Loading...
Five-Year Street Construction Program for Fiscal Years 2025-2029 Copyrighted April 15, 2024 City of Dubuque Action Items # 06. City Council Meeting ITEM TITLE: Five-Year Street Construction Program for Fiscal Years 2025-2029 SUM MARY: City Manager recommending approval of a resolution adopting the Five- Year Street Construction Program for Fiscal Years 2025 -2029. Additional information is located in the City Manager's memo for Public Hearing #4. RESOLUTION Adopting the Five-Year Street Construction Program for Fiscal Years 2025 - 2029 SUGGESTED Suggested Disposition: Receive and File;Adopt Resolution(s) DISPOSITION: ATTACHMENTS: Description Type Staff Memo Staff Memo Resolution Resolutions Five-Year Street Program FY25-29 Proposed Supporting Documentation Dubuque THE CITY OF � All•p�eriea Ci$ Du� � ti���r���r,k�� , � ���, I I MAster 12CE 01Z t�1e MiS81S51 1 zoo��zoiz=zois p pp zoi�*zoi9 TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer DATE: April 10, 2024 RE: Five-Year Street Construction Program for Fiscal Years 2025 - 2029 INTRODUCTION The enclosed resolution provides for the City Council approval of the Annual Five-Year Street Construction Program for Fiscal Years 2025 - 2029. DISCUSSION The Five-Year Street Construction Program for Fiscal Years 2025 - 2029, which is part of the Five-Year Capital Improvement Projects, includes the estimated costs for the street construction work and the anticipated year during which each project will be undertaken. The Five-Year Street Construction Program is considered annually by the City Council as part of the budget process. The lowa Department of Transportation (IDOT) provides annual projections on the amount of Road Use Tax Funds the City of Dubuque will receive over the next five years based on a per capita amount. The State Road Use Tax Fund consists of revenues from fuel tax, vehicle registration fees, use tax, driver's license fees and other miscellaneous sources and is distributed to cities on a per capita basis. It should be noted that in FY 2010, the lowa Department of Revenue increased Road Use Tax Funds (RUT) as a result of higher vehicle registration fees passed into law in 2008. The gas tax was increased ten cents beginning in February 2015. The city is estimated to receive $43,870,059 for FY 2025-2029, of which $23,224,233 is programmed for street related improvements. RECOMMENDATION I recommend that the City Council accept the Annual Five-Year Construction Program for Fiscal Years 2025 - 2029. ACTION TO BE TAKEN The City Council is requested to approve this resolution for the acceptance of the Five- Year Construction Program for Fiscal Years 2025 - 2029. GNP/kjb cc: Jenny Larson, Chief Financial Officer Pre ared by Kerry Bradley City of Dubuque Engineering 50 W. 1V 5t. Dubuciue. IA 52001 563 589-4270 Return to Adrienne N. Breitfelder City Clerk City of Dubuque, 50 W. 131h 5t. Dubuque, IA 52001 (563)589-4100 RESOLUTION NO. 102-24 ADOPTING THE FIVE-YEAR STREET CONSTRUCTION PROGRAM FOR FISCAL YEARS 2025 - 2029 Whereas, a recommended Five -Year Street Construction Program for the Fiscal Year 2025 - 2029 beginning July 1, 2024 and ending June 30, 2029, for the City of Dubuque has been prepared and submitted to the City Council; and Whereas, the Five -Year Street Construction Program: 1) describes specific capital improvement projects-, 2) provides estimated costs for those projects; 3) proposes sources of funding; and 4) schedules the fiscal/calendar year during which each project will be undertaken; and Whereas, the capital improvement projects for the first year of such five-year program are included in the Fiscal Year 2025 budget; and Whereas, the adoption of the Five -Year Street Construction Program is a prudent measure to provide continuity of programs and is in the best interest of the City of Dubuque. