ITEM TITLE: Southwest Arterial / US 52 ITS Corridor Project Initiate Public
Bidding Process and Setting Date for a Public Hearing
SUMMARY: City Manager recommending City Council grant preliminary
approval of the construction plans and specifications;
estimated construction amount of $1,791,400.00 and
establish June 1, 2026, as the date of the public hearing; and
hereby authorized to advertise for bid proposals for the
Southwest Arterial / US 52 ITS Corridor Project.
RESOLUTION Southwest Arterial / Us 52 Its Corridor Project,
Preliminary Approval Of Plans, Specifications, Form Of
Contract, And Estimated Cost; Setting Date Of Public
Hearing On Plans, Specifications, Form Of Contract, And
Estimated Cost; And Ordering The Advertisement For Bids
SUGGUESTED Receive and File; Adopt Resolution(s), Set Public Hearing for
DISPOSITION: June 1, 2026
ATTACHMENTS:
1. MVM Memo Southwest Arterial _ US 52 ITS Corridor Project Initiate Public Bidding
Process and Set Date for PH
2. SW Arterial ITS Corridor Project - Initiate Bid Set PH Staff MEMO
3. SW Arterial ITS Corridor Project - Council Initiate Set PH RESOLUTION
4. SW Arterial ITS Corridor Project - Notice of Hearing
Page 657 of 890
Dubuque
THE CITY OF �
uhA�eMa cin
DuB E ; . � ,
I � � I.
Maste iece on the Mississi t 2oo�•zoiz•zois
�P Pp zoi�*zoi9
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Southwest Arterial / US 52 ITS Corridor Project Initiate Public Bidding
Process and Setting Date for a Public Hearing
lowa DOT Project No. ITS-032-1 (51)--25-31
Project No. 5521000033
DATE: May 14, 2026
City Engineer Gus Psihoyos is recommending City Council grant preliminary approval of
the construction plans and specifications; estimated construction amount of
$1,791,400.00 and establish June 1, 2026, as the date of the public hearing; and hereby
authorized to advertise for bid proposals for the Southwest Arterial / US 52 ITS Corridor
Project through adoption of the attached resolution.
The Southwest Arterial / US 52 ITS Corridor Project will provide for the installation and
integration of Intelligent Transportation System infrastructure throughout the Southwest
Arterial corridor. Improvements are anticipated to include fiber optic communications
infrastructure, traffic monitoring cameras, communications equipment, dynamic
message signs, associated electrical and network infrastructure, conduit systems,
handholes, cabinets, poles, and other related ITS technologies intended to improve
traffic operations, incident management, traveler information, and corridor efficiency.
The project includes a base bid and two alternate bid packages that provide flexibility in
construction implementation depending on final project costs and available funding. The
project generally consists of installation of fiber optic communications systems, conduit
and microduct infrastructure, traffic monitoring equipment, ITS field devices, and
associated electrical and communications infrastructure throughout the corridor.
The project will improve the City's ability to monitor and manage traffic operations along
the Southwest Arterial corridor and provide enhanced communication and coordination
between field devices and the City's Traffic Operations Center. The improvements are
also intended to support regional mobility, traveler information, incident response, and
future smart transportation initiatives.
Page 658 of 890
The proposed funding for the project is summarized in the following table:
Project Number Fund Description Fund Amount
City - SW Arterial ITS Corridor $ 123,000.00
5521000033
lowa DOT - Partnership Funding 1,900,000.00
5524000020 City Furnished Materials already acquired 277,600.00
5524000019 Broadband Acceleration and Universal 185,000.00
Access
5575000002 INET Fiber Replacement Buildout 125,000.00
5524000016 Street Camera Installation 33,100.00
Total Construction Project Funding $ 2,643,700.00
I concur with the recommendation and respectfully request Mayor and City Council
approval.
v
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Dave Ness, Civil Engineer III
Jenny Larson, Chief Financial Officer
Laura BendorF, Budget Manager
Bob Schiesl, Assistant City Engineer
Duane Richter, Traffic Project Supervisor
Justine Hull, Traffic Engineer
2
Page 659 of 890
Dubuque
THE CITY OF �
AIFAuriea Ciry
DuB E �� ,
I � � I.
