Loading...
Ambassador Court Storm Sewer Replacement Project - Initiate Public Bidding Process and Setting Date for a Public HearingCity of Dubuque City Council Copyrighted October 20, 2025 kIW44&1Ai797:A1l1 311102:W_1NIZICIZIP ITEM TITLE: Ambassador Court Storm Sewer Replacement Project - Initiate Public Bidding Process and Setting Date for a Public Hearing SUMMARY: City Manager recommending City Council authorize the public bidding process and set a public hearing for November 3, 2025, and to preliminarily approve the plans, specifications, form of contract, and estimated cost of $161,038.13 for the Ambassador Court Storm Sewer Replacement Project through the adoption of the attached resolution. RESOLUTION Ambassador Court Storm Sewer Replacement Project: Preliminary Approval Of Plans, Specifications, Form Of Contract, And Estimated Cost; Setting Date Of Public Hearing On Plans, Specifications, Form Of Contract, And Estimated Cost; And Ordering The Advertisement For Bids SUGGUESTED Receive and File; Adopt Resolution(s), Set Public Hearing for DISPOSITION: November 3, 2025 ATTACHMENTS: 1. MVM Memo 2. 2025-10-15_AmbassadorCtStm-Initiate Memo 3. AmbassadorCtStm - Council Initiate Set PH RESOLUTION 4. AmbassadorCtStm - Notice of Hearing Page 479 of 817 THE CITY OF Dubuque DUB TEE All -America City Masterpiece on the Mississippi � pp 13 z°°'"*o zoi720zoi9 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Ambassador Court Storm Sewer Replacement Project Initiate Public Bidding Process and Setting Date for a Public Hearing Project No. 5586500036 DATE: October 15, 2025 City Engineer Gus Psihoyos is recommending City Council authorize the public bidding process and set a public hearing for November 3, 2025, and to preliminarily approve the plans, specifications, form of contract, and estimated cost of $128,830.50 for the Ambassador Court Storm Sewer Replacement Project through the adoption of the attached resolution. This project provides for the extension of 380 feet of storm sewer along Embassy West Drive to address a drainage issue on Ambassador Court. The current drainage system for Ambassador Court is tasked with accommodating drainage from parts of Pennsylvania and Embassy West Drive. Due to capacity issues, stormwater overwhelms the existing storm sewer such that stormwater will flow out of the system and flood Ambassador Court from curb to curb and flood an adjacent home and neighboring properties. Also the street is impassable during major rainfall occurrences. I concur with the recommendation and respectfully request Mayor and City Council approval. Mic ael C. Van Milligen MCVM:sv Attachment cc: Crenna Brumwell, City Attorney Cori Burbach, Assistant City Manager Gus Psihoyos, City Engineer Maxwell O'Brien, Civil Engineer Jenny Larson, Chief Financial Officer Laura Bendorf, Budget Manager Page 480 of 817 THE CF DU�j__B E Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer DATE: October 15, 2025 Dubuque A [America City II 2007-2012.2013 2017*2019 SUBJECT: Ambassador Court Storm Sewer Replacement Project Initiate Public Bidding Process and Setting Date for a Public Hearing Project No. 5586500036 INTRODUCTION This memorandum requests the City Council authorize initiating the bidding process and set a public hearing on November 3, 2025, for the Ambassador Court Storm Sewer Replacement Project. DISCUSSION This project provides for the extension of 380 feet of storm sewer along Embassy West Drive to address a drainage issue on Ambassador Court. The current drainage system for Ambassador Court is tasked with accommodating drainage from parts of Pennsylvania and Embassy West Drive. Due to capacity issues, stormwater overwhelms the existing storm sewer such that stormwater will flow out of the system and flood Ambassador Court from curb to curb and flood an adjacent home and neighboring properties. Also the street is impassable during major rainfall occurrences. PROJECT SCHEDULE The proposed schedule for the project is as follows: Initiate Public Bidding Process & Notice of Public Hearing October 20, 2025 Publish Notice to Bidders, Advertise for Bids October 22, 2025 Pre Bid Meeting October 30, 2025 Public Hearing on Plans & Specifications November 3, 2025 Receipt of Bid Proposals (Bid -Letting) November 6, 2025 Award Construction Contract November 17, 2025 Substantial Completion June 1, 2026 Final Project Completion Date June 30, 2026 RECOMMENDATION I recommend preliminary approval of the proposed plans, specifications, form of contract and construction estimate for the Ambassador Court Storm Sewer Replacement Project. I further recommend establishing the date of the public hearing and authorizing the Engineering Department to advertise for bids for the project. Page 481 of 817 BUDGET IMPACT The estimate of probable cost for the Ambassador Court Storm Sewer Replacement Project is summarized as follows: Descri lion Estimate Construction $ 128,830.50 Contingency 10% $ 12,883.05 Engineering 15% $ 19,324.58 Total Project Cost $ 161,038.13 The construction of the Ambassador Court Storm Sewer Replacement Project will be covered by the funding sources described below: Ambassador Court Storm Sewer Replacement Project Funding 5586500036 Embassy West Storm Sewer $ 153,000.00 Improvement Total Project Funding $ 153.000.00 Any project construction overages would be covered through a future budget amendment request through the CIP and amounts shown below, if needed. Future Budget Amendment Project Contingency Funding 5586500001 Storm Sewer Replacements $ 8,038.13 ACTION TO BE TAKEN I respectfully request the City Council authorize the public bidding process and set a public hearing for November 3, 2025, and to