3000 Jackson Dubuque Brewing and Malting Project UpdateCity of Dubuque
City Council Meeting
Consent Items # 011.
Copyrighted
March 4, 2024
ITEM TITLE: 3000 Jackson Dubuque Brewing and Malting Project Update
SUMMARY: City Manager submitting a status update on the Dubuque Brewing and
Malting project at 3000 Jackson Street.
SUGGESTED Suggested Disposition: Receive and File
DISPOSITION:
ATTACHMENTS:
Description Type
MVM Memo City Manager Memo
Staff Memo Staff Memo
THE C
DUj!BQTE
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 3000 Jackson Dubuque Brewing and Malting Project Update
DATE: February 27, 2024
Dubuque
WAWca 914
ii
2007-2012.2013
2017*2019
Housing & Community Development Director Alexis Steger is submitting a status update
on the Dubuque Brewing and Malting project at 3000 Jackson Street.
v
Mic ael C. Van Milligen
MCVM:sv
Attachment
CC' Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Alexis Steger, Housing & Community Development Director
Jill Connors; Economic Development Director
Wally Wernimont, Planning Services Director
Michael Belmont, Asst. Housing & Comm Development Director
Dubuque
THE CITY OF
All -America My
nni K xvni , nz: a:u�ir,
DUB E
2007-2012.2013
Masterpiece on the Mississippi 2017*2019
TO: Michael C. Van Milligen, City Manager
Housing & Community
Development Department
350 W 61h Street, Suite 312
Dubuque, Iowa 52001-4763
Office (563) 589-4230
http://www.cityofdubuque.org
FROM: Alexis M. Steger, Housing and Community Development Director
SUBJECT: 3000 Jackson, Dubuque Brewing and Malting Building Update
DATE: February 27, 2024
INTRODUCTION
This memorandum provides a status update on the Dubuque Brewing and Malting project
at 3000 Jackson Street.
BACKGROUND
February 19, 2024 staff presented a memo to update the City Council providing the
following information:
The chute to remove the asbestos material has been constructed and materials are being
removed this week.
Zinser, the construction company hired by the owner, has submitted the following
timeline:
- Mobilize and setup equipment March 11 — March 15
- Demolition of building — March 18 — April 5th
- Cleanup of site April 8 — April 12
The owner has requested that the building be demolished above the third floor and then
the remainder would be demolished with the intent to salvage and recycle usable building
materials. City staff are only recommending this option if the entire demolition scope of
work is included, with no break in work until the entire building is demolished.
DISCUSSION
Most of the asbestos removal work has been completed and the chute constructed to aid
in the removal has been removed. There is some asbestos that is not safe to remove
from the inside. The removal of this remaining asbestos will be completed by Zinser, with
the proper lift equipment, prior to the demolition starting.
The sewer was scoped Tuesday February 20, 2024. The Alliant service change
application with a plan for a new disconnect was submitted to Alliant Monday February
26, 2024, after a plan for service line changes to continue service to Prairie Farms was
completed by the owner.
Wednesday February 28t", the Fire Department will complete a site visit for their sign off
on the demolition permit application.
The owner is also exploring recycling options for the building materials and has asked a
local contractor to evaluate and provide a proposal for the salvage of those materials.
RECOMMENDATION
This memo is for information only.
CC: Jill Connors; Economic Development Director
Wally Wernimont, City Planner
Michael Belmont, Asst. Housing & Comm Development Director
2