Maste iece on the Mississi 1 zoo�•2oiz•zois
rP PP zoi�*zoi9
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
DATE: May 13, 2026
SUBJECT: Southwest Arterial / US 52 ITS Corridor Project
Initiate Public Bidding Process and Setting Date for a Public Hearing
lowa DOT Project No. ITS-032-1 (51)--25-31
Project No. 5521000033
INTRODUCTION
This memorandum requests the City Council approval and authorizes the initiation of the
public improvement construction bidding process and sets a public hearing date for June
1, 2026, for the Southwest Arterial / US 52 ITS Corridor Project.
BACKGROUND
In April 2020, the City of Dubuque and the lowa Department of Transportation entered
into a Cooperative Funding Agreement (Agreement No. 2020-16-033A) for the
development and implementation of an Intelligent Transportation System (ITS) along the
U.S. 52 / Southwest Arterial Corridor. The project corridor extends from U.S. 20 to U.S.
61/151 and includes the deployment of fiber optic communications infrastructure, traffic
cameras, sensors, dynamic message signs (DMS), and other ITS-related technologies.
In January 2022, the Cooperative Funding Agreement was amended to increase lowa
DOT participation due to increased costs associated with fiber optic cable and ITS
equipment. Under the agreement, the City is responsible for the design, construction,
operation, and maintenance of the ITS system, including fiber optic communications
infrastructure with reserved fiber strands for lowa DOT use.
The project has continued through design and coordination efforts between the City, lowa
DOT, and project consultants in preparation for implementation of the corridor ITS
improvements.
DISCUSSION
The Southwest Arterial / US 52 ITS Corridor Project will provide for the installation and
integration of Intelligent Transportation System infrastructure throughout the Southwest
Arterial corridor. Improvements are anticipated to include fiber optic communications
infrastructure, traffic monitoring cameras, communications equipment, dynamic message
signs, associated electrical and network infrastructure, conduit systems, handholes,
cabinets, poles, and other related ITS technologies intended to improve traffic operations,
incident management, traveler information, and corridor efficiency.
Page 660 of 890
The project includes a base bid and two alternate bid packages that provide flexibility in
construction implementation depending on final project costs and available funding. The
project generally consists of installation of fiber optic communications systems, conduit
and microduct infrastructure, traffic monitoring equipment, ITS field devices, and
associated electrical and communications infrastructure throughout the corridor.
The project will improve the City's ability to monitor and manage traffic operations along
the Southwest Arterial corridor and provide enhanced communication and coordination
between field devices and the City's Traffic Operations Center. The improvements are
also intended to support regional mobility, traveler information, incident response, and
future smart transportation initiatives.
PROJECT SCHEDULE
The project development schedule for the project will be as follows:
Initiate Public Bidding Process May 18, 2026
Publish Notice to Bidders, Advertise for Bids May 22, 2026
Notice of Public Hearing on Plans and Specs May 22,2026
Public Hearing on Plans and Specs June 1, 2026
Receipt of Bid Proposals June 11, 2026
Award Construction Contract June 15, 2026
Completion Date December 1, 2026
RECOMMENDATION
I recommend preliminary approval of the proposed plans, specifications, form of contract
and construction estimate for the Southwest Arterial / US 52 ITS Corridor Project. I further
recommend establishing the date of the public hearing and authorizing the Engineering
Department to advertise for bids for the project.
BUDGET IMPACT
The estimate of probable cost for the Southwest Arterial / US 52 ITS Corridor Project is
summarized in the following table:
PROJECT COSTS ESTIMATE
Construction - Base Bid $ 1,474,000.00
Construction - Bid Alternate No. 1 128,300.00
Construction - Bid Alternate No. 2 189,100.00
Construction - Bid Estimate Total 1,791,400.00
Contingency 268,800.00
Power Services Estimate 37,800.00
City Furnished Material 277,600.00
Consultant Design Services 165,000.00
Engineering Design and Administration 103,100.00
Total Project Cost $ 2,643,700.00
2
Page 661 of 890
The proposed funding for the project is summarized in the following table:
Project Number Fund Description Fund Amount
City - SW Arterial ITS Corridor $ 123,000.00
5521000033
lowa DOT - Partnership Funding 1,900,000.00
5524000020 City Furnished Materials already acquired 277,600.00
5524000019 Broadband Acceleration and Universal 185,000.00
Access
5575000002 INET Fiber Replacement Buildout 125,000.00
5524000016 Street Camera Installation 33,100.00
Total Construction Project Funding $ 2,643,700.00
ACTION TO BE TAKEN
I respectfully request that the City Council grant preliminary approval of the construction
plans and specifications; and establish June 1, 2026, as the date of the public hearing;
and hereby authorized to advertise for bid proposals for the Southwest Arterial / US 52
ITS Corridor Project through adoption of the attached resolution.
