fee will be increased due to the revised scope of services and the additional level of work to meet the NEPA level regulatory requirements, which will add additional cost ($149,556) to the Consultant contract, and is summarized as follows: Description Amount HDR - Consultant Professional Services Base Contract $ 1,040,618.00 Supplemental Agreement No. 1 - Scope of Services Revisions 149,556.00 Total Contract Cost $ 1,190,175.00 The Consultant contract funding summary is as follows: Project Code Funding Source Amount 5521000001-301-64070 DMATS STBG SWAP Funds $ 1,190,175.00 Total Project Funding $ 1,190,175.00 ACTION TO BE TAKEN The City Council is requested to authorize the City Manager to execute the Consultant Professional Services - Supplemental Agreement No.1 with HDR, Inc. which approves revisions to the original scope of services to complete the Preliminary Engineering Design and Environmental Clearance Phase to advance the development of East-West Corridor Capacity Improvements, subject to the concurrence of the lowa Department of Transportation, through adoption of the enclosed resolution. Prepared by Robert Schiesl, Assistant City Engineer cc: Jenny Larson, Chief Financial Officer Nathan Steffen, Civil Engineer Dillon Feldmann, lowa DOT Chris Malmberg, HDR F:\PROJECTS\EAST-WEST CORRIDOR CAPACITY IMPROVEMENTS\2021 Consultant PE NEPA RFP\Supplemental Agreement 1 Prepared by:Bob Schiesl, City of Dubuque Engineering, 50 W. 13th Street,Dubuque, IA 52001 (563)589-4270 Return to:Adreinne N.Breitfelder, City Clerk,50W 13'h Street,Dubuque,SA 52001 (563)589-4100 RESOLUTION NO. 124-23 RESOLUTION APPROVING THE CONSULTANT PROFESSIONAL SERVICES - SUPPLEMENTAL AGREEMENT NO. 1 BETWEEN HDR INC. AND THE CITY OF DUBUQUE FOR THE EAST-WEST CORRIDOR CAPACITY IMPROVEMENTS Whereas, the City of Dubuque is proceeding with East-West Corridor Capacity Improvements; and Whereas, due to the revised scope of services and the additional level of work to meet the NEPA level regulatory requirements, this will add additional cost ($149,556) to the Consultant design services contract; and Whereas, the Consultant Professional Services - Supplemental Agreement No.1 authorizes HDR to provide the revised NEPA scope of services to continue to advance the completion of the Preliminary Engineering Design and Environmental Clearance Phase and to advance the development of East-West Corridor Capacity Improvements. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That said Consultant Professional Services - Supplemental Agreement No. 1 between HDR, Inc. and the City of Dubuque for the Preliminary Engineering Design and Environmental Clearance Phase for the East-West Corridor Capacity Improvements is hereby approved, subject to the concurrence of the Iowa Department of Transportation. Section 2. That the City Manager be authorized and directed to execute said Consultant Professional Services - Supplemental Agreement No. 1 with HDR, Inc. for the East-West Corridor Capacity Improvements. Passed, approved, and adopted this 1st day of May, 2023. Brad M. Cava a ih(Mayor Attest: Trish Gleason, Assistant City Clerk Contract No. Owner Project No. CIP 2501039/ 3001039 Iowa DOT Project No. STBG-SWAP-2100(698)—SG-31 SUPPLEMENTAL AGREEMENT#1 TO STANDARD CONSULTANT CONTRACT FOR ENGINEERING SERVICES WHEREAS: HDR ENGINEERING, INC. ("HDR") entered into an Agreement on January 19, 2022 to perform preliminary engineering and environmental study services for The City of Dubuque("Owner"); Owner desires to amend this Agreement in order for HDR to perform services beyond those previously contemplated; HDR is willing to amend the agreement and perform the services herein identified. NOW, THEREFORE, HDR and Owner do hereby agree: The Agreement and the terms and conditions therein shall remain unchanged other than those sections and exhibits listed below; Attachment A Scope of Services shall be revised to include additional NEPA services per the attached Exhibit A. Attachment C-Fees and Payments shall be revised per the following tables. Total Contract Maximum Amount Payable increased by$149,556 to$1,190,175. Base Contract Summary Of Fee HDR SERVICES{IV+V-VI) 5602,700 SUBCONSULTANT SERVICES IMSA} S393,536 SUBCONSULTANT SERVICES ITERRACON) $24,600 SUBCONSULTANT SERVICES(TALLGRASS) $19,783 (TOTAL FEE $1,040,618 Revision to Base Contract Base Contract Fee Revised Fee