Flora Pool and Sutton Pool Water Playground Project
Sealed bids were received to construct water playgrounds at Flora and Sutton Pools.
Leisure Services Manager Gil Spence is recommending award to the Iow bidder,
Portzen Construction, in the amount of $725,021. Considering the previous expenses
related to design fees, this results in the project being over budget by $141,330. Gil
Spence has been able to identity other Leisure Services projects that came in under
budget or that could be delayed to a future date to cover this extra expense.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, Corporation Counsel
Cindy Steinhauser, Assistant City Manager
Gil D. Spence, Leisure Services Manager
CITY OF DUBUQUE, IOWA
MEMORANDUM
June 11, 2001
TO: Michael C. Van Milligen, City Manager
FROM: Gil D. Spence, Leisure Services Manager
SUBJECT: Flora Pool and Sutton Pool Water Playground Project
INTRODUCTION
The purpose of this memorandum is to provide a recommendation on awarding the
contract for constructing water playgrounds at Flora and Sutton Pools.
DISCUSSION
Sealed bids were received on June 5, 2001, to construct water playgrounds at Flora and
Sutton Pools. A summary of the bids received is as follows:
Portzen Construction
Base bid $ 438,161
Alternate 1 - Deck per sq, ff. 5
Alternate 2 - Shade structures 11,530
Alternate 3 - Pool heaters 30,645
Alternate 4 - SCS equipment 253,185
Alternate 5 - Com-pac equipment 235,087
deduct for doing both pools 8,500
Riccio Construction
$ 698,000
5
14.800
30,800
333,800
282,400
0
The FY 2001 C.I.P.-budget contains $262,500 and the FY 2002 C.I.P. budget contains
$439,000 ($701,500 total) for this project, design and engineering. Portzen's base bid plus
Alternate 2, 3 and 4 results in a total bid of $725,021. Adding design fees ($117,810) to the
Iow bid ($725,021), total project cost is $842,830. This results in the project being
$141,330 over budget. Design fees are $48,810 over the budgeted amount and
construction costs are $92,521 over the budgeted amounts.
Alternate 4 - SCS equipment is the interactive equipment shown in the video dudng budget
presentations. Alternate 5 - Com-pac equipment would be substitute for the SCS equip-
water playgrounds, page two
ment and is not interactive. We included this alternate for a cost comparison and do not
feel the savings are worth the change to non-interactive equipment.
This is an important project that the citizens are looking forward to and one we very much
would like to see move forward. To help make up the cost overrun, we propose using
savings from the following pool projects where savings have resulted or where the project
can be re-budgeted for a later date without a significant impact to the operation.
Fiscal Year
2001
2001
2001
2001
2001
2001
2001
2002
2002
2002
Proiect Cost
waterslide flumes $ 20,200
storage building * 5,000
Flora - expansion of fence 14,700
Sutton - chemical controller * 3,000
paint filter tanks 6,300
ventilation fans 15,000
shade structures * 22,000
ozone disinfection 16,000
shade structures 12,000
landscaping * 3,000
$ 117,200
The balance of the shortfall of $24,130 will be covered from savings in park division capital
projects, including painting Town Clock light standards, renovating park office and
McAleece storm sewers.
RECOMMENDATION
I recommend that the contract be awarded to Portzen Construction in the amount of
$725,021.
ACTION STEP
The action requested is that the City Council adopt the attached resolutions approving the
plans and specifications and awarding the contract to Portzen Construction in the amount
of $725,021.
GDS:et
attachments
* projects where savings have resulted; remaining projects will be re-budgeted
Prepared by: Leisure Services Address: 2200 Bunker Hill Rd Phone: 589-4263
RESOLUTION NO.
RESOLUTION ADOPTING PLANS AND SPECIFICATIONS
WHEREAS, on the 7th day of May, 2001, plans, specifications, form of contract and
estimated cost were filed with the City Clerk of Dubuque, Iowa for the FLORA AND
SUTTON POOLS WATER PLAYGROUND CONSTRUCTION PROJECT.
WHEREAS, notice of hearing on plans, specifications, form of contract, and
estimated cost was published as required by law.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
That the said plans, specifications, form of contract and estimated cost are hereby
approved as the plans, specifications, form of contract and estimated cost for said
improvements for said project.
Passed, approved and adopted this day of ,2001.
Attest:
Terrance M. Duggan, Mayor
Jeanne F. Schneider, City Clerk
PK
~ by: Leisure Services
Address: 2200 Bunker Hill Rd
Phone: 589-4263
RESOLUTION NO.
AWARDING CONTRACT
WHEREAS, sealed proposals have been submitted by contractors for the FLORA
AND SUTTON POOLS WATER PLAYGROUNDS CONSTRUCTION PROJECT pursuant
to Resolution No. 184-01, and notice to bidders published in a newspaper published in the
City of Dubuque, Iowa, on the 11th day of May, 2001.
WHEREAS, said sealed proposals were opened and read on the 5t~ day of June,
2001, and it has been determined that the bid of PORTZEN CONSTRUCTION, in the
amount of $725,021.00 was the lowest bid for the furnishings of all labor and materials and
performing the work as provided for in the plans and specifications.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
That the contract for the above improvement be awarded to PORTZEN
CONSTRUCTION, and the Manager be and is hereby directed to execute a contract on
behalf of the City of Dubuque for the complete performance of the work.
BE IT FURTHER RESOLVED:
That upon the signing of said contract and the approval of the contractor's bond, the
City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful
bidders.
Passed, approved and adopted this day of
,2001.
