Upper Bee Branch Creek Restoration Railroad Sanitary Interceptor Crossing Project (part of Phase IV of the Bee Branch Watershed Flood Mitigation Project) Copyrighted
May 20, 2024
City of Dubuque Consent Items # 012.
City Council Meeting
ITEM TITLE: Upper Bee Branch Creek Restoration Railroad Sanitary Interceptor
Crossing Project (part of Phase IV of the Bee Branch Watershed Flood
Mitigation Project) - Project#5581500003: Acceptance of Public
I mprovements and Contract
SUM MARY: City Manager recommending City Council adopt the attached resolution
accepting the Public Improvement Construction Contract and to
authorize final payment in the amount of$3,289,254.55 to Engineering &
Construction I nnovations, I nc for the Upper Bee Branch Creek
Restoration Railroad Sanitary Interceptor Crossing Project.
RESOLUTION Accepting the Upper Bee Branch Creek Restoration
Railroad Sanitary I nterceptor Crossing Project and authorizing final
payment to the contractor
SUGGESTED Suggested Disposition: Receive and File;Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
Description Type
MVM Memo City Manager Memo
Staff Memo Staff Memo
Resolution Resolutions
Engineer's Certificate of Completion Supporting Documentation
Dubuque
THE CITY QF �
All-Meriea Ciry
DLT B E ; . � . �
�� � �
MaSt� Z�C� aYd t�Q Mt55ZSSZ Z zoa�•zoiz•�ai3
YP pp za��*zai�
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Upper Bee Branch Creek Restoration Railroad Sanitary Interceptor
Crossing Project (part of Phase IV of the Bee Branch Watershed Flood
Mitigation Project) - Project #5581500003
Acceptance of Public Improvements and Contract
DATE: May 14, 2024
City Engineer Gus Psihoyos is recommending City Council adopt the attached
resolution accepting the Public Improvement Construction Contract and to authorize
final payment in the amount of $3,289,254.55 to Engineering & Construction
Innovations, Inc for the Upper Bee Branch Creek Restoration Railroad Sanitary
Interceptor Crossing Project.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Jenny Larson, Chief Financial Officer
Arielle Swift, Public Works Director
Deron Muehring, Water & Resource Recovery Center Director
Dubuque
THE CITY OF �
pll•America Ci�
DuB E �.�K,����K�, .
� � ���
� �
Maste iece oYl the MisSisSi i zoo��zoiz�zoi3
�`P pp zoi�*zatg
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: Upper Bee Branch Creek Restoration Railroad Sanitary Interceptor
Crossing Project (part of Phase IV of the Bee Branch Watershed
Flood Mitigation Project) - Project #5581500003
Acceptance of Public Improvements and Contract
DATE: May 13, 2024
INTRODUCTION
The enclosed resolution provides for the acceptance of the Public Improvement
Construction Contract for the Upper Bee Branch Creek Restoration Railroad Sanitary
Interceptor Crossing Project.
BACKGROUND
In November of 2013, the City Council passed Resolution 335-13 adopting the 2013
Drainage Basin Master Plan Amendment. The amended Drainage Basin Master Plan
outlined several improvements throughout the Bee Branch watershed to mitigate the
effects of future flooding and disasters. Collectively, the improvements form the basis of
the Bee Branch Watershed Flood Mitigation Project outlined in Table 1 below.
Table 1. Twelve phases of the Bee Branch Watershed Flood Mitigation Project
Phase Description Status
1 Carter Road Detention Basin Complete
2 West 32nd Street Detention Basin Complete
3 Historic Millwork District Complete
4 Lower Bee Branch Creek Restoration Complete
5 Flood Mitigation Gate Replacement Initiated'
6 Impervious SurFace Reduction (Green Alleys) Initiated2
7 Upper Bee Branch Creek Restoration Initiated3
g 22"d Street Storm Sewer Improvements Complete to N. Main St.4
9 Flood Mitigation Maintenance Facility Site Cleanup
10 North End Storm Sewer Improvements
11 Water Plant Flood Protection
12 17t" Street Storm Sewer Improvements Complete to Heeb St.5
� Bids for the project were rejected in June of 2022 with the low bid at more than 50% (almost$9 million)over the
engineer's estimate and City budget. Two federal grants will allow for proceeding with bidding the work in 2024.
2 80 of the 240 alleys have been reconstructed as"green", pervious alleys. Several are currently under design.
3 The Upper Bee Branch Creek Restoration Project includes the improvements associated with the Upper Bee
Branch Railroad Culverts Project, including the sanitary sewer crossing through the railroad property.
4 Design complete to Kane Street.
5 Design is complete to Angela St., 60%design to Kirkwood St., 30%design to Rosedale.
Until the sewer system through the railroad property could be installed, a temporary
siphon was installed as part of the Upper Bee Branch Creek Restoration Project
improvements included a temporary siphon to force wastewater flow under the restored
creek, allowing the wastewater to flow west along Garfield Avenue, then south down Elm
Street, and to the Cedar Street Lift Station. Siphons require significant maintenance
challenges and as the flow characteristics necessarily back up wastewater flows which
can lead to the accumulation of solids within the line upstream of the siphon. Installation
of the proposed sewer through the railroad property will allow for the elimination of the
siphon, providing a more hydraulically efficient system that will not be prone to the
accumulation of solids or require frequent, intensive maintenance.
