English Lane Sanitary Replacement ProjectCity of Dubuque
City Council Meeting
Consent Items # 021.
Copyrighted
June 5, 2023
ITEM TITLE: English Lane Sanitary Replacement Project
SUMMARY: City Manager recommending City Council adopt a resolution accepting
the improvements and authorize the final payment of the contract amount
of $67,155.76 to Offset Construction, LLC, for the English Lane Sanitary
Replacement Project.
RESOLUTION Accepting the English Lane Sanitary Reconstruction
Project and authorizing the payment to the contractor
SUGGESTED Suggested Disposition: Receive and File; Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
Description
Type
MVM Memo
City Manager Memo
Staff Memo
Staff Memo
Resolution
Resolutions
Engineer's Certificate of Completion Supporting Documentation
THE C
DUj!BQTE
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: English Lane Sanitary Replacement Project
DATE: May 31, 2023
Dubuque
WAWca 914
ii
2007-2012.2013
2017*2019
City Engineer Gus Psihoyos is recommending City Council adopt a resolution accepting
the improvements and authorize the final payment of the contract amount of $67,155.76
to Offset Construction, LLC, for the English Lane Sanitary Replacement Project.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
v
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Deron Muehring, Civil Engineer II
THE C
DUj!B9kFE
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: English Lane Sanitary Replacement Project
DATE: May 30, 2023
Dubuque
AIIā¢Amarica City
2007-2012.2013
2017*2019
INTRODUCTION
The enclosed resolution provides for the acceptance of the construction contract for the
English Lane Sanitary Replacement Project.
BACKGROUND
The English Lane Sanitary Replacement Project provided for the replacement of
approximately 220 linear feet of 8" PVC sanitary sewer. The project also included minor
streambank restoration and stormwater outfall stabilization in areas located along the
sanitary sewer replacement limits.
DISCUSSION
The English Lane Sanitary Replacement Project was completed by Offset Construction,
LLC, of Farley, IA in the final contract amount of $67,155.76. The 1.7% increase to the
original contract amount of $66,034.00 was due to unsuitable backfill material.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment
of the final contract amount of $67,155.76 to Offset Construction, LLC for the English
Lane Sanitary Replacement Project.
BUDGETIMPACT
The summary of project costs for the English Lane Sanitary Replacement Project is as
follows:
Description
Estimate
Award
Final
Construction Contract
$ 85,660.00
$ 66,034.00
$ 67,155.76
Contingency
$8,566.00
$8,566.00
$ 0.00
Construction Administration & Inspection
$18,845.20
$18,845.20
$10,073.36
Total Construction Cost
$ 113,071.20
$93,445.20
$ 77,229.12
The project funding is summarized below:
Funding Code
Fund Description
Fund Amount
5581500017
General Sanitary Repair
$53,360.82
5581500020
Sanitary Sewer Manhole Replacement
$11,057.99
5586500002
Catch Basin Reconstruction
$12,810.31
Total Project Funding
$77,229.12
REQUESTED ACTION
The City Council is requested to adopt the attached resolution accepting the
improvements and authorize the final payment of the contract amount of $67,155.76 to
Offset Construction, LLC, for the English Lane Sanitary Replacement Project.
MWO:kb
cc: Deron Muehring, Civil Engineer II
Prepared by: Max O'Brien City of Dubuque Engineering, 50 W. 13th street Dubu ue IA 52001 563 589-4270
Return to: Adrienne N. Breitfelder, City Clerk, 50W 13th Street, Dubuque, IA 52001 (563)589-4100
RESOLUTION NO. 169-23
ACCEPTING THE ENGLISH LANE SANITARY RECONSTRUCTION PROJECT AND
AUTHORIZING THE PAYMENT TO THE CONTRACTOR
WHEREAS, the public improvement contract for the English Lane Sanitary
Reconstruction Project (the Project) has been completed by the Contractor, Offset
Construction, LLC, (Contractor), the City Engineer has examined the work and
recommends that the Project be accepted; and
WHEREAS, the final contract amount for the Project is $67,155.76; and
WHEREAS, the Contractor has previously been paid $63,797.97, leaving a
balance of $3,357.79; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved, and the
Project is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of $3,357.79 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa Code
chapter 26.13.
Passed, approved and adopted this 5th day of June 2023.
Attest:
Adrienne N. Breitfel er, CMC City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF ENGLISH LANE
SANITARY RECONSTRUCTION PROJECT
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has
inspected the English Lane Sanitary Reconstruction Project has been performed in
compliance with the terms of the Public Improvement Contract, and that the total cost of
the completed work is $77,229.12.
Dated this 30t" day of May 2023.
Gus Psihoyos, City Engineer
Filed in the office of the City Clerk on the 30t" day of May 2023.
Adrienne N. Breitfelder, City Clerk