Prepared by Dave Ness, Civil Engineer III
cc: Jenny Larson, Chief Financial Officer
Laura BendorF, Budget Manager
Bob Schiesl, Assistant City Engineer
Dave Ness, Civil Engineer III
Duane Richter, Traffic Project Supervisor
Justine Hull, Traffic Engineer
F:\PROJECTS\SOUTHWEST ARTERIAL\ITS Corridor\Council and Staffllnitiate
3
Page 662 of 890
Prepared by David Ness City of Dubuque Engineering,50 W. 13th St. Dubuque, IA 52001 (563)589-4270
Return to Adrienne N.Breltfelder, City Clerk, 50 W. 1311 St., Dubuque, IA 52001,(563)589-4100
RESOLUTION NO. 197-26
SOUTHWEST ARTERIAL/ US 52 ITS CORRIDOR PROJECT
PRELIMINARY APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT,
AND ESTIMATED COST; SETTING DATE OF PUBLIC HEARING ON PLANS,
SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED COST; AND ORDERING
THE ADVERTISEMENT FOR BIDS
WHEREAS, the Southwest Arterial / US 52 ITS Corridor Project will provide for the
installation and integration of Intelligent Transportation System (ITS) infrastructure
throughout the Southwest Arterial corridor, including fiber optic communications
infrastructure, traffic monitoring cameras, communications equipment, dynamic message
signs (DMS), associated electrical and network infrastructure, conduit systems,
handholes, cabinets, poles, and other related ITS technologies intended to improve traffic
operations, incident management, traveler information, and corridor efficiency; and
WHEREAS, the project includes a base bid and two alternate bid packages
associated with installation of fiber optic communications systems, conduit and microduct
infrastructure, traffic monitoring equipment, ITS field devices, and associated electrical
and communications infrastructure throughout the corridor.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
The proposed plans, specifications, form of contract, and estimated cost for the
Southwest Arterial / US 52 ITS Corridor Project, in the estimated construction amount of
$1,791 ,400.00, are hereby preliminarily approved and ordered filed in the office of the City
Clerk for public inspection.
A public hearing will be held on the 1st day of June, 2026, at 6:30 p.m. in the Historic
Federal Building Council Chambers, 350 W. 6th Street, Dubuque, Iowa, at which time
interested persons may appear and be heard for or against the proposed plans and
specifications, form of contract, and estimated cost of said Project, and the City Clerk be
and is hereby directed to cause the attached notice of the time and place of such hearing
to be published in a newspaper having general circulation in the City of Dubuque, Iowa,
which notice shall be published not less than four days nor more than twenty days prior
to the date of such hearing. At the hearing, any interested person may appear and file
objections to the proposed plans, specifications, form of contract, or estimated cost of the
Project.
The Southwest Arterial / US 52 ITS Corridor Project is hereby ordered to be
advertised for bids for construction.
The amount of security to accompany each bid shall be in an amount which shall
conform to the provisions of the Notice to Bidders hereby approved.
The City Engineer is hereby directed to advertise for bids for the construction of the
improvements herein provided by publishing the Notice to Bidders on the City of Dubuque
website and a contractor plan room service with statewide circulation, which notice shall
be published not less than thirteen nor more than forty-five days before the date for filing
bids before 2:00 p.m. on the 11th day of June, 2026. Bids shall be opened and read by
the City Clerk at said time and will be submitted to the City Council for final action at 6:30
p.m. on the 15th day of June 2026, in the Historic Federal Building Council Chambers,
350 W. 6th Street, Dubuque, Iowa.
Passed, approved and adopted this 18th day of May 2026.
Attest: Brad WC,avanagh, Mayor
Trish L. Gleason, Assistant City Clerk
CITY OF DUBUQUE, IOWA
OFFICIAL NOTICE
PUBLIC NOTICE is hereby given that the Dubuque City Council will conduct a public
hearing on the 1St day of June, 2026, at 6:30 p.m., in the Historic Federal Building, 350
W. 6th Street, 2�d floor, Dubuque, lowa, at which meeting the City