Revised Fee HDR SERVICES(IV+V'VI) 5602,700 S550,555 SUBCONSULTANT SERVICES(WA) S393;536 S52,115 5115,680 SUBCONSULTANT SERVICES ITERRACON) 524,600 50 524,600 SUBCONSULTANT SERVICES(TALLGRASS)^ 519,783 50 $19,783 ITOTAL FEE 51,040,618 50 $1,040,618 Base Contract plus Supplement tit Revised Fee Supplement 41 Total Kee HDR SERVICES(IV+V+VI) 5550,555 5118,436 S698,991 SUBCONSULTANT SERVICES MSA} 5445,680 SO $445,680 SUBCONSULTANT SERVICES(TERRACON) 524,600 50 $24,600 SUBCONSULTANT SERVICES(TALLGRASS) $19,783 51.120 $20,903 (TOTAL FEE 51,040,618 S149,556 $1,190,175 Contract No. Owner Project No. CIP 2501039 / 3001039 Iowa DOT Project No. STBG-SWAP-2100(698)-SG-31 IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed by their proper officials thereunto duly authorized as of the dates below. HOR ENGINEERING, INC. . Matthew B. Tondl Senior Vice President ATTEST: '-J/2 (,/.U!tl. I 7 /C7Kt//( tu By ./1 CITY OF DUBUQUE, IOWA By~ 7 Michael C. Van Milligen City Manager Date: Apr 20, 2023 Date: Apr 20, 2023 Date:J~ 7 IOWA DEPARTMENT OF TRANSPORTATION Accepted for FHWA Authorization* By ___________ _ Date: _________ _ Name ___________ _ Title ___________ _ * The 'Iowa DOT is not a party to this agreement. However, by signing this agreement, the Iowa DOT is indicating the work proposed under this Agreement is acceptable for FHWA authorization of Federal funds. · 5/4/2023 Dillon J. Feldmann, P.E. Iowa DOT LSFE Eastern Region EXHIBIT A EAST-WEST CORRIDOR UNIVERSITY AVENUE OVERLAP SECTION INTERSECTION CAPACITY IMPROVEMENTS SCOPE OF SERVICES SUPPLEMENTAL AGREEMENT 1 -NEPA SUPPORT I. INTRODUCTION This project was assumed to be completed using Iowa SWAP funding, which would not require compliance with the National Environmental Policy Act (NEPA). With the changes to the SWAP program with reduced funding for construction, federal funding is required to complete this project, thus requiring NEPA compliance. This scope of services is to add in the additional effort to complete NEPA and other relevant environmental documentation. The following tasks are anticipated to address NEPA compliance requirements: • Public Agency Coordination • Expanded environmental resource studies under existing contract • Additional studies for resources not included in the existing contract • NEPA documentation and decision document • Strategic Communications to support a public hearing • Additional alternatives development to support NEPA requirements All of the environmental tasks under the existing contract are relevant to a NEPA process and would need to be expanded for an Environmental Assessment (EA) or Environmental Impact Statement (EIS) level of effort. Iowa DOT and FHWA have started a new planning and environmental linkage process where they are deferring determination of a NEPA classification to help delay the start of the NEPA clock for completion of NEPA documents. Before NEPA classification, environmental studies are completed, initial public involvement and environmental resource agency coordination is conducted, concepts/alternatives are developed, and alternatives screening is performed to recommend a preferred alternative or a limited number of alternatives for detailed evaluation. For purposes of this amendment, it is assumed an EA level of analysis will be required. However, based on relocation impacts (potentially of historic properties eligible for the National Register of Historic Places (NRHP)) and potential controversy, an EIS could be possible. Under NEPA, if it is unknown whether an EA or EIS would be the appropriate NEPA classification, the effort typically follows an EA classification, then could be upgraded to an EIS if needed. It is also assumed for the purposes of developing scope that the potential impacts of the project could be addressed via a Finding of No Significant Impact (FONSI) decision document, if found to be supported by the findings of the EA. A-1 1/22/2023 HDR proposes to conduct a two-phase approach for meeting NEPA and other relevant environmental requirements, with the first phase to perform public and agency coordination, expand environmental resource studies approved under the existing contract for EA-level of analyses, and conduct additional studies for resources not included in the current contract. The second phase would be the preparation of the appropriate NEPA document and decision document (assumed to be an EA and FONSI,respectively). II. DESCRIPTION OF WORK TASKS The details of the tasks are described as follows: 1. Project Management and Coordination 1.1. Project Management. This task includes activities to prepare and process invoices and prepare monthly progress reports beyond the 12-month schedule to a proposed 24-Month schedule. 