Madison, Gay, and Jefferson Park Playground ReplacementsCity of Dubuque
City Council
/_[QIfQ►III=1Ji6'1314
Copyrighted
October 6, 2025
ITEM TITLE: Madison, Gay, and Jefferson Park Playground Replacements
SUMMARY: City Manager recommending approval of Madison, Gay, and
Jefferson Park Playground Replacements Projects that are
not currently included or do not have enough funding to
complete the projects in the Fiscal Year 2026 budget.
SUGGUESTED Receive and File; Approve
DISPOSITION:
ATTACHMENTS:
1. MVM Memo
2. Staff Memo
Page 1234 of 1264
OF
THE CDtUB
Dubuque
E
Masterpiece on the Mississippi
zoo2-2013
2017*2019
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Madison, Gay, and Jefferson Park Playground Replacements
DATE: September 30, 2025
Parks and Recreation Director Matthew Kalcevich is recommending approval of
Madison, Gay, and Jefferson Park Playground Replacements Projects that are not
currently included or do not have enough funding to complete the projects in the Fiscal
Year 2026 budget.
Playgrounds have recently been replaced at Avon Park and Welu Park. Based on the
replacement costs of those playground structures including a poured in place rubber
surfacing under the playground, it is estimated to cost $194,000 to replace the
playground at Madison Park. It is estimated to cost $266,736 to replace the playground
at Gay Park. It is estimated to cost $230,000 to replace the playground at Jefferson
Park.
There is $175,742 funded in the Fiscal Year 2025 budget being requested to carryover
as part of the Fiscal Year 2026 first budget amendment for playground replacements at
Madison and Gay Parks. The additional funding needed of $514,994 for playground
replacement projects would be provided from Fiscal Year 2025 general fund savings.
The Madison, Gay, and Jefferson Playground Replacement projects are included in
Fiscal Year 2026 first budget amendment that will be considered by City Council at a
future public hearing.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Michael C. Van Milligen
MCVM/jml/sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Jennifer Larson, Chief Financial Officer
Laura Bendorf, Budget Manager
Matthew Kalcevich, Parks and Recreation Director
Page 1235 of 1264
THE CITY OF
DUB E
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Matthew K. Kalcevich, Parks and Recreation Director
SUBJECT: Madison, Gay, and Jefferson Park Playground Replacements
DATE: September 29, 2025
INTRODUCTION
Dubuque
MI-Amedea City
tllll®r
2007-2012.2013
2017*2019
The purpose of this memo is to request funding from the FY26 Budget Amendment #1
for playground replacements at Madison, Gay, and Jefferson Parks.
BACKGROUND
There is currently $85,800 in CIP project #3043000010 to fund the replacement of a
playground structure including poured in place rubber surfacing at Madison Park. This
funding is being requested to carryover as a part of FY26 Budget Amendment #1. The
standard replacement cycle of a playground is 10 years, and this site is past due.
There is currently $89,942 in CIP project #3043000067 to fund the replacement of a
playground structure including poured in place rubber surfacing at Gay Park. This
funding is being requested to carryover as a part of FY26 Budget Amendment #1. The
standard replacement cycle of a playground is 10 years, and this site is past due.
There is currently no funding budgeted for the replacement of Jefferson Park
playground including poured in place rubber surfacing. In 2025, the retaining wall on
Jefferson Street was replaced and new sidewalks, stairs, railings, and fencing were
installed. A new park sign was also installed. The last piece to be updated in the park
is the playground. The standard replacement cycle of a playground is 10 years, and
this site is past due
Page 1236 of 1264
DISCUSSION
Steve Fehsal, Park Division Manager, and Marie Ware, Acting Projects and Facilities
Manager have prepared cost estimates to replace playgrounds. Playgrounds have
recently been replaced at Avon Park and Welu Park. Based on the replacement costs
of those playground structures including a poured in place rubber surfacing under the
playground, it is estimated to cost $194,000 to replace the playground at Madison Park.
It is estimated to cost $266,736 to replace the playground at Gay Park. It is estimated
to cost $230,000 to replace the playground at Jefferson Park.
BUDGET IMPACT
Project
Current Funding
Additional Funding
Total Project Cost
Madison Park
$85,800
$108,200
$194,000
Playground
Replacement
Gay Park
$89,942
$176,794
$266,736
Playground
Replacement
Jefferson
$0
$230,000
$230,000
Park
Playground
Replacement
ACTION REQUESTED
I respectfully request $690,736 in total funding from the FY26 Budget Amendment #1
for playground replacements at Madison, Gay, and Jefferson Parks.
Prepared by Steve Fehsal, Park Division Manager
Cc; Jenny Larson, Chief Financial Officer
Laura Bendorf, Budget Manager
Marie Ware, Acting Project and Facilities Manager
0