North Schmitt Island Collection System Project — Contract #1: Public Improvement Contract - Project AcceptanceCity of Dubuque
City Council
CONSENT ITEMS # 7.
Copyrighted
November 3, 2025
ITEM TITLE: North Schmitt Island Collection System Project — Contract #1:
Public Improvement Contract — Project Acceptance
SUMMARY: City Manager recommending City Council adopt the attached
resolution accepting the improvements and authorize the final
payment of the contract amount of $250,365.88 to Tschiggfrie
Excavating, for the North Schmitt Island Collection System
Project — Contract #1 Project.
RESOLUTION Accepting The North Schmitt Island Collection
System Project — Contract #1 Project And Authorizing The
Payment To The Contractor
SUGGUESTED Receive and File; Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
1. MVM Memo
2. Staff Memo
3. Resolution
4. Engineers Certificate of Completion
Page 89 of 525
THE CITY OF
DUBE
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: North Schmitt Island Collection System Project — Contract #1
Public Improvement Contract — Project Acceptance
Project No. 5581500049
DATE: October 29, 2025
Dubuque
AI WIN av
2007-2012.2013
2017*2019
City Engineer Gus Psihoyos is recommending City Council adopt the attached
resolution accepting the improvements and authorize the final payment of the contract
amount of $250,365.88 to Tschiggfrie Excavating, for the North Schmitt Island
Collection System Project — Contract #1 Project.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
v
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Maxwell O'Brien, Civil Engineer
Jenny Larson, Chief Financial Officer
Laura Bendorf, Budget Manager
Page 90 of 525
THE C
DUUB-.**--TE
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: North Schmitt Island Collection System Project — Contract #1
Public Improvement Contract — Project Acceptance
Project No. 5581500049
DATE: October 29, 2025
Dubuque
All -America City
2007-2012.2013
2017*2019
INTRODUCTION
The enclosed resolution provides for the acceptance of the construction contract for the
North Schmitt Island Collection System Project — Contract #1 Project.
BACKGROUND
The small portion of sewer replacements adjacent to the Key Hotel Expansion Project
was bid as North Schmitt Island Collection System Project — Contract #1. This project
provided for the installation of approximately 200 LF of sanitary sewer, in the area
located immediately adjacent to the Key Hotel Expansion Project on the north half of
Chaplain Schmitt Island.
DISCUSSION
The North Schmitt Island Collection System Project — Contract #1 Project was
completed by Tschiggfrie Excavating, of Dubuque, IA in the final contract amount of
$250,365.88. A 0.7% increase to the original contract amount of $248,560.00 was due
to unforeseen field conditions that required additional quantities of materials under the
contract unit prices.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment
of the final contract amount of $250,365.88 to Tschiggfrie Excavating for the North
Schmitt Island Collection System Project — Contract #1 Project.
BUDGET IMPACT
The summary of project costs for the North Schmitt Island Collection System Project —
Contract #1 Project is as follows:
Page 91 of 525
Description
Estimate
Award
Final
Construction
$
226,685.00
$
248,560.00
$ 250,365.88
Contingency (10%)
$
22,668.50
$
24,856.00
$ 0.00
Engineering Inspection Fees (5%)
$
11,334.25
$
12,428.00
$ 37,554.88
Total Project Cost
$
260,687.75
$
285,574.00
$ 287,920.76
The project funding is summarized below:
North Schmitt Island Collection System Project — Contract
#1 Funding
5581500049
Schmitt Island Sanitary Improvement
$ 287 920.76
(sanitary sewer construction funds)
Total Project Funding
$ 287,920.76
REQUESTED ACTION
The City Council is requested to adopt the attached resolution accepting the
improvements and authorize the final payment of the contract amount of $250,365.88 to
Tschiggfrie Excavating, for the North Schmitt Island Collection System Project —
Contract #1 Project.
Prepared by Maxwell O'Brien, Civil Engineer
cc: Jenny Larson, Chief Financial Officer
Laura Bendorf, Budget Manager
2
Page 92 of 525
Prepared by: Max O'Brien, City of Dubuque Engineering, 50 W. 13'" Street Dubuque IA 52001 (563)589-4270
Return to: Adreinne N. Breitbelder, City Clerk, 50W 131' Street, Dubuque, IA 52001 (563)589-4100
RESOLUTION NO. 352-25
ACCEPTING THE NORTH SCHMITT ISLAND COLLECTION SYSTEM PROJECT —
CONTRACT #1 PROJECT AND AUTHORIZING THE PAYMENT TO THE
CONTRACTOR
WHEREAS, the public improvement contract for the North Schmitt Island
Collection System Project — Contract #1 Project (the Project) has been completed by the
Contractor, Tschiggfrie Excavating, (Contractor), the City Engineer has examined the
work and recommends that the Project be accepted; and
WHEREAS, the final contract amount for the Project is $250,365.88; and
WHEREAS, the Contractor has previously been paid $242,854.90, leaving a
balance of $7,510.98; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved, and the
Project is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of $7,510.98 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa Code
chapter 26.13.
Passed, approved and adopted this 3rd day of
Attest:
Adrienne N. Breitfeldei, CMC City Clerk
November 2025.
Brad M. Cav ayor
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF NORTH SCHMITT
ISLAND COLLECTION SYSTEM PROJECT — CONTRACT #1 PROJECT
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has
inspected the North Schmitt Island Collection System Project — Contract #1 Project has
been performed in compliance with the terms of the Public Improvement Contract, and
that the total cost of the completed work is $287,920.76.
Dated this 27t" day of October 2025.
Gus Psihoyos, City Engineer
Filed in the office of the City Clerk on the 271" day of October 2025.
x" AVAIO�M'.'
Adrienne N. Breitfelder, City Clerk