1.2. Correspondence. Additional correspondance will be managed under the existing contract. 1.3. Project Meetings. Additional project meetings will be managed under the existing contract. Existing in person meetings will be converted to virtual meetings. 1.4. Team Meetings. Additional project team meetings will be manager under the existing contract. 1.5. Quality Control. Perform QA/QC checks prior to all official submittals. Prepare a quality management plan (including subs) describing the anticipated reviews, review schedule, and reviewers. Reviews of draft and final NEPA, decision document, and additional or expanded environmental resource studies. 2. Environmental Resources Phase L The first phase will consist of planning and environmentallinkage process to support the NEPA document. 2.1. Agency Coordination. HDR will perform resource agency coordination using Iowa DOT's database and list of agencies. This would be done noting it is part of the environmental planning process leading up to NEPA. 2.2. Cultural Resources Expansion Oversight. HDR to coordinate and oversee the expanded Cultural Resources tasks of Tallgrass to include consideration of Section 106 effect determinations and coordination with SHPO office. If an Adverse Effect would occur for a proposed full acquisition of one or more NRHP-eligible properties, additional scope would be required and is not included in this amendment. Deliverables: Historic architectural report 2.3. Section 4(f) 5-step process and Individual Section 4(f) Evaluation. A Section 4(f) Iowa DOT 5-step process memo would be utilized to identify and evaluate potential uses of Section 4(�properties (park,recreational, and historic properties (a wildlife/waterfowl refuge is not present). If only minimal uses of Section 4(fj properties would occur, they could be addressed through a de minimis process under NEPA in Phase 2. If an Adverse Effect would occur for impacts to one or more NRHP-eligible A-2 1/22/2023 properties, that would constitute a Section 4(fj use, requiring an Individual Section 4(fj Evaluation. Because the preliminary review of NRHP-eligible properties has identified potential historic properties on both sides of University Avenue, and within initial concept footprints, it is anticipated that an adverse effect to one or more properties is unavoidable, and an Individual Section 4(� Evaluation would be required. HDR will prepare an Individual Section 4(fj Evaluation to address potential uses of the individual NRHP-eligible buildings, as well as any park or recreation property uses [there are no wildlife and waterfowl refuge properties in the study area]. The evaluation will address if there is no feasible and prudent alternative that completely avoids the use of Section 4(�properties, and that the project includes all possible planning to minimize harm on Section 4(f)properties resulting from the transportation use. The Evaluation will consider the no-action or no-build alternative, and alternatives identified and reviewed during concept and alternatives development and screening. If there is no feasible and prudent avoidance alternative, HDR will evaluate alternatives and identify the alternative or alternatives with the least overall harm. HDR will coordinate with Iowa DOT on the consideration of mitigation measures for reducing impacts on Section 4(� properties. The results of the analysis will be documented in a Draft Individual Section 4(f) Evaluation for Iowa DOT and FHWA review and approval. After agency and public review and comment on the Draft Evaluation, HDR will prepare a Final Individual Section 4(� Evaluation for Iowa DOT and FHWA approval. Deliverables: Section 4(f� Iowa DOT 5-step process memorandum and Individual Section 4(f) Evaluation 2.4. Environmental Justice Expansion. Environmental Justice requirements under federal funding would require a more rigorous process than currently scoped. For example, if several relocations are required in an area of low-income or minority populations identified