ITEM TITLE: Reject Bids 2025 Repair and Maintenance of the Iowa Street
Parking Garage
SUMMARY: City Manager recommending City Council reject the single
bid proposal received for the 2025 Repair and Maintenance
of the Iowa Street Parking Garage due to a lack of
competitive bids and insufficient funding to proceed with the
construction improvements as proposed.
RESOLUTION Rejecting Competitive Bid Proposal Received
For The 2025 Repair And Maintenance Of The Iowa Street
Parking Garage
SUGGUESTED Receive and File; Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
1. MVM Memo
2. 2025 Repair and Maintenance of the Iowa St Parking Garage - Reject Bid Staff
MEMO
3. 2025 Repair and Maintenance of the Iowa St Parking Garage - Reject Bid
RESOLUTION
Page 890 of 950
THE CITY OF
Dubuque
DuBE
uFA�a9a av
Masterpiece on the Mississippi
rP PP
zoo�•*o 13
2017202019
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 2025 Repair and Maintenance of the Iowa Street Parking Garage
Rejection of Single Competitive Bid Proposal
Project No. 4683000002
DATE: May 14, 2025
Director of Transportation Services Ryan Knuckey and Project Manager Jim Bousley
are recommending City Council reject the single bid proposal received for the 2025
Repair and Maintenance of the Iowa Street Parking Garage due to a lack of competitive
bids and insufficient funding to proceed with the construction improvements as
proposed.
It is also recommend that staff review the scope of the project; further evaluate the
estimate of probable cost based on current construction cost market conditions; identify
potential value engineering components so that the improvements can be modified or
adjusted to meet the current available funding; evaluate the construction schedule to
potentially allow contractors more time to complete the ramp repair work; and prepare to
re -bid the project.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Y
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Ryan Knuckey, Director of Transportation Services
Gus Psihoyos, City Engineer
Jim Bousley, Project Manager
Robert Schiesl, Assistant City Engineer
Russ Stecklein, Operations Supervisor Transportation Services
Page 891 of 950
THE C
DUUB%FE
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Ryan Knuckey, Director of Transportation Services
Jim Bousley, Project Manager
Dubuque
All -America Cily
I I® r
2007-2012.2013
2017*2019
SUBJECT: 2025 Repair and Maintenance of the Iowa Street Parking Garage
Rejection of Single Competitive Bid Proposal
Project No. 4683000002
DATE: May 14, 2025
INTRODUCTION
The enclosed resolution authorizes the rejection of the single competitive bid proposal
received for the 2025 Repair and Maintenance of the Iowa Street Parking Garage due
to a lack of competitive bids and insufficient funding to proceed with the construction
improvements as proposed.
BACKGROUND
In 2022 the City issued a Request for Proposals for a Parking Ramp Maintenance
Needs Assessment. In November of 2022 the City Council approved the awarding of
the contract to Desman, Inc. of Chicago, Illinois.
The Iowa Street Ramp condition assessment report completed by Desman indicated
several areas in the Iowa Street parking ramp that need repairs and maintenance work.
A professional services contract was signed with Desman to provide design and
construction administration services for structural repairs.
The 2025 Repair and Maintenance of the Iowa Street Parking Garage would provide for
slab -on -grade asphalt and concrete repairs, full depth pan joist slab repairs, partial
depth concrete repairs on garage ramps, concrete curb island removal and
replacement, form and pour joist repairs, form and pour beam repairs, column repairs,
waterproofing repair and enhancements, new waterproofing membrane, stair tower
repairs, installation of new supplemental floor drains on roof level, electrical upgrades
including circuit conduit and feeders, lighting fixtures, plumbing upgrades including
waste drains, piping, hose bibs, replacement of elevator pit pump and other
miscellaneous work.
PROJECT FUNDING
The estimate of probable cost for the 2025 Repair and Maintenance of the Iowa Street
Parking Garage is summarized as follows:
Page 892 of 950
PROJECT COSTS
ESTIMATE
Construction Contract - Base Bid
$ 4,011,300
Construction Contract - Alternate Bid
978,000
Contingency
523,000
Consultant Services Design - Desman
116,200
Consultant Services Construction - Desman
148,600
City Staff Services, Construction Administration & Inspection
70,000
Total Project Cost
$ 5,847,100
The project funding summary is as follows:
Project No.
Fund Description
Fund
Amount
Parking Ramp Maintenance (FY25)
$ 5,213,362
4683000002
Parking Ramp Maintenance (FY26)
633,738
Total Project Funding
$ 5,847,100
BID RESULTS
Competitive sealed bids were received on the 2025 Repair and Maintenance of the
Iowa Street Parking Garage on May 12, 2025. One (1) bid proposal was received, with
a base bid of $5,606,000, which is 39.8% above the estimate of probable cost. The
single bid received is significantly over the current funding available to complete the
construction improvements as proposed.
RECOMMENDATION
I recommend that the City Council reject the single bid proposal received for the 2025
Repair and Maintenance of the Iowa Street Parking Garage due to a lack of competitive
bids and insufficient funding to proceed with the construction improvements as
proposed.
I also recommend that staff review the scope of the project; further evaluate the
estimate of probable cost based on current construction cost market conditions; identify
potential value engineering components so that the improvements can be modified or
adjusted to meet the current available funding; evaluate the construction schedule to
potentially allow contractors more time to complete the ramp repair work; and prepare to
re -bid the project.
ACTION TO BE TAKEN
I recommend that the City Council reject the single bid proposal received through the
adoption of the enclosed resolution for the 2025 Repair and Maintenance of the Iowa
Street Parking Garage.
cc: Gus Psihoyos, City Engineer
Robert Schiesl, Assistant City Engineer
Russ Stecklein, Operations Supervisor Transportation Services
F:\PROJECTS\Iowa Street Parking Ramp\2025 Repair and Maintenance of the Iowa Street Parking Garage\City Council\Reject Bids
Page 893 of 950
Prepared by Kerry Bradley City of Dubuque Engineering 50 W. 13th St. Dubuque IA 52001 (563)589-4270
Return to Adrienne N. Breitfelder City Clerk City of Dubuque, 50 W. 13th St. Dubuque, IA 52001 (563)589-4100
RESOLUTION NO. 173-25
REJECTING COMPETITIVE BID PROPOSAL RECEIVED FOR THE 2025 REPAIR
AND MAINTENANCE OF THE IOWA STREET PARKING GARAGE
WHEREAS, one (1) competitive sealed bid proposal was received for the 2025
Repair and Maintenance of the Iowa Street Parking Garage (the Project) pursuant to
Resolution No. 136-25 and Notice to Bidders published in the City of Dubuque, Iowa
website and a contractor plan room service with statewide circulation on the 25th day of
April, 2025; and
WHEREAS, the one (1) competitive sealed bid proposal was opened and read on
the 12th day of May 2025; and
WHEREAS, the City Council has deemed it advisable to reject the one (1)
competitive sealed bid proposal for the Project.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
SECTION 1. The one (1) competitive sealed bid proposal for the 2025 Repair and
Maintenance of the Iowa Street Parking Garage is hereby rejected.
SECTION 2. The City Clerk is authorized and instructed to return the bid deposit
of the unsuccessful bidders for the 2025 Repair and Maintenance of the Iowa Street
Parking Garage.
Passed, approved and adopted this 19th day of May 2025.
Attest: Brad M. Cava�g , Mayor