Eagle Valley, Westbrook and English Ridge Subdivision Parks Development ProjectsCity of Dubuque City Council ACTION ITEMS # 3. Copyrighted November 3, 2025 ITEM TITLE: Eagle Valley, Westbrook and English Ridge Subdivison Parks Development Projects SUMMARY: City Manager recommending City Council adopt the attached resolution to accept the Eagle Valley, Westbrook, and English Ridge Subdivision Parks Development Project and authorize the payment of the contract amount of $735,897 to McDermott Excavating. RESOLUTION Accepting The Eagle Valley, Westbrook, And English Ridge Subdivision Parks Development Project And Authorizing The Payment Of The Contract Amount To The Contractor SUGGUESTED Receive and File; Adopt Resolution(s) DISPOSITION: ATTACHMENTS: 1. MVM Memo 2. Staff Memo 3. Resolution 4. Engineer Completion Letter Page 517 of 525 THE CITY OF DUBE Masterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Eagle Valley, Westbrook, and English Ridge Subdivision Parks Development Project Acceptance DATE: October 28, 2025 Dubuque AI WIN av 2007-2012.2013 2017*2019 Parks and Recreation Director Matthew Kalcevich is recommending City Council adopt the attached resolution to accept the Eagle Valley, Westbrook, and English Ridge Subdivision Parks Development Project and authorize the payment of the contract amount of $735,897 to McDermott Excavating. I concur with the recommendation and respectfully request Mayor and City Council approval. 1�,A� k�4 S4-zn" Mic ael C. Van Milligen MCVM:sv Attachment cc: Crenna Brumwell, City Attorney Cori Burbach, Assistant City Manager Matthew Kalcevich, Parks and Recreation Director Jennifer Larson, Chief Financial Officer Laura Bendorf, Budget Manager Marie Ware, Acting Project and Facilities Manager Page 518 of 525 THE CITY OF DUB E Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Manager FROM: Matthew K. Kalcevich, Parks and Recreation Director SUBJECT: Eagle Valley, Westbrook, and English Ridge Subdivision Parks Development Project Acceptance DATE: October 27, 2025 INTRODUCTION Dubuque All -America City 2007-2012.2013 2017*2019 The purpose of this memorandum is to recommend that the City Council accept the Eagle Valley, Westbrook, and English Ridge Subdivision Parks Development Project and approve the attached resolution. BACKGROUND The project involved the furnishing of labor and new materials for the construction of Eagle Valley, Westbrook, & English Ridge Parks and includes approximately; 949 CY of excavation; 366 Tons of granular subbase; 46 LF of curb and gutter; 11 SY of 4" HMA pavement; 662 SY of 4" PCC Sidewalk, 0.53 AC of conventional seeding, type 4; trees and plants; landscaping; 1,385 LF of filter socks; 680 CY of topsoil; three (3) park signs; 394 LF of split rail fence; 4,105 SF of pour -in -place safety surfacing; new park equipment; and 0.53 AC of hydraulic seeding. DISCUSSION The Eagle Valley, Westbrook, and English Ridge Subdivision Parks Development Project was completed by McDermott Excavating, of Dubuque, Iowa in the final contract amount of $735,897. The original contract amount was $719,550. The increase in cost of $16,347 was due to change orders related to nuclear density testing, rodent guards and concrete aprons on outlets of drain tiles, thickened edge sidewalk, additional sidewalk installation, additional embankment material, and additional drainage swale construction. Page 519 of 525 RECOMMENDATION I recommend that the City Council accept the Eagle Valley, Westbrook, and English Ridge Subdivision Parks Development Project and authorize the payment of the contract amount of $735,897 to McDermott Excavating based on the facts above. BUDGET IMPACT The summary of project costs for the Eagle Valley, Westbrook, and English Ridge Subdivision Parks Development Project is as follows: Construction Contract Award $719,550 The project funding summary is as follows: Project No. Fund Description 3043000027-100 Eagle Valley Park Dev 3043000028-100 Westbrook Park Development 3043000029-100 English Ridge Park ACTION STEP Final $735,897 Fund Amount $290,104.59 $287,492.25 $287,345.15 I respectfully request City Council adoption of the attached resolution to accept the Eagle Valley, Westbrook, and English Ridge Subdivision Parks Development Project and authorize the payment of the contract amount of $735,897 to McDermott Excavating. cc: Jennifer Larson, Chief Financial Officer Laura Bendorf, Budget Manager Marie Ware, Acting Project and Facilities Manager Attachment: Resolution 2 Page 520 of 525 Prepared by Matthew K. Kalcevich, 2200 Bunker Hill Rd Dubuque IA 52001 (563) 589-4264 Return to Adrienne N. Breitfelder, City Clerk, 50 W. 1311 St., Dubuque, IA 52001, (563) 589-4100 RESOLUTION NO. 362-25 ACCEPTING THE EAGLE VALLEY, WESTBROOK, AND ENGLISH RIDGE SUBDIVISION PARKS DEVELOPMENT PROJECT AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE CONTRACTOR WHEREAS, the Public Improvement Contract for the Eagle Valley, Westbrook, and English Ridge Subdivision Parks Development Project (the Project) has been completed by the contractor, McDermott Excavating. (Contractor) and WHKS has examined the work and filed a certificate stating that the Project has been completed according to the terms of the Public Improvement Contract and that WHKS recommends that the Project be accepted; and WHEREAS, the final contract amount for the Project is $735,897.00; and WHEREAS, the contractor has previously been paid $699,102.15, leaving a balance of $36,794.85; and WHEREAS, the City Council finds that the recommendation of WHKS should be accepted. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA THAT: Section 1. The recommendation of WHKS is approved, and the Project is hereby accepted. Section 2. The Chief Financial Officer is hereby directed to pay the balance of the retainage of $36,794.85 as provided in Iowa Code chapter 573, and to pay such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa chapter 26.13. Passed, approved, and adopted this 3rd day of November 2025. Brp�-—Cfavanagh, Mayor Attest: Adrienne N. Breitfelder, CIVIC City Clerk 801 Bluff Street, Suite 2C Dubuque,lA 52001 Phone: 563.239.9400 Email: eastdub@whks.com Website: www.whks.com October 27, 2025 Mr. Steve Fehsal Parks Division Manager Parks and Recreation Department 2200 Bunker Hill Road Dubuque, IA 52001 RE: Dubuque, Iowa Eagle Valley, Westbrook, and English Ridge Parks Letter Recommending Project Acceptance Dear Mr. Fehsal: whks engineers + planners + land surveyors McDermott Excavating has completed construction of the Eagle Valley, Westbrook, and English Ridge Parks project at a total cost of $735,897.00. The project included eight (8) change orders that added an additional $16,347.00 to the original bid amount of $719,550.00. The improvements were constructed in substantial compliance with the contract documents and authorized extra work. WHKS recommends that the City of Dubuque accept the construction project as complete. Once the City accepts the project as complete, final payment can be made to McDermott Excavating, after waiting a minimum of thirty days. The two-year maintenance bond and equipment warranties on this project will start with the City's acceptance of the project. Sincerely, WHKS & co. Kevin M. Podstawa, P.E. Project Manager Page 522 of 525