as an EJ population, additional analysis and outreach would be required, and would be documented in an expanded memorandum. Deliverable: Expanded Environmental Justice memorandum 2.5. Noise Expansion.Noise requirements under federal funding would require a more rigorous process than currently scoped including noise monitoring, running the FHWA traffic noise model on one proposed build alternative and the no build alternative, and preparing a noise report (which would evaluate noise impacts and review potential noise mitigation measures to determine if they are reasonable and feasible). Deliverable: Traffic noise technical memorandum 2.6. Regulated Materials Expansion. The current scope will identify potential hazards of regulated materials sites using Iowa DOT risk categories. The results will be documented in a report and summarize contaminated and regulated material sites impacts (relative to public health and other environmental concerns)for alternatives evaluated in the NEPA document. The findings of the regulated materials review may A-3 1/22/2023 result in the need for further detailed studies in support of a further federal funding process. For example, if contamination from the gas station on the northwest corner of University Boulevard and Asbury would require additional review such as sampling, a supplemental task could be added to address this situation and not included in this amendment. Deliverable: Expanded regulated materials technical memorandum 2.7. Environmental Resources.NEPA documents require consideration of other resources outside the scope of a SWAP process. Below is a list of environmental resources addressed by Iowa DOT EAs that were not included in the initial SWAP scope, are applicable to the Project, and can be evaluated and documented in an environmental planning document or separate memoranda during Phase 1: • Land Use and Related Characteristics • Community Cohesion • Churches and Schools • Economic • Joint Development • Parklands and Recreation Areas • Bicycle and Pedestrian Facilities • Right-of-Way • Relocations • Construction and Emergency Routes • Transportation • Air Quality • Energy • Visual • Utilities • Cumulative Impacts Deliverable: Environmental planning document 3. Environmental Resources Phase 2. The second phase is the preparation of the appropriate classification of NEPA document and decision document. 3.1. Environmental Assessment and Individual Section 4(� Evaluation. HDR will prepare an EA, which includes detailed analysis on up to one build alternative and the No-Build Alternative. Direct and indirect impacts will be identified and addressed, noting any required or proposed mitigations to minimize the impacts. It is assumed up to four iterations of the EA is required for City, Iowa DOT and FHWA comments. • Preliminary Version of EA with Draft Individual Section 4(� Evaluation. Prepare preliminary version of EA to be submitted to the City and then Iowa DOT for review and comment. • Draft EA with Draft Individual Section 4(f) Evaluation. Revise per comments from Preliminary EA and resubmit to City and Iowa DOT for review. A-4 1/22/2023 • EA with Draft Individual Section 4(f) Evaluation. Revise and submit to Iowa DOT for their submittal to and coordination with Iowa FHWA for review for Signature. Upon FHWA approval and signature, HDR will prepare an electronic version of the EA and 10 hard copies. 3.2. Decision Document with Final Individual Section 4(f) Evaluation. Following public review of the Signature EA, a preliminary decision document will be prepared. For estimating purposes, it is assumed that the Project will warrant preparation of a FONSI; if it is determined that a Notice of Intent to prepare an EIS is required, a supplemental scope will be prepared. A Final Section 4(f) Evaluation will accompany the Decision Document. • Preliminary Version of FONSI with Final Individual Section 4(f� Evaluation. Prepare preliminary version of the of the decision document (assumed to be a FONSI) to be submitted to the City and Iowa DOT for review and comment. • Draft FONSI with Final Individual Section 4(f� Evaluation. Revise per comments and resubmit to City and Iowa DOT. • Final FONSI with Final Individual Section 4(f) Evaluation. Revise and submit to Iowa DOT for their submittal to and coordination with Iowa FHWA. Upon FHWA approval and signature, an electronic