Awarding Public Improvement Construction Contract for the Chaplain Schmitt Island Trail Connection Project Copyrighted
October 2, 2023
City of Dubuque Action Items # 05.
City Council Meeting
ITEM TITLE: Awarding Public Improvement Construction Contractforthe Chaplain
Schmitt Island Trail Connection Project
SUM MARY: City Manager recommending City Council adopt the resolution to award
the public improvement contract for the Chaplain Schmitt I sland Trail
Connection Project to Midwest Concrete, I nc., of Peosta, IA, in the
amount of$696,632.33, subject to lowa DOT concurrence and approval
of award.
RESOLUTIONAwarding Public ImprovementConstruction Contractfor
the Chaplain Schmitt Island Trail Connection Project, lowa DOT Project
No. E D P-2100 (704)--7Y 31
SUGGESTED Suggested Disposition: Receive and File;Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
Description Type
MVM Memo City Manager Memo
Staff Memo Staff Memo
Resolution Resolutions
Dubuque
THE CITY QF �
All-Meriea Ciry
DLT B E ; . � . �
�� � �
MaSt� Z�C� aYd t�Q Mt55ZSSZ Z zoa�•zoiz•�ai3
YP pp za��*zai�
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Chaplain Schmitt Island Trail Connection Project
Award Public Improvement Construction Contract
lowa DOT Project No. EDP-2100 (704)--7Y-31
DATE: September 27, 2023
Assistant City Engineer Bob Schiesl is recommending City Council adopt the attached
resolution to award the public improvement contract for the Chaplain Schmitt Island
Trail Connection Project, lowa DOT Project No. EDP-2100 (704)--7Y-31 to Midwest
Concrete, Inc., of Peosta, IA, in the amount of$696,632.33, subject to lowa DOT
concurrence and approval of award.
In October of 2022 the City Council approved a funding agreement with the lowa
Department of Transportation to construct a 10-foot-wide multi-use trail along Admiral
Sheehy Drive from 16th street to the Veteran's Memorial on Chaplain Schmitt Island.
The funding agreement allows the City of Dubuque to use $615,000 in a Community
Project Funding Grant resulting from the work of Congresswoman Ashley Hinson. The
trail project will complement the design elements incorporated as part of the Veteran's
Memorial and the Chaplain Schmitt Island Development Master Plan. Engineering staff
coordinated with Leisure Services, and the DRA Chaplain Schmitt Island Development
team on the design of the trail and trailhead. The Engineering Department completed
the construction document development and will be responsible for construction
administration and inspection.
The Chaplain Schmitt Island Trail Connection will provide installation of a 10-foot-wide
multi-use trail along Admiral Sheehy Drive from 16t" street to the Veteran's Memorial on
Chaplain Schmitt Island and would include the following elements:
• Excavation to allow for the installation of the trail
• Installation of base stone for the trail
• Installation of a 10 foot-wide 6-inch thick concrete trail
• Installation of retaining walls where needed due to topography to accommodate the
trail. This includes decorative railing matching what is used at the Veteran's
Memorial.
• Installation of a 6-inch thick decorative concrete trail head plaza
• Installation of parking to accommodate ADA parking near the trail and trailhead.
• Installation of decorative lighting to illuminate the trail and trailhead.
• Installation of an emergency phone tower
• Restoration of disturbed area with topsoil and seed.
The schedule for the Chaplain Schmitt Island Trail Connection Project is scheduled to
start construction no later than May 15, 2024, and the estimated completion date is
August, 2024.
Bids were received on the project by the lowa Department of Transportation on
September 19, 2023, in Ames. Midwest Concrete Inc. submitted the low bid in the
amount of $696,632.33. This bid amount is 15.4% below the estimate of probable cost.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Bob Schiesl, Assistant City Engineer
Jon Dienst, Civil Engineer II
Marie Ware, Leisure Services Director
Alex Dixon, President and CEO Dubuque Racing Association
2
Dubuque
THE CITY OF �+
All•p�eriea Ci�
DuB E Wv���a�����M��
1IIII�r
MAste 22CE OYl t�1e M1S&1SS1 1 zoo�•zoiz*zois
� pp zoi�*zot9
TO: Michael C. Van Milligen, City Manager
FROM: Bob Schiesl, Assistant City Engineer
DATE: September 26, 2023
RE: Chaplain Schmitt Island Trail Connection Project
Award Public Improvement Construction Contract
lowa DOT Project No. EDP-2100 (704)--7Y-31
INTRODUCTION
The purpose of this memorandum is to provide the City Council with information related
to the recommendation to award the public improvement construction contract for the
Chaplain Schmitt Island Trail Connection Project, lowa DOT Project No. EDP-
2100(704)--7Y-31.
BACKGROUND
In October of 2022 the City Council approved a funding agreement with the lowa
Department of Transportation to construct a 10-foot-wide multi-use trail along Admiral
Sheehy Drive from 16th street to the Veteran's Memorial on Chaplain Schmitt Island.
The funding agreement allows the City of Dubuque to use $615,000 in a Community
Project Funding Grant resulting from the work of Congresswoman Ashley Hinson. The
project construction documents follow the lowa DOT Standard Specifications. The trail
project will complement the design elements incorporated as part of the Veteran's
Memorial and the Chaplain Schmitt Island Development Master Plan. Engineering staff
coordinated with Leisure Services, and the DRA Chaplain Schmitt Island Development
team on the design of the trail and trailhead. The Engineering Department completed
the construction document development and will be responsible for construction
administration and inspection.
