Eagle Point Water Plant Supervisory Control and Data Acquisition (SCADA) Upgrade Award Construction ContractCity of Dubuque City Council ACTION ITEMS # 8. Copyrighted November 18, 2024 ITEM TITLE: Eagle Point Water Plant Supervisory Control and Data Acquisition (SCADA) Upgrade Award Construction Contract SUMMARY: City Manager recommending City Council award the construction contract for Eagle Point Water Plant Supervisory Control and Data Acquisition (SCADA) Upgrade, through the adoption of the enclosed resolution, to Westphal & Company, Inc. of Dubuque, Iowa, in the amount of $1,345,500. RESOLUTION Awarding Public Improvement Construction Contract For The Eagle Point Water Plant Supervisory Control And Data Acquisition (SCADA) Upgrade Project SUGGUESTED Receive and File; Adopt Resolution(s) DISPOSITION: ATTACHMENTS: 1. MVM Memo 2. SCADA System Upgrade Project Construction Award Memo 11.12.2024 3. SCADA System Upgrade Project Construction Award - Resolution 11.12.2024 4. Bid Tab 5. Bid Award Letter Page 1445 of 1454 Dubuque THE CITY OF uFA�a9a av DuBE 13 Masterpiece on the Mississippi zoo�•*o rP PP 2017202019 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Eagle Point Water Plant Supervisory Control and Data Acquisition (SCADA) Upgrade Award Construction Contract DATE: November 14, 2024 Water Department Director Christopher Lester is recommending City Council award the construction contract for Eagle Point Water Plant Supervisory Control and Data Acquisition (SCADA) Upgrade, through the adoption of the enclosed resolution, to Westphal & Company, Inc. of Dubuque, Iowa, in the amount of $1,345,500. The lump sum bid is 27% lower than the engineer's estimate of $1,850,000.00. I concur with the recommendation and respectfully request Mayor and City Council approval. Mic ael C. Van Milligen MCVM:sv Attachment cc: Crenna Brumwell, City Attorney Cori Burbach, Assistant City Manager Christopher Lester, Water Department Director Jennifer Larson, Chief Financial Officer Nick Connolly, Water Operations Supervisor Page 1446 of 1454 THE CITY OF DUB E Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Manager FROM: Christopher Lester, Water Department Director Dubuque All -America City 2007-2012.2013 2017*2019 DATE: November 12, 2024 SUBJECT: Eagle Point Water Plant Supervisory Control and Data Acquisition (SCADA) Upgrade Award Construction Contract INTRODUCTION The purpose of this memorandum is to request award of the Eagle Point Water Plant Supervisory Control and Data Acquisition (SCADA) Upgrade to Westphal & Company of Dubuque, IA in the amount of $1,345,500.00. BACKGROUND The Dubuque Water Works, known as the Eagle Point Water Treatment Plant (WTP), treats and distributes on average 7 million gallons per day (MGD) through a distribution system comprised of over 330 miles of water main via a combined fourteen (14) storage tank and pump station sites. The WTP operators control and monitor the treatment and distribution of drinking water from the treatment plant via a SCADA or Supervisory Control and Data Acquisition system. The SCADA system is linked to each of the remote distribution system sites via radio communications from the WTP. Data collected from each of the remote sites is transmitted back to the WTP and the operators at the plant routinely interact with the SCADA system to make decisions on water production, storage, and overall supply to the distribution system including during emergency situations such as main breaks or fire events. The SCADA system is currently the only method of data collection used for informing the operating staff on what changes are occurring in the water supply and distribution system and how the operators need to respond. Beyond immediate operations, the SCADA system eliminates the need for manned operations at each remote site. It provides constant monitoring of tank and pump station operations. SCADA also provides a level of security with immediate reports of any security breaches or abnormal operating conditions. Having a reliable SCADA system also reduces the number of patrols and manned visits to each of the remote sites reducing overall costs. The current SCADA system has been in place since 1993 and the programming and operating system, RSLogix 500, is outdated and the hardware is no longer supported by the manufacture/vendor and will need to be replaced for continued WTP and remote