version of the FONSI would be prepared and provided to the City. HDR would reproduce and mail the FONSI, with the Signature EA attached, for agency and public distribution. For the purposes of the scope, 10 total copies of the Signature EA and FONSI are proposed for distribution, Iowa DOT use, and Consultant use. Assumptions: • The reconnaissance field review conducted under the existing contract confirmed no wetlands or other waters of the US within the project area, so no further work on these resources is anticipated. • A total of ten agency comments and ten public comments (including those received at the hearing) would be received on the EA and addressed in the decision document. HDR will draft responses to comments for review by the City and Iowa DOT, to be incorporated in the decision document. • If right-of-way requirements identified after the decision document requires a change in ROW (potentially including additional relocations) or design, a NEPA Reevaluation would be required and would be added as a supplemental task. 4. Strategic Communications 4.1. Communications Plan. Update the communication plan to revise the schedule to include the NEPA process and additional public meeting. 4.2. Project Updates. The second public meeting in the original scope will be repurposed as the public hearing. No additional public meeting will be planned with NEPA studies. • Task supports additional communication/project updates via website and social media platforms. Assumptions: • No additional public meetings, stakeholder, one-one meetings or City Council Updates are included. A-5 1/22/2023 • The second public meeting under the original contract will be repurposed as the Public Hearing to support the EA. 5. Conceptual Roadway Design.No additional concepting is required to support NEPA studies. Assumptions: • One concept will be developed for the roundabouts to avoid historical property impacts to support NEPA. • Additional alternatives will not be expected to support NEPA. Additional alternatives would require an amendment. III. REVISIONS TO ORIGINAL SCOPE Per the working meeting with City staff, it was determined roundabouts and on street bike lanes are preferred features for this corridor and reduces the need for additional alternatives development. In additional to avoiding historical properties the current project moving forward includes one build alternative including roundabouts. Only minor design variations to support NEPA EA Studies will be anticipated. Due to the project evolution to one build alternative, the original contract includes alternatives development and can be repurposed. The additional scope to analysis and design alternatives will be repurposed to support the additional NEPA studies. Tasks listed below are modified/reduced to support one alternative. 1. Project Management and Coordination. 1.3. Project Meetings. Convert six (6) in person progress meetings to online/virtual meetings. 2. Preliminary Field Work(Data Collection). Work complete. No additional task modifications required. 3. Environmental Review. Additional tasks to support NEPA include in this scope. 4. Geotechnical Investigation.No additional task modifications required. 5. Traffic Analysis 5.3. Safety Evaluation. Reduce from two (2)to one (1)refined alternative to perform predictive crash modeling with Interactive Highway Safety Design Model (IHSDM). 5.4. Alternative Analysis. Reduce from two (2)to one (1)refined alternative to evaluate with Synchro, SIDRA or ARCADY for year 2045 AM and PM peak hours and proof-of- concept (uncalibrated) Vissim microsimulation for year 2045 AM and PM peak hours. 6. Conceptual Roadway Design 10% 6.2. Confirm Typical Section. Up to three (3)typical sections will be reduced to one (1) final section to be developed for the project. 6.4. Initial Alternatives. Reduce from up to three (3) alternatives to one (1) roundabout option. Signalized option will not be developed. 7. Preliminary Roadway Design 30%. Task lead revised with MSA lead with HDR to provide technical resource and QC. Scope proposed and fee proposed to shift to MSA. 8. Preliminary Roadway Design 65%. Task lead revised with MSA lead with HDR to provide technical resource and QC. Scope proposed and fee proposed to shift to MSA. A-6 1/22/2023 9. Drainage Design.No additional task modifications required. 