DISCUSSION
The Chaplain Schmitt Island Trail Connection will provide installation of a 10-foot-wide
multi-use trail along Admiral Sheehy Drive from 16t" street to the Veteran's Memorial on
Chaplain Schmitt Island and would include the following elements:
• Excavation to allow for the installation of the trail
• Installation of base stone for the trail
• Installation of a 10 foot-wide 6-inch thick concrete trail
1
• Installation of retaining walls where needed due to topography to accommodate the
trail. This includes decorative railing matching what is used at the Veteran's
Memorial.
• Installation of a 6-inch thick decorative concrete trail head plaza
• Installation of parking to accommodate ADA parking near the trail and trailhead.
• Installation of decorative lighting to illuminate the trail and trailhead.
• Installation of an emergency phone tower
• Restoration of disturbed area with topsoil and seed.
PROJECT SCHEDULE
The schedule for the Chaplain Schmitt Island Trail Connection Project is as follows:
lowa DOT Advertisement for Bids August 15, 2023
City Initiate Concurrence in Public Bidding Process August 21, 2023
City Publish Public Hearing Notice on Plans & Specs August 25, 2022
City Public Hearing on Plans & Specifications September 5, 2023
lowa DOT Receipt of Bids Proposals (Bid Letting) September 19, 2023
City Award Construction Contract (Subject to IDOT Approval) October 2, 2023
Contract Late Start Date May 15, 2024
Contract Working Days 55 Working Days
Contract Completion Date (Estimated) August 2024
The project was let by the lowa DOT and will be constructed on a working day contract
and the number of working days was established by the Office of Contracts at the lowa
DOT.
BID RESULTS
Bids were received on the project by the lowa Department of Transportation on
September 19, 2023, in Ames. Midwest Concrete Inc., of Peosta, IA submitted the low
bid in the amount of $696,632.33. This bid amount is 15.4% below the estimate of
probable cost.
A summary of the bid proposals received is as follows:
Contractor Name Total Bid
Midwest Concrete Inc. $ 696,632.33
Tschiggfrie Excavating Co. $ 699,639.58
Eastern lowa Excavating and Concrete, LLC $ 806,460.79
Portzen Construction, Inc. $ 862,978.50
RECOMMENDATION
I recommend the public improvement contract for the Chaplain Schmitt Island Trail
Connection Project be awarded to Midwest Concrete, Inc. of Peosta, lowa in the
amount of $696,632.33, subject to lowa DOT concurrence and approval of award.
2
BUDGET IMPACT
The estimate of probable cost for the Chaplain Schmitt Island Trail Connection Project
is as follows:
Description Estimate Award
Construction Contract $ 823,253.00 $ 696,632.33 (1)
Contingency 82,325.00 35,000.00 (1)
Engineering Design Services 104,000.00
Contract Admin / Construction Engineering 135,837.00 55,000.00
Total Project Cost $ 1,041,415.00 $ 890,632.33
The current project funding summary is as follows:
Project Code Funding Source Amount
5544000004 Community Project Funding Grant $ 585,305.86 (1)
Schmitt Island Trail 275,000.00
5521000014 Trails, Sidewalks and Signs 30,326.47
Total Project Funding $ 890,632.33
(1) Construction cost only eligible for grant funding at 80% reimbursement
$696,632.33 + $35,000 (contingency) x 80% _ $585,305.86
The City received $615,000 in Community Project Funding Grant from the USDOT
which can only be used for eligible construction costs at a reimbursement rate of 80%.
Based on the favorable bids received, the City may not utilize all the grant fund
allocation. The City is responsible for providing the 20% local match funding
requirement in addition to other non-participating costs such as design, construction
administration, and inspection services.
ACTION TO BE TAKEN
I recommend that the City Council adopt the attached resolution to award the public
improvement contract for the Chaplain Schmitt Island Trail Connection Project, lowa
DOT Project No. EDP-2100 (704)--7Y-31 to Midwest Concrete, Inc., of Peosta, IA, in
the amount of$696,632.33, subject to lowa DOT concurrence and approval of award.
Prepared by Jon Dienst, P.E.
cc: Marie Ware, Leisure Services Manager
Adam Decker, Engineering Technician
Steve Sampson-Brown, Project Manager
3
Prepared by Jon Dienst City of Dubuque Engineering 50 W 13'St Dubuque, Iowa 52001 (563)589-4270
Return to Adrienne N.Breitfe€der City of Dubuque City Clerk 50 W 13"St Dubuque, Iowa 52001 (563)589-4100
RESOLUTION NO. 332-23
AWARDING PUBLIC IMPROVEMENT CONSTRUCTION CONTRACT FOR THE
CHAPLAIN SCHMITT ISLAND TRAIL CONNECTION PROJECT, IOWA DOT
PROJECT NO. EDP-2100 (704)--7Y-31
Whereas, said sealed proposals were opened and read by the Iowa Department
of Transportation on the 19th day of September 2023 and it has been determined that
Midwest Concrete, Inc. of Peosta, IA with a bid in the amount of $696,632.33 is the
lowest responsive, responsible bidder for the project.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1 . That a Public Improvement Construction Contract for the Chaplain
Schmitt Island Trail Connection Project, Iowa DOT Project No. EDP-2100 (704)--7Y-31 ,
is hereby awarded to Midwest Concrete, Inc. subject to Iowa Department of
Transportation concurrence and approval of award, and the City Manager is hereby
directed to execute a Public Improvement Construction Contract on behalf of the City of
Dubuque for the Project.
Passed, adopted, and approved this 2nd day of October 2023.
toad M. C g gh, Mayor
Attest:
Trish L. Gleason, Assistant City Clerk