operations. In addition, the existing hardware has reached its capacity for installing new infrastructure controls and devices required to communicate with tanks, towers, and pump stations. Page 1447 of 1454 DISCUSSION The Water Treatment Plant SCADA System Upgrade project provides for the replacement of the existing Supervisory Control and Data Acquisition (SCADA) hardware and software at the Eagle Point Water Treatment Plant and remote sites including the wells, pump stations, tanks, and towers. The programmable logic controllers (PLCs) and other major components of the existing SCADA system have become obsolete. Additionally, very little of the softening, filtering, and sludge treatment equipment at the WTP is currently monitored by SCADA. It is desirable to install an Ethernet network and add additional control panels in select locations within the WTP to connect important instruments and include provisions for future additions. The existing SCADA software at the WTP is not compatible with the software packages currently in use at the W&RRC. To improve efficiencies associated with problem solving or cross training of staff, it would be desirable for the replacement SCADA system WTP software to be compatible with, and possibly integrated into, the W&RRC SCADA system. Replacing the SCADA system at the WTP would not only replace outdated and obsolete equipment, hardware and software, it would also provide an opportunity to make operational efficiency improvements. While the current SCADA system is capable of collecting and reporting chlorine, pH, turbidity, flow, and pressure measurements at the WTP, with chlorine, tank elevations, pressures and intrusion alarms reporting back from the remote sites, there are additional monitoring possibilities. With added SCADA controls, new analyzers could be introduced to provide further on-line measurements including flow and pressure readings at the pressure reducing vaults, distribution system flow measurement reporting as part of a District Metered Zone program to reduce and detect leaks and main breaks, and research continues in the water industry, the possibility of on-line monitoring for the detection of contaminants in the distribution system. An additional benefit of a replacement SCADA system in coordination with the change from radio communications to fiber optic communication (the fiber optic project will be under a separate RFP) includes the option to enhance security at the remote sites. Such security measures would include the ability to add video cameras, motion detectors, contact switches, keypad entry devices and card readers, which can be interfaced directly to the SCADA system and provide live information back to the operators. The city selected Strand Associates through the public RFP process to complete the design, specifications and assist the city through the SRF loan application procedure. The Strand design team completed the design and bidding documents, and the city has received an approved Iowa DNR preliminary engineering report letter dated April 29, 2024. The scope and bidding documents were prepared, and the project was publicly bid. DISCUSSION Sealed bids for the Eagle Point Water Plant Supervisory Control and Data Acquisition (SCADA) Upgrade were received and publicly opened on October 17, 2024. Westphal & Company, Inc, of Dubuque, Iowa submitted the apparent low bid in the amount of $1,345,500. A summary of the bid proposals received is as follows: 2 Page 1448 of 1454 Item No. Contractor Name Lump Sum Bid Amount 1 Westphal & Company, Inc. $1,345,500.00 2 The Esco Group (Marion IA) $1,420,000.00 3 Altronex Control Systems (Plymouth MN) $1,696,300.00 The lump sum bid of $1,345,500.00 is 27% lower than the engineer's estimate of $1,850,000.00. The execution of the contract may be delayed pending approval from the Iowa Finance Authority (IAF). BUDGET IMPACT The estimate of probable and awarded costs for the project are summarized as follows: Description Estimate Award Planning and Design $47,700 $47,700 Construction plus Other: Materials $1,850,000 $1,345,500 Construction Admin/ Construction Engineering $65,100 $65,100 Contingency 10% $196,000 $196,000 Fees $10,794 $10,794 Total Project Cost, rounded to the nearest $1,000 2.170.000* $1,665,094 The funding summary is: CIP Description Funding Source Amount 4281000001 SCADA and Communications SRF $1,665,094 