10. Private Utility Coordination.No additional task modifications required. 11. Public Utility Preliminary Design.No additional task modifications required. 12. Quantities and Cost Estimates. Task lead revised with MSA to pull quantities with HDR to finalize cost estimate and unit prices. Scope proposed and fee proposed to shift to MSA. 12.1. Prepare opinion of probable cost for 10%. Reduce from up to three (3) to one (1) alternative. 13. Right-of-Way Design. No additional task modifications required. 14. Strategic Communications. 14.5. Public Meetings. Repurpose meeting#2 from preferred alternative to a Public Hearing. VI. PROPOSED SCHEDULE Schedule will be updated upon NTP and coordinated with the City and State on major milestones. Overall schedule is expected to increase by 12 months. A-7 1/22/2023 �,� ESTIMATE OF RESOURCES AND FEE East-West Corridor llniversity Fvenue Overlap Section Intersection Capacity Improvemen[s VROIER SENIORENGINEER ENGINEERIII/ ENGINEERII/ ENGINEERI/ DESIGNER/ p7p�HOURSBY Resource VROIEttMANAGER CONTROLLER Q[&REVIEW ENVIRONMENTFL ENVIflONMENTAL ENVIflONMENTAL STMTEGIC 7�k 5[IENTISTIII 5[IENTISTII SCIENTISTI GIS COMMUNICATIONS TASK 1-PROJECT MANAGEMENT antl COOROINATION 8 8 responda n eme 0 tings 0 1.0 etings 0 1.5 QualiryCon[rol Oo Oa TASK2-ENVIRONMENTALRESOURCESPHASEI 3.1 Pgenry[oordination 36 ].t NlcuralResourcezExpansionOversigM1c 20 Sec[ion 0(�S�rtep p�ocess and Indivitlual Section J�f�Evaluation 00 Environmental lurti�e Expansion 91 Noise Expansion 300 Regulated Materials Expansion 60 2.) EnvironmentalResources ��a u:e z u ia CommuniNCohesion 2 a 6 Oiw�hes antl SCM1oolz 2 0 6 Ewnomic 2 16 IS loinlDevelopmen[ Pa�klands and Recreation Hreas 2 8 10 Birycle antl VeEeztrian Facilifiez 2 0 6 Rlghtrof-way 2 12 1a Relocafions i 12 16 andEme�gentyRoutes 2 3 8 12 T ansP�t on 2 16 8 21 Alr quality 1 1 2 nergy 1 0 5 2 8 10 2 0 6 d 16 30 TASKS-ENVIRONMENTALRESOURCESPHASEI tal Assessment ana Inaiviaual section 4(f�Ev 0 PrclminaryVenionofEAwicM1Dralclndividual5ecfion4�l�aEvaluafion 30 16 68 382 OrahEAwithUrahlndivitlual5ectionO�f�EvaluaHon 20 30 J8 36 312 wiiM1lntlividual5eciionO�f�Evaluacion 10 5 38 13 55 3.2 OecisionDocument VreliminaryvcrsionofFON5lwitMFinallndlvidual5eccion0�l�Evalua[ion 10 9 30 ]9 ]8 �rak PoN51 witM1 Final Inaiviaual section o�f�Ev 8 5 18 41 FinaIFON5lwithFinallndiridual5tttion4�f�Evalua�ion d 2 9 32 TASK 4-STRATEGIC COMMUNICATIONS d.1 Communi�ationsPlan 3 10 i.2 Vroject Updatez 2 15 0 0 TASK 5-CONCEPTUAL ROADWAY DESIG� 5.1 AI[emativesrosupportNEPAStutlies 0 0 TOTFLHOUflSBYC1A551FICATION < 8 192 300 <) )08 260 1323 L ESTMATEO DIRER IABOR QASSIFICHTION TOTALHOURS AVEHOURLYRATE DIRECTLABORCOST Project Manager $J8.J3 $313-)2 Voller 8 550.)9 $4�6.32 Sro.Engineer/Sr.En ntalScientist 192 $80.00 $15,36000 Englneerlll/Envonrmen al5den�istlll/TrafFicll ]04 $J1.09 $J,430.96 Enginee�II/Envommental5cientizt I 4] $60.58 $2,&1�.36 Engineer I/Envornmental5cien[is[I/GIS J08 50].39 $33,552.12 Designer/SVatiegic Comunciations 260 538.23 59,939.80 TOTAL DIRECT IABOR COST 132i 569,054.18 II.VAYROLLBURDENANOOHCOSTS�VRIMEONLY) Overhead= 154.88Vo $1a8,190.15 I I I.OIRER PROIER E%VENSES qUANi UNIT UNIiCOSi TOTALCOST GeneralPho[ocopies 100 SM1ee[z $0.12 512.00 GPSUsage 1 Days $1�0.�0 $1�0.�0 Pental[ar/Fuel 4 Dayz 5100.00 $400.00 Meals 6 Meals 525.00 $150.00 HotelStay 2 OvernigM1h $300.00 $200.00 EA/FON51 Printing(ll Copies� 11 copies 550.00 $550.�0 Display boards-30x40 0 boards $85.00 $0.00 ScrollPlots-36x120 0 ScrollPlots 560.00 $0.00 Postcards 0 portcards $1.80 50.00 Pos[age 0 pos[age $0.58 $0.0 Legal Noticez 0 notices $500.00 $0.00 Onlinemeetingdomain/M1os[ing 0 Domain/hos[ing $1�0.�0 $0.0 Zoho 1 database yean $960.00 $960.00 Handou[s 0 shee[s $1.80 $0.0 courc aeporcer i each Si,soo.00 Si,soo.00 NoiseMoni[or 2 Days $150.�0 $3�0.�0 Fadll[IesCortofUpital 569,850.18 Dlrectlabor 0.1300% 591.09 TOTAL ESiIMATED DIRECi E%PENSE $0,263.�9 IV.ESTIMATED ARUAL COSTS(I�II r II1�,ROUNDEO 5382,30].43 V.FIXED FEE 13%x(I r I1�-FCO( $21,2)0.33 vi.u�n�mo.