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA- Section 1. That the Five -Year Street Construction Program for Fiscal Years 2025 — 2029 beginning July 1, 2024, set out in the Fiscal Years 2025 — 2029 recommended Capital Improvement Budget, is hereby approved and adopted as the proposed allocation of City resources for capital improvements as scheduled in the years shown, subject to annual review and revision. Passed, adopted and approved this 15th day of April 2024. -Brad M. va h, Mayor Attest: .C�1iilirt� Adrienne N. Breitfelder, CMC City Clerk STREET CONSTRUCTION PROGRAM 2025-2029 SUMMARY rxec�Tv oF CALENDAR YEAR 202412025 DUB E FISCAL YEAR 2025 Masterpiece on the Mississippi Street From To Construction Tvae Cost Estimate Fundinp Assistance Pavement Rehabilitation-Concrete Street Repair Multiple Street Locations Street Pavement Rehabilitation $ 700,000 DIC McFadden Farm-South Heacock Rd. Chavenelle Road Pennsylvania Avenue Street Construction $ 4,647,776 State Grant $ 1,766,926 14th Street Overpass Bridge Washington Street Sycamore Street Design $ 100,000 Auburn and Custer Pavement Auburn Street Custer Street Street Construction $ 500,000 Wildwood Drive Bridge Replacement Wildwood Drive at 32nd Street Design $ 100,000 Preliminary Cost Estimate-Annual Street Construction Program $ 6,047,776 Total: � $ 1,766,926 j PROPOSED BUDGET FY 2025 $ 6,047,776 PROGRAM FINANCING: CITY ANNUAL STREET PROGAM $ 4,280,850 SPECIAL ASSESSMENTS FEDERALSTBGFUNDS FEDERALGRANTFUNDS STATE GRANT $ 1,766,926 PRIVATE PARTICIPATION TOTAL STREET PROGRAM FINANCING: $ 6,047,776 ADDITIONAL STREET RELATED IMPROVEMENT PROJECTS Sbeet From To Construction Tvpe Cost Estimate Fundinq Assistance Street Construction General Repairs General Repairs $ 130,000 Concrete Street Section Repair Program General Repairs $ 50,000 Pavement Preservation Joint Sealing General Repairs $ 25,000 Asphalt Milling Program HMA Resurfacing Program $ 99,530 Pavement Marking Project Pavement Markings $ 225,000 lowa DOT Funding $ 25,000 TOTAL ADDITIONAL STREET RELATED COSTS: $ 529,530 TOTAL STREET RELATED IMPROVEMENT COSTS: $ 6,577,306 F:\PROJECTSWnnual Street Program-5 Year\FY2025-2029 Five Year Street Program\Five Year Street Program 2025-2029-Proposed STREET CONSTRUCTION PROGRAM 2025-2029 SUMMARY rxe c�Tv oF CALENDAR YEAR 2025/2026 DUB E FISCAL YEAR 2026 Masterpiece on the Mississippi Street From To Construction Tvae Cost Estimate Fundinp Assistance 14th Street Overpass Bridge Washington Street Sycamore Street Bridge/Street Construction $ 33,153,635 RAISE Grant,Fed STBG $31,539,732 Wildwood Drive Bridge Replacement Wildwood Drive at 32nd Street Bridge Construction $ 400,000 Preliminary Cost Estimate-Annual Street Construction Program $ 33,553,635 Total: �$31,539,732� PROPOSED BUDGET FY 2026 $ 33,553,635 PROGRAM FINANCING: CITY ANNUAL STREET PROGAM $ 2,013,903 SPECIAL ASSESSMENTS FEDERAL STBG FUNDS $ 6,539,732 FEDERAL GRANT FUNDS $ 25,000,000 STATE GRANT PRIVATE PARTICIPATION TOTAL STREET PROGRAM FINANCING: $ 33,553,635 ADDITIONAL STREET RELATED IMPROVEMENT PROJECTS Street From To Construction Tvae Cost Estimate Fundinp Assistance Street Construction General Repairs General Repairs $ 12Q000 Concrete Street Section Repair Program General Repairs $ 25,000 Asphalt Milling Program HMA Resurfacing Program $ 50,000 Bridge Repairs/Maintenance General Repairs $ 100,000 Pavement Marking Project Pavement Markings $ 225,000 lowa DOT Funding $ 25,000 TOTAL ADDITIONAL STREET RELATED COSTS: $ 520,000 TOTAL STREET RELATED IMPROVEMENT COSTS: $ 34,073,635 F:\PROJECTSWnnual Street Program-5 Year\FY2025-2029 Five Year Street Program\Five Year Street Program 2025-2029-Proposed STREET CONSTRUCTION PROGRAM 2025-2029 SUMMARY rxec�Tv oF CALENDAR YEAR 2026 I 2027 DUB E FISCAL YEAR 2027 Masterpiece on the Mississippi Street From To Construction Tvae Cost Estimate Fundinp Assistance 14th Street Overpass Bridge Washington Street Sycamore Street Bridge/Street Construction $ 4,952,462 Fed STBG,Private $ 3,616,866 7th Street Extension to Pine Street 7th Street Pine Street Street Construction $ 400,000 Central Ave Corridor Streetscape Improvements 11th Street 22nd Street Complete Street Corridor Improvements $ 211,736 Preliminary Cost Estimate-Annual Street Construction Program $ 5,564,198 Total: � $ 3,616,866 j PROPOSED BUDGET FY 2027 $ 5,564,198 PROGRAM FINANCING: CITY ANNUAL