North Grandview Avenue Pavement Rehabilitation ProjectCopyrighted
October 7, 2024
City of Dubuque CONSENT ITEMS # 5.
City Council
ITEM TITLE: North Grandview Avenue Pavement Rehabilitation Project -
PROJECT 5521000018
SUMMARY: City Manager recommending City Council adopt the attached
resolution to accept the Public Improvement Construction
Contract and to authorize the payment of the contract amount
of $382,449.82 to Eastern Iowa Excavating and Concrete,
LLC, of Cascade, IA, for the North Grandview Avenue
Pavement Rehabilitation Project.
RESOLUTION Accepting the North Grandview Avenue
Pavement Rehabilitation Project and authorizing final
payment to the contractor
SUGGUESTED Receive and File; Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
1. MVM Memo
2. 1 Memo Acceptance N Grandview Pavement Rehab
3. 2 Acceptance Resolutions N Grandview Pavement Rehab
4. 3 Engineer's Certificate of Completion
Page 189 of 674
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: North Grandview Avenue Pavement Rehabilitation Project
PROJECT 5521000018
DATE: October 2, 2024
Dubuque
bikd
AH erla City
111111
2007•2012.2013
2017*2019
City Engineer Gus Psihoyos is recommending City Council adopt the attached
resolution to accept the Public Improvement Construction Contract and to authorize the
payment of the contract amount of $382,449.82 to Eastern Iowa Excavating and
Concrete, LLC, of Cascade, IA, for the North Grandview Avenue Pavement
Rehabilitation Project.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
1.
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Jon Dienst, Civil Engineer II
Arielle Swift, Public Works Director
Bob Schiesl, Assistant City Engineer
Nate Steffen, Civil Engineer
Phil Grommet, Engineering Technician
Page 190 of 674
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
DATE: September 30, 2024
RE: North Grandview Avenue Pavement Rehabilitation Project
PROJECT 5521000018
Dubuque
AII•America City
2007.2012.2013
2017*2019
INTRODUCTION
The attached resolution provides for the acceptance of the public improvement
construction contract for the North Grandview Avenue Pavement Rehabilitation Project.
BACKGROUND
North Grandview Avenue from Loras Boulevard to Rosedale Avenue was last
reconstructed in 1992. Since that time, the concrete joints have become badly
deteriorated. The pavement ride is rough, and city staff have received many complaints
from the public.
DISCUSSION
The North Grandview Avenue Pavement Rehabilitation Project was completed by Eastern
Iowa Excavating and Concrete, LLC. in the final contract amount of $382,449.82 which is
a 7.8% increase above the original contract amount of $354,756.33.
The additional cost is due to additional pavement rehabilitation needed on Delaware
Street east of North Grandview Avenue. Also, additional curb and gutter and sidewalk
needed to be removed and replaced near a city owned lot.
RECOMMENDATION
I recommend that the City Council accept the Public Improvements and authorized the
payment of $382,449.82 to Eastern Iowa Excavating & Concrete, LLC for the North
Grandview Avenue Pavement Rehabilitation Project.
BUDGET IMPACT
The project cost for the North Grandview Avenue Pavement Rehabilitation Project is as
follows:
Page 191 of 674
Description
Award
Final
Construction Contract
$ 354,756.33
$ 382,449.82
Contingency
35,475.63
0.00
Construction Engineering & Inspection
58,534.79
38,244.99
Total
$448,766.75
$420,694.81
The project funding summary is as follows:
CIP No.
Fund Description
Fund Amount
5521000018
Pavement Rehabilitation
$ 420,694.81
Total Project Funding
$ 420.694.81
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolution to accept the Public
Improvement Construction Contract and to authorize the payment of the contract amount
of $382,449.82 to Eastern Iowa Excavating and Concrete, LLC, of Cascade, IA, for the
North Grandview Avenue Pavement Rehabilitation Project.
Prepared By: Jon Dienst, Civil Engineer II
cc: Arielle Swift, Public Works Director
Bob Schiesl, Assistant City Engineer
Nate Steffen, Civil Engineer
Phile Grommet, Engineering Technician
2
Page 192 of 674
Prepared by Jon Dienst City of Dubuque Engineering 50 W. 13th St. Dubuque, IA 52001 (563)589-4270
Return to Adrienne N. Breitfelder City Clerk City of Dubuque, 50 W. 13'h St. Dubuque, IA 52001 (563)589-4100
RESOLUTION NO. 305-24
ACCEPTING THE NORTH GRANDVIEW AVENUE PAVEMENT REHABILITATION
PROJECT AND AUTHORIZING FINAL PAYMENT TO THE CONTRACTOR
WHEREAS, the Public Improvement Contract for the North Grandview Avenue
Pavement Rehabilitation Project (the Project) has been completed by the contractor,
Eastern Iowa Excavating and Concrete LLC (Contractor), and the City Engineer has
examined the work and recommends that the Project be accepted; and
WHEREAS, the final contract amount for the Project is $382,449.82; and
WHEREAS, the Contractor has previously been paid $363,327.33, leaving a
balance of $19,122.49; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the
Project is hereby accepted.
Section 2. The Director of Finance and Budget is hereby directed to pay the
balance of the retainage of $19,122.49 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa
chapter 26.13.
Passed, approved and adopted this 7th day of October 2024.
Cavanagh, Mayor
Attest:
Adrienne N. Breitfelder, CMC City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE NORTH
GRANDVIEW AVENUE PAVEMENT REHABILITATION PROJECT
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the North Grandview Avenue Pavement Rehabilitation Project and work
has been performed in compliance with the terms of the Public Improvement Contract,
and that the total cost of the completed work is $382,449.82.
Dated this 7th day of October 2024.
Gus Psihoyos, City Engineer
Filed in the office of the City Clerk on the 7th day of October 2024.
azi.. 77, Ai:4w,
Adrienne N. Breitfelder, CMC City Clerk