p. Total Project Funding 11&65.094 Of the SRF funds in the amount of $1,665,094, the project has adequate funding for the total construction cost of $1,345,500. ACTION TO BE TAKEN I respectfully request that the City Council award the construction contract for Eagle Point Water Plant Supervisory Control and Data Acquisition (SCADA) Upgrade, through the adoption of the enclosed resolution, to Westphal & Company, Inc. of Dubuque, Iowa, in the amount of $1,345,500. cc: Jennifer Larson, Chief Financial Officer Nick Connolly, Water Operations Supervisor 3 Page 1449 of 1454 F:\Users\Water\ENGINEERING\Projects - City Projects\Projects - ACTIVE (City)\SCADA Upgrade and Fiber Optic Communication (2020-2022)\Council\Award\Construction Contract Page 1450 of 1454 Prepared by Christopher Lester Water Department 1902 Hawthorne St. Dubuque IA 52001 (563) 589-4291 Return to Adrienne N. Breitfelder City Clerk City of Dubuque, 50 W. 13th St. Dubuque, IA 52001 (563) 589-4100 RESOLUTION NO. 387-24 AWARDING PUBLIC IMPROVEMENT CONSTRUCTION CONTRACT FOR THE EAGLE POINT WATER PLANT SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA) UPGRADE PROJECT WHEREAS, sealed proposals have been submitted by contractors for the Eagle Point Water Plant Supervisory Control and Data Acquisition (SCADA) Upgrade Project, (the Project) pursuant to Resolution No. 275-24 and Notice to Bidders published on the City of Dubuque, Iowa website and plan room service wide circulation on the 5th day of September 2024; and WHEREAS, said sealed proposal was opened and read on the 17th day of October 2024 and it has been determined that Westphal and Company, Inc. of Dubuque, Iowa submitted low bid in the amount of $253,434.00, plus Alternate A in the amount of $38,552.00, with an hourly rate of $381.00/HR, and is the lowest responsive, responsible bidder for the Project. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL FO THE CITY OF DUBUQUE, IOWA. SECTION 1. That a Public Improvement Construction Contract for the Project is hereby awarded to Westphal and Company, Inc. of Dubuque, Iowa and the City Manager is hereby directed to execute a Public Improvement Construction Contract on behalf of the City of Dubuque for the Project. Passed, adopted and approved this 18th day of November 2024. B ad . Ca 'a agh, Mayor Attest: v Adrienne N. Breitfelder,`City Clerk Bids Received: 2 P.M. October 17, 2024 CITY OF DUBUQUE DUBUQUE, IOWA DUBUQUE WATER SCADA UPGRADE IDNR SRF #FS-31-23-DWSRF-080 BID TABULATION SUMMARY STRAND ASSOCIATES, INC.° 910 West Wingra Drive Madison, WI 53715 Bidder Bid Bond and or Addenda Lump Sum Address Guarantee Acknowled ed Bid Westphal & Company, Inc. 10% Yes $1,345,500.00 750 Cedar Cross Road Dubuque, IA 52003 The ESCO Group 10% Yes $1,420,000.00 3450 Third Street Marion, IA 52302 Altronex Control Systems 10% Yes $1,696,300.00 13005 16th Avenue North Plymouth, MN 55441 Reviewed by: 1154.084\JSC:Ier\R:\MAD\Documents\Specifications\Archive\2024\Dubuque, City of (IA)\1154.084.FS-31-23-DWSRF-080.jsc\(14) Bid Tabs\Dubuque.FS-31-23-DWSRF-080.BT1.docx Page 1452 of 1454 6 : A =I STRAND ASSOCIATES® Excellence in Engineeringsm Strand Associates, Inc.® 910 West Wingra Drive Madison, WI 53715 (P) 608.251.4843 www.strand.com October 18, 2024 Mr. Christopher Lester City of Dubuque 1902 Hawthorne Street Dubuque, IA 52001 Re: Dubuque Water SCADA Upgrade IDNR SRF #FS-31-23-DWSRF-080 City of Dubuque, Iowa Dear Chris, Bids for the above -referenced Project were opened on October 17, 2024. Three Bids were received with the resulting Bid tabulation enclosed. The low Bid of $1,345,500 was less than ENGINEER's opinion of probable construction cost. Westphal & Company, Inc. of Dubuque, Iowa, was the apparent low Bidder at $1,345,500. The Bid included a Bid Bond for 10 percent and Addendums No. 1 through No. 3 were acknowledged. The Bid is deemed to be responsive. Strand Associates, Inc.® has previously worked with Westphal & Company, Inc. on projects for Emmi Roth. For those projects, the owner determined Westphal & Company, Inc. to be responsible. Sincerely, STRAND ASSOCIATES, INC.® son S. Carden Enclosure 1154.084VSC:1AerR:AMADADo euisASpecifimtimsAArchiveA2024VDubuque, City of(IA)A1154.084.FS-31-23-DWSRF-080.jsA(16) Speoif tionLetters\(a) Resulting Sid TabulationA101824.docx Arizona I Illinois I Indiana I Iowa I Kentucky I Ohio I Tennessee I Texas I Wisconsin Page 1453 of 1454