STREET PROGAM $ 1,947,332 SPECIALASSESSMENTS FEDERAL STBG FUNDS $ 2,616,866 FEDERALGRANTFUNDS STATE GRANT PRIVATE PARTICIPATION $ 1,OOQ000 TOTAL STREET PROGRAM FINANCING: $ 5,564,198 ADDITIONAL STREET RELATED IMPROVEMENT PROJECTS Street From To Construction Tvae Cost Estimate Fundinp Assistance Street Construction General Repairs General Repairs $ 130,000 Concrete Street Section Repair Program General Repairs $ 25,000 Asphalt Milling Program HMA Resurfacing Program $ 50,000 Bridge Repairs/Maintenance General Repairs $ 10Q000 Pavement Marking Project Pavement Markings $ 225,000 lowa DOT Funding $ 25,000 TOTAL ADDITIONAL STREET RELATED COSTS: $ 530,000 TOTAL STREET RELATED IMPROVEMENT COSTS: $ 6,094,198 F:\PROJECTSWnnual Street Program-5 Year\FY2025-2029 Five Year Street Program\Five Year Street Program 2025-2029-Proposed STREET CONSTRUCTION PROGRAM 2025-2029 SUMMARY rxe c�Tv oF CALENDAR YEAR 2027/2028 DUB E FISCAL YEAR 2028 Masterpiece on the Mississippi Street From To Construction Tvpe Cost Estimate Fundinp Assistance 14th Street Overpass Bridge Washington Street Sycamore Street Bridge/Street Construction $ 913,903 7th Street Extension to Pine Street 7th Street Pine Street Street Construction $ 700,000 US20-NW Arterial Intersection Improvements Old Highway Intersection Cresent Ridge Intersection Highway Corridor/Intersection Improvements $ 2,097,000 Federal STBG Funds $ 2,097,000 Preliminary Cost Estimate-Annual Street Construction Program $ 3,710,903 Total: �$ 2,097,000 j PROPOSED BUDGET FY 2028 $ 3,710,903 PROGRAM FINANCING: CITY ANNUAL STREET PROGAM $ 1,613,903 SPECIAL ASSESSMENTS FEDERAL STBG FUNDS $ 2,097,000 FEDERALGRANTFUNDS STATE GRANT PRIVATE PARTICIPATION TOTAL STREET PROGRAM FINANCING: $ 3,710,903 ADDITIONAL STREET RELATED IMPROVEMENT PROJECTS Street From To Construction Tvpe Cost Estimate Fundinp Assistance Street Construction General Repairs General Repairs $ 135,000 Concrete Street Section Repair Program General Repairs $ 50,000 Asphalt Milling Program HMA Resurfacing Program $ 50,000 Bridge Repairs/Maintenance General Repairs $ 100,000 Pavement Marking Project Pavement Markings $ 225,000 lowa DOT Funding $ 25,000 TOTAL ADDITIONAL STREET RELATED COSTS: $ 425,000 TOTAL STREET RELATED IMPROVEMENT COSTS: $ 4,135,903 F:\PROJECTSWnnual Street Program-5 Year\FY2025-2029 Five Year Street Program\Five Year Street Program 2025-2029-Proposed STREET CONSTRUCTION PROGRAM 2025-2029 SUMMARY rxec�Tv oF CALENDAR YEAR 2028/2029 DUB E FISCAL YEAR 2029 Masterpiece on the Mississippi Street From To Construction Tvpe Cost Estimate Fundinp Assistance East-West Corridor Capacity Improvements University/Pennsylvania University/Loras Street/Intersection Reconstruction $ 250,000 14th Street Overpass Bridge Washington Street Sycamore Street Bridge/Street Construction $ 100,000 US20-NW Arterial Intersection Improvements Old Highway Intersection Cresent Ridge Intersection Highway Corridor/Intersection Improvements $ 3,400,000 Federal STBG,ICAAP $ 3,400,000 Central Ave Corridor Streetscape Improvements 11th Street 22nd Street Complete Street Corridor Improvements $ 250,000 Preliminary Cost Estimate-Annual Street Construction Program $ 4,000,000 Total: �$ 3,400,000� PROPOSED BUDGET FY 2029 $ 4,000,000 PROGRAM FINANCING: CITY ANNUAL STREET PROGAM $ 600,000 SPECIAL ASSESSMENTS FEDERAL STBG FUNDS $ 2,400,000 FEDERALGRANTFUNDS STATE GRANT $ 1,000,000 PRIVATE PARTICIPATION TOTAL STREET PROGRAM FINANCING: $ 4,000,000 ADDITIONAL STREET RELATED IMPROVEMENT PROJECTS Street From To Construction Tvpe Cost Estimate Fundinp Assistance Street Construction General Repairs General Repairs $ 140,000 Concrete Street Section Repair Program General Repairs $ 50,000 Asphalt Milling Program HMA Resurfacing Program $ 50,000 Bridge Repairs/Maintenance General Repairs $ 100,000 Pavement Marking Project Pavement Markings $ 225,000 lowa DOT Funding $ 25,000 TOTAL ADDITIONAL STREET RELATED COSTS: $ 425,000 TOTAL STREET RELATED IMPROVEMENT COSTS: $ 4,425,000 F:\PROJECTSWnnual Street Program-5 Year\FY2025-2029 Five Year Street Program\Five Year Street Program 2025-2029-Proposed