Brewing and Malting Project Update - 3000 Jackson DubuqueCity of Dubuque
City Council Meeting
Consent Items # 08.
Copyrighted
March 18, 2024
ITEM TITLE: Brewing and Malting Project Update - 3000 Jackson Dubuque
SUMMARY: Housing & Community Development Director Alexis Steger is submitting
a status update on the Dubuque Brewing and Malting project at 3000
Jackson Street.
SUGGESTED Suggested Disposition: Receive and File
DISPOSITION:
ATTACHMENTS:
Description
MVM Memo
Staff Memo
Type
City Manager Memo
Staff Memo
THE C
DUj!BQTE
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 3000 Jackson Dubuque Brewing and Malting Project Update
DATE: March 14, 2024
Dubuque
WAWca 914
ii
2007-2012.2013
2017*2019
Housing & Community Development Director Alexis Steger is submitting a status update
on the Dubuque Brewing and Malting project at 3000 Jackson Street.
v
Mic ael C. Van Milligen
MCVM:sv
Attachment
CC' Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Alexis Steger, Housing & Community Development Director
Jill Connors; Economic Development Director
Wally Wernimont, Planning Services Director
Michael Belmont, Asst. Housing & Comm Development Director
Dubuque
THE CITY OF
All-Amerim City
wxawi.awc ir-,+ease
DUB E �I I
2007-2012.2013
Masterpiece on the Mississippi 2017*2019
TO: Michael C. Van Milligen, City Manager
Housing & Community
Development Department
350 W 6th Street, Suite312
Dubuque, Iowa 52001-4763
Office (563) 589-4230
http://www.cityofdubuque.org
FROM: Alexis M. Steger, Housing and Community Development Director
SUBJECT: 3000 Jackson, Dubuque Brewing and Malting Building Update
DATE: March 13, 2024
INTRODUCTION
This memorandum provides a status update on the Dubuque Brewing and Malting project
at 3000 Jackson Street.
BACKGROUND
February 27, 2024 staff presented a memo to update the City Council providing the
following information:
Zinser, the construction company hired by the owner, has submitted the following
timeline:
- Mobilize and setup equipment March 11 — March 15
- Demolition of building — March 18 — April 5th
- Cleanup of site April 8 — April 12
Most of the asbestos removal work has been completed and the chute constructed to aid
in the removal has been removed. There is some asbestos that is not safe to remove
from the inside. The removal of this remaining asbestos will be completed by Zinser, with
the proper lift equipment, prior to the demolition starting.
The sewer was scoped Tuesday February 20, 2024. The Alliant service change
application with a plan for a new disconnect was submitted to Alliant Monday February
26, 2024, after a plan for service line changes to continue service to Prairie Farms was
completed by the owner.
Wednesday February 28t", the Fire Department will complete a site visit for their sign off
on the demolition permit application.
The owner is also exploring recycling options for the building materials and has asked a
local contractor to evaluate and provide a proposal for the salvage of those materials.
DISCUSSION
Today, the electrical contractor completed relocation of internal electric service that enters the 3000
Jackson building that is scheduled for demolition but serves a portion of the building used by
Prairie Farms. Alliant energy could not schedule removal of existing overhead powerlines until that
internal work was completed. Now that it is complete, Alliant is scheduling the removal of existing
power lines during the week of March 25, 2024.
A plumbing contractor has scheduled water and sewer disconnects for Monday March 18cn
A large excavator has been brought on site, however the crane will not be delivered until after
Alliant has removed the overhead powerlines.
RECOMMENDATION
This memo is for information only.
CC: Jill Connors; Economic Development Director