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, City Clerk
PK
CITY OF DUBUQUE, IOWA
MEMORANDUM
April 30, 2001
/
TO:
FROM:
SUBJECT:
The Honorable Mayor and City Council Members
Michael C. Van Miliigen, City Manager
Flora Pool and Sutton Pool Water Playgrounds
Leisure Services Manager Gil Spence recommends approval of the attached resolutions
to initiate the public bidding procedure for construction of the water playgrounds at Flora
and Sutton Pools and that a public hearing be set for June 18, 2001.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
, (,
Michael C. VarfMilligen' ~ - ~
MCVM/jh
Attachment
cc: Barry Lindahl, Corporation Counsel
Gil [3. Spence, Leisure Services Manager
CITY OF DUBUQUE, IOWA
MEMORANDUM
Apdl20,2001
TO: Michael C. Van Milligen, City Manager
FROM: Gil D. Spence, Leisure Services Manager~
SUBJECT: Flora Pool and Sutton Pool Water Playgrounds
INTRODUCTION
The purpose of this memorandum is to request that the City Council initiate the bidding
process for construction of the water playgrounds at Flora and Sutton Pools.
DISCUSSION
The FY 2001 C.I.P. budget includes $262,500 and the FY 2002 C.LP. budget includes
$439,000 to design and construct water playgrounds at Sutton and Flora Pools.
The bidding scheduled outlined in the attached resolutions would be as follows:
Presentation to City Council
Notice to bidders
Receive bids
Notice of public headng
Public heating and award contract
May 7,2001
May 11,2001
June 5, 2001
June 8,2001
June 18, 2001
ACTION STEP
The action requested is that the City Council adopt the attached resolutions giving
preliminary approval to the plans and specifications, authorizing the advertisement for
proposals, and establishing a date for the public hearing.
GDS:et
attachments
Prepared by: Leisure Services
Address: 2200 Bunker Hill Rd
Phone: 589,-4263
RESOLUTION NO.
ORDERING BIDS
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF DUBUQUE, IOWA:
That the SUTTON POOL AND
CONSTRUCTION PROJECT is hereby
construction.
FLOR~ POOL WATER PLAYGROUNDS
ordered to be advertised for bids for
BE IT FURTHER RESOLVED, that the amount of the secudty to accompany
each bid shall be in an amount which shall conform to the provisions of the notice to
bidders hereby approved as a part of the plans and specifications heretofore adopted.
That the City Clerk is hereby directed to advertise for bids for the construction of
the improvements herein provided, to be published in a newspaper having general
circulation in the City of Dubuque, Iowa, which notice shall not be less than four days
nor more than twenty days prior to the receipt of said bids at 2:00 p.m. on the 5th day of
June, 2001. Bids shall be opened and read by the City Clerk at said time and will be
submitted to the Council for final action at 6:30 p.m. on the 18th day of June, 2001.
Passed, approved and adopted this day of
,2001.
Terrance M Duggan, Mayor
Attest:
Jeanne F. Schneider, City Clerk
PK
Prepared by: Leisure Services
Address: 2200 Bunker Hill R__d
Phone: 589-4263
RESOLUTION NO.
FIXING DATE OF HEARING ON PLANS AND SPECIFICATIONS
WHEREAS, the City COuncil of the City of Dubuque, Iowa has given its
preliminary approval on the proposed plans, specifications, and form of contract and
placed same on file in the office of the City Clerk for public inspection of the SU-I-FON
POOL AND FLORA POOL WATER PLAYGROUNDS CQNSTRUCTION PROJECT.
NOW, THEREFORE, BE IT RESOLVED, BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA, that on the 18th day of June, 2001, a public hearing will be
held at 6:30 p.m. in the Public Library Auditorium, at which time interested persons may
appear and be heard for or against the proposed plans and specifications, form of
contract and cost of said improvement, and the City Clerk be and is hereby directed to
cause a notice of time and place of such headng to be published in a newspaper having
general circulation in the City of Dubuque, Iowa, which notice shall be not less than four
days nor more than twenty days pdor to the' day fixed for its consideration. At the
headng, any interested person may appear and file objections to the proposed plans,
specifications, contract, or estimated cost of the improvement.
Passed, approved and adopted this day of
,2001.
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, City Clerk
PK
Prepared by: Leisure Services Address: 2200 Bunker Hill Rd Phone: 589-4263
RESOLUTION NO,
PRELIMINARY APPROVAL OF PLANS AND SPECIFICATIONS
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE,
IOWA:
That the proposed plans, specifications, form of contract and estimated cost for
the SUTTON POOL AND FLORA POOL WATER PLAYGROUNDS CONSTRUCTION
PROJECT, in the estimated amount of $645,380, are hereby approved and ordered
filed in the ofr~ce of the City Clerk, for public inspection.
Passed, approved and adopted this day of ,2001.
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, City Clerk
PK
Prepared ~ Leisure Services
Address: 2200 Bunker Hill Rd
Phone: 589--4263
· NOTICE OF HEARING ON PLANS AND SPECIFICATIONS
Notice of public headng on proposed plans and specifications, proposed form of
contract and estimate of cost for the SUTTON POOL AND FLORA POOL WATER
PLAYGROUNDS CONSTRUCTION PROJECT.
NOTICE IS HEREBY GIVEN: The City Council of Dubuque, Iowa will hold a
public hearing on the proposed plans, specifications, form of contract and estimate of
cost for the SUTTON POOL AND FLORA POOL WATER PLAYGROUNDS
CONSTRUCTION PROJECT, in accordance with the provisions of Chapter 384, City
Code of Iowa, at 6:30 p.m. on the 18th day of June, 2001, in the Public Library
Auditorium in Dubuque, Iowa. Said proposed plans, specifications, form of contract and
estimate of cost are now on file in the office of the City Clerk. At said hearing any
interested person may appear and file objections thereto or to the cost of the
improvements.
Published by order of the City Council given on the day of
,2001.
Jeanne F. Schneider
City Clerk
PK