preliminarily approve the plans, specifications, form of contract and estimated cost for the Ambassador Court Storm Sewer Replacement Project through the adoption of the attached resolution. Prepared by Maxwell O'Brien, Civil Engineer cc: Jenny Larson, Chief Financial Officer Laura Bendorf, Budget Manager I Page 482 of 817 Prepared by Max O'Brien Civil Engineer 50 W 1311 St., Dubuque IA 52001 (563) 589-4270 Return to Adrienne N. Breitfelder, City Clerk, 50 W. 1311 St., Dubuque, IA 52001, (563) 589-4100 RESOLUTION NO. 341-25 AMBASSADOR COURT STORM SEWER REPLACEMENT PROJECT PRELIMINARY APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED COST; SETTING DATE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED COST; AND ORDERING THE ADVERTISEMENT FOR BIDS Whereas, the Ambassador Court Storm Sewer Replacement Project will provide for the extension of 380 feet of storm sewer along Embassy West Drive to address a drainage issue on Ambassador Court. The current drainage system for Ambassador Court is tasked with accommodating drainage from parts of Pennsylvania and Embassy West Drive. Due to capacity issues, stormwater overwhelms the existing storm sewer such that stormwater will flow out of the system and flood Ambassador Court from curb to curb and flooding adjacent homes. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: The proposed plans, specifications, form of contract and estimated cost for the Ambassador Court Storm Sewer Replacement Project in the estimated construction amount $ 128,830.50 are hereby preliminarily approved and ordered filed in the office of the City Clerk for public inspection. A public hearing will be held on the 3rd day of November, 2025, at 6:30 p.m. in the Historic Federal Building Council Chambers 350 W. 6th Street, Dubuque, Iowa, at which time interested persons may appear and be heard for or against the proposed plans and specifications, form of contract and estimated cost of said Project, and the City Clerk be and is hereby directed to cause the attached notice of the time and place of such hearing to be published in a newspaper having general circulation in the City of Dubuque, Iowa, which notice shall be published not less than four days nor more than twenty days prior to the date of such hearing. At the hearing, any interested person may appear and file objections to the proposed plans, specifications, form of contract, or estimated cost of the Project. The Ambassador Court Storm Sewer Replacement Project is hereby ordered to be advertised for bids for construction. The amount of the security to accompany each bid shall be in an amount which shall conform to the provisions of the Notice to Bidders hereby approved. The City Engineer is hereby directed to advertise for bids for the construction of the improvements herein provided, by publishing the Notice to Bidders to be published on the City of Dubuque website and a contractor plan room service with statewide circulation, which notice shall be published not less than thirteen but not more than forty- five days before the date for filing bids before 2:00 p.m. on the 6th day of November 2025. Bids shall be opened and read by the City Clerk at said time and will be submitted to the City Council for final action at 6:30 p.m. on the 17th day of November 2025, in the Historic Federal Building Council Chambers 350 West 6th Street, Dubuque, Iowa. Passed, adopted and approved this 20th day of October, 2025. �._ rad M. Cavan*h, Mayor Attest: � ,?"- �' I - I � � A e I � 2; 4�� �)'4- 64- Adrienne N. Breitfelder, City Clerk CITY OF DUBUQUE, IOWA OFFICIAL NOTICE PUBLIC NOTICE: is hereby given that the Dubuque City Council will conduct a public hearing on the 3rd day of November, 2025 at 6:30 p.m., in the Historic Federal Building, 350 W. 6t" Street, 2nd floor, Dubuque, Iowa, at which meeting the City Council proposes to hold a public hearing on the proposed plans, specifications, form of contract and estimated cost for the Ambassador Court Storm Sewer Replacement Project. The scope of the Project is as follows: The project provides for the extension of 380 feet of storm sewer along Embassy West Drive to address a drainage issue on Ambassador Court. The current drainage system for Ambassador Court is tasked with accommodating drainage from parts of Pennsylvania and Embassy West Drive. Due to capacity issues, stormwater overwhelms the existing storm sewer such that stormwater will flow out of the system and flood Ambassador Court from curb to curb and flooding adjacent homes. At the meeting, the City Council will receive oral and written comments from any resident or property owner of said City to the above action. The official City Council agenda will be posted the Friday before the meeting and will contain public input options. The agenda can be accessed at https://dubugueia.portal.civicclerk.com/ or by contacting the City Clerk's Office at 563-589-4100, ctyclerk@cityofdubuque.org. Written comments on the public hearing may be submitted to the City Clerk's Office by email at ctyclerk@cityofdubuque.org or by mail to City Hall, 50 W. 13t" St., Dubuque, IA 52001, before the scheduled hearing. The City Council will review all written comments at the time of the hearing. Documents related to the public hearing are on file in the City Clerk's Office and may be viewed Monday through Friday between 8:00 a.m. and 5:00 p.m. Individuals requiring special assistance should contact the City Clerk's Office as soon as feasible. Deaf or hard -of -hearing individuals can use Relay Iowa by dialing 711 or (800) 735-2942. Published by order of the City Council given on the 20t" day of October 2025. Adrienne N. Breitfelder, City Clerk Page 485 of 817