�:ea co�amgeo�v li�x U*i�t�i�ll So.00 Summary Of Fee H�RSERVICES�NaVaVI) $2a3,582 SUB[ONSUITANTSERVICE5�M5A� SUB[ONSULTANTSERVICES�TERRACON) SUBCONSULTANTSERVICES(TALLGPASS) S1,1i0 $200,102 CREDR FROM ORIGINAL SCOVE OF WORN OTALSUVVLEMENTFEE 309556 1702 Pankratz Street Madison, WI 53704 M S A P (608)242-7779 TF (800)446-0679 F (608)242-5664 www.msa-ps.com January 19, 2023 Chris Malmberg, PE, ENV SP HDR 1917 S. 67t" Street Omaha, NE 68106-2973 Re: Supplemental Agreement#1 City of Dubuque, IA East-West Corridor University Avenue Overlap Section Intersection Capacity Improvements This project was assumed to be completed using lowa SWAP funding, which would not require compliance with the National Environmental Policy Act (NEPA). With the changes to the SWAP program with reduced funding for construction, federal funding is required to complete this project, thus requiring NEPA compliance. This scope of services is to add in the additional effort to complete NEPA and other relevant environmental documentation. MSA will support HDR with the following additional tasks as described in the Supplemental Agreement#1 Scope of Services prepared by HDR. 1. Project Management and Coordination 1.1. Project Management. This task includes project management beyond the 12-month schedule to a proposed 24-Month schedule. 1.3. Project Meetings. Additional project meetings will be managed under the existing contract. Existing in person meetings will be converted to virtual meetings. 1.4. Team Meetings. Additional project team meetings will be managed under the existing contract. 4. Strategic Communications 4.2. Project Updates. The second public meeting in the original scope will be repurposed as the public hearing. No additional public meeting will be planned with NEPA studies. 5. Conceptual Design. No additional concepting is required to support NEPA studies. In addition to the above revised scope, MSA will assume the lead of Tasks 7 and 8 of the original contract (Task 7— Preliminary Roadway Design 30%, Task 8 — Preliminary Roadway Design 65%). For Task 12, MSA will provide item quantities for HDR to prepare opinions of probable costs. The expected date of completion date of the preliminary design and environmental document will be extended as documented in the scope of services prepared by HDR . We propose working on a cost plus fixed fee basis not to exceed $445,680.39 (an increase of$52,144.68). A breakdown of our costs is shown in the attached Exhibit B. \\msa-ps.com\fs\Projects\490s\492\00492059\Contract\Contract Amendment#1\Updated\230119_HDR_Dubuque_East West Corridor_MSA SA#1.docx Page 2 January 19, 2023 We look forward to continuing to work with you on this project. Sincerely, MSA Professional Services, Inc. �_ �S��;� Ben Wilkinson, PE Team Leader bwilkinson(c�msa-ps.com (608) 216-2057 \\msa-ps.com\fs\Projects\490s\492\00492059\Contract\Contract Amendment#1\Updated\230119_HDR_Dubuque_East West Corridor_MSA SA#1.docx Consultant Weiqhted Direct Labor Rates MSA Professional Services,Inc. Supplemental Agreement#1 East-West Corridor University Avenue Overlap Section City of Dubuque, IA Classification: PROJECT MANAGER Classification: DESIGN TECHNICIAN Current Percent Percent Employee Name(a) Rate b Contribution c (b*c) Employee Name(a) Current Rate(b) Contribution c (b'c) 13383 $69.00 100% $69.00 100% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTAL 100% $69.00 TOTAL 100% $0.00 Classification: SENIOR PROJECT ENGINEER Classification: PRO. LAND SURVEYOR Current Percent Percent Employee Name(a) Rate b) Contribution c (b*c) Employee Name(a) Current Rate(b) Contribution c �b*c) 19703 $49.30 100% $49.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTAL 100% $49.30 TOTAL 0% $0.00 Classification: PROJECT ENGINEER Classification: FIELD TECHNICIAN/SURVEYOR Current Percent Percent Employee Name(a) Rate b Contribution c (b*c) Employee Name(a) Current Rate(b) Contribution(c �b*c) 19698 $44.30 100% $44.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0.00 0.00 TOTAL 100% $44.30 TOTAL 0% $0.00 Classification: ENGINEER Classification: N/A Current Percent Percent Employee Name(a) (b*c) Employee Name(a) Current Rate(b) (b'c) Rate b Contribution c Contribution c 19953 $32.80 100% $32.80 100% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0.00 0.00 TOTAL 100% $32.80 TOTAL 100% $0.00 Page 1 of 6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o N o o N v m � o o N o v o � o v o N ro ro m o v , . , . . . . . . . . . . . . . . . . . . . . . . ' O O O O I� N O N O O I� O N O M O N O O fp fp O W tA tA C] H3 tA N c0 N c0 tA tA N tA c0 H3 01 tA c0 tA I� N 01 01 tA I� N ER I� N M N h N 61 � EA EA EA � EA EA EA EA ' EA EA EA EA W � � W � Z N Z M O O O O O N W m N O O N O N O N O W O 10 (D (p (p O N � f) U.