On November 21, 2022, the City Council adopted Resolution 363-22 approving the plans,
specifications, form of contract and estimated cost for the Upper Bee Branch Creek
Restoration Railroad Sanitary Interceptor Crossing Project, in the estimated amount
$3,203,300.00.
In December of 2022, the City Council adopted Resolution 396-22, awarding the
construction contract for the Upper Bee Branch Creek Restoration Railroad Sanitary
Interceptor Crossing Project to Engineering & Construction Innovations, Inc of Oakdale,
Minnesota in the amount of $3,265,620.00.
DISCUSSION
The Upper Bee Branch Creek Restoration Railroad Sanitary Interceptor Crossing Project
has been completed by Engineering & Construction Innovations, Inc of Oakdale,
Minnesota, in the amount of $3,289,254.55 which is a 0.72% increase over the original
contract amount of $3,265,620.00 at the time of award.
RECOMMENDATION
I recommend acceptance of the Public Improvements and authorize payment of
$3,289,254.55 to Engineering & Construction Innovations, Inc for the Upper Bee Branch
Creek Restoration Railroad Sanitary Interceptor Crossing Project.
BUDGET IMPACT
The cost for the Upper Bee Branch Creek Restoration Railroad Sanitary Interceptor
Crossing Project is as follows:
Description Estimate Award Final
Construction Contract $3,203,300.00 $3,265,620.00 $3,289,254.55
Contingency 320,000.00 320,000.00 0.00
Engineering 198,000.00 198,000.00 $195,000.00
Total Project Cost $3,721,300.00 $3,783,620.00 $3,484,254.55
L
The Project is to be funded through a FY22/23 appropriation in the amount of $448,620
(CIP#3402769) and an FY23 appropriation in the amount of $3,335,000 (CIP#7101298/
Project#5581500003). The funding summary is as follows:
ARPA $3,335,000.00
State Sales Tax Increment Proceeds 149,254.55
TOTAL $3,783,620
ACTION TO BE TAKEN
I respectfully request adoption of the attached resolution accepting the Public
Improvement Construction Contract and to authorize final payment in the amount of
$3,289,254.55 to Engineering & Construction Innovations, Inc for the Upper Bee Branch
Creek Restoration Railroad Sanitary Interceptor Crossing Project.
Attach.
Prepared by Deron Muehring
cc: Crenna Brumwell, City Attorney
Jenny Larson, Chief Financial Officer
Arielle Swift, Public Works Director
Deron Muehring, Water & Resource Recovery Center Director
�
Prepared by, Deron Muenring, City of Dubuque Engineering 50 W. 1V Street Dubuque, to 52001 (563)589-4270
Return to: Adrienne N. Breitfelder, City Clerk, 50W 1311 Street, Dubuque, IA 52001 (563)589-4100
RESOLUTION NO. 134-24
ACCEPTING THE UPPER BEE BRANCH CREEK RESTORATION RAILROAD
SANITARY INTERCEPTOR CROSSING PROJECT AN❑ AUTHORIZING FINAL
PAYMENT TO THE CONTRACTOR
Whereas, the Public Improvement Contract for the Upper Bee Branch Creek
Restoration Railroad Sanitary Interceptor Crossing Project (the Project) has been
completed by Engineering & Construction Innovations, Inc (the Contractor), and the City
Engineer has examined the work and that the Project be accepted; and
Whereas, the final contract amount for the Project is $3,289,254.55; and
Whereas, the Contractor has previously been paid $3,124,791.82, leaving a
balance of $164,462.73; and
Whereas, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Chief Financial Officer is hereby directed to pay to the Contractor
the balance of the retainage of $164,462.73 as provided in Iowa Chapter 573, and to pay
such retainage only in accordance with the provisions of Iowa Code Chapter 573 or Iowa
Code Chapter 26.13.
Passed, approved and adopted this 20th day of May, 2024.
Ric W. Jones, M4VPro Tern
Attest: ,7
Adrienne Breitfelder, CMC, City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE UPPER BEE
BRANCH CREEK RESTORATION RAILROAD SANITARY INTERCEPTOR
CROSSING PROJECT
The undersigned City Engineer of the City of Dubuque, lowa, hereby certifies that
he has inspected the Upper Bee Branch Creek Restoration Railroad Sanitary Interceptor
Crossing Project and work has been performed in compliance with the terms of the Public
Improvement Contract, and that the total cost of the completed work is $3,484,254.55.
Dated this 13th day of May 2024.
Gus Psihoyos, City Engineer
Filed in the office of the City Clerk on the 13t" day of May 2024.
�
."' � �r � i
. . '.� ., .:' .' -r ., % � � � . '}, + 'Y , '
Adrienne N. Breitfelder, CMC City Clerk