� C O O O O O O O O O O O O O O O O O O O o O O O O O - � w O O O (p CO O N (O O O O O (O N CO (p O O N c0 (p (p (p O CO - O O O W CO I� lf) O O O O C� I� W OJ O O I� N W W W O N - V � W n n n m o �n � � n in in n o � o ro n in � m m m n co Z � I� (O O M t7 M I� ER M N ER ER EA N � (n Ef3 EA N � � EA EA N � Ef3 EA � � EA U� O Z O ER ER ER ER - Q V w � L F � O O O N (p � O � O W N O 1N O (p N O W O ON N N N O (p - C O J � ' 7 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 - N � Q � O O O N O O O N O O O (p O O O O O O O (p O O O O O � � C � o 0 0 � o 0 0 � o 0 o m o 0 0 0 0 0 o m o 0 0 0 0 � > N f� U Ev Ev Ev rn Ev Ev Ev rn Ev Ev Ev rn� Ev Ev vj Ev Ev Ev Ev rn� Ev Ev Ev Ev Ev N Q 7 w� in in p�y � i OW o a i � � a Z m (p � 0 = �Z � o 0 o v o 0 o v o 0 o c� o 0 0 0 0 0 o c� o 0 0 0 0 > N � O � W w � � �Y � °� `o �� U � � o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 = � o 0 o c�i o o m o 0 o co 0 0 o m oi ro o oi o m m � o v O W m m n in e» <n m rn n n � n n n m co m n co rn m m r> n U Q M M � EA � � EA � EA � � EA EA EA � N (� Q O d) EA - � � � o � � ' � w � N N O W O O N O O O V O O O N N O O N N N O (p N v! � � � ' W d � O O U U U s a a �6 m m � a a � o 0 a a` a` � `o `o � � � � � � o 0 m m m � '� '� � s � � O O 0 0 c � ` � � ` a o o � Q o t o � a o v+ � a F a ° `o `o a M o a�i � M � o a�i � � � R � a3i a3i � � C7 `o � � C7 E > > > p 'j� N N O O� 'j� N N O j C t9 £ N N N � U N 0 � r a N � � � r a N N � a O N � � � p:f U � -6 � p U � -6 � W [/J O � N N N �0 .- � O N a q '- � O N y � � N •- - - � E c 3 ~ m � ° � 3 ~ m � [q ° � rn N >m o ' U ��6 �m �m N N p � (n U � q (6 (n C U U � > d C U' 3 3 � � � � o c � � � � o c �� � o � o o N � N � d d �C N N C ' . y i0 i0 � � � C ' O (0 O C ' O � N O O f0 � L � N �� ' a a x � � a Y � � x � � a Y � � x � c� � w` � � � � o q R a > > Y N 7 N 1� N V N t0 1� � � � � = N M O O � 1� 1� 1� 1� 1� � i aD aD o0 0o aD aD � CI � � � O T�a, a a a a a �o �o �o � �o a a # ___ � N r N ao N � N �i E « w� Fee Computation Summary bv Enqineerinq Task MSA Professional Services, Inc. Supplemental Agreement#1 East-West Corridor University Avenue Overlap Section City of Dubuque,IA PROJECT TOTAL Task Direct Labor Indirect Costs Fixed Fee Direct Total Costs Expenses 1.Project Management&Coordination $1,380.00 $2,585.98 $475.92 $0.00 $4,441.90 7.Preliminary Roadway Design 30% $6,143.60 $11,512.49 $2,118.73 $0.00 $19,774.82 8.Preliminary Roadway Design 65% $7,078.40 $13,264.21 $2,441.11 $0.00 $22,783.72 12.Quantities and Cost Estimates $1,598.20 $2,994.87 $551.17 $0.00 $5,144.24 AUTHORIZED TOTAL: $16,200.20 $30,357.55 $5,586.93 $0.00 $52,144.68 Home Office Indirect Cost Rate(%): 187.3900% Percent Fixed Fee(%): 12.00°/o Page 5 of 6 Consultant Contract Total Fee Computation MSA Professional Services, Inc. Supplemental Agreement#1 East-West Corridor University Avenue Overlap Section City of Dubuque, IA Original Contract SA#1 Total for ContracU Work Order Number of Staff 2741 370 3111 Hours Total Direct Labor $116,273.87 $16,200.20 $132,474.07 TotalOverhead $217,490.28 $30,357.55 $247,847.83 Costs Fixed Fee $40,051.71 $5,586.93 $45,638.64 Direct Expenses $19,719.85 $0.00 $19,719.85 Subtotal $393,535.71 $52,144.68 $445,680.39 Subconsultant $0.00 $0.00 $0.00 TOTAL COST $393,535.71 $52,144.68 $445,680.39 Home Office Indirect Cost Rate(%) 187.3900% Fixed Fee(°/a): 12.00% Schedule of Subcontracts Subcontract WORK ELEMENT NAME OF SUBCONSULTANT Method of Payment Amount $0.00 $0.00 $0.00 Page 6 of 6 ��� FEE SUMMARY East-West Corridor University Avenue Overlap Section Intersection Capacity Improvements Base Contract Summary Of Fee HDRSERVICES�IVtV+VI) $602,]00 SUBCONSIILTANTSERVICE5�M5A) $393,536 SUBCONSIILTANTSERVICES�TERRA[ON) $24,600 SUBCONSULTANTSERVICES�TALLGRA55) 519�783 TOTAL FEE $1�040,618 Revision to Base Contract Base Contract Fee Revised Fee Revised Fee HDRSERVICES�IVtV+VI) $602�700 5550�555 SUBCONSIILTANTSERVICE5�M5A) $393,536 $52,145 $445,680 SUBCONSIILTANT5ERV1[ES�TERRA[ON) $24,600 SO $24,600 SUBCONSULTANTSERVICES�TALLGRA55) 519�783 $0 519�783 TOTNL FEE $1�090,618 $0 $1�090�618 Base Contract plus Supplement Nl Revised Fee Supplement#1 Total Fee HDRSERVICES�IVtV+VI) $550�555 $148�436 $698�991 SUBCONSULTANTSERVICES�MSA) 5445,680 S� 5�5,680 SUBCONSULTANTSERVICES�TERRA[ON) 524,600 S� SZ4,600 SUBCONSULTANTSERVICES�TALLGRA55) $19,]83 51,120 520�903 TOTAL FEE $1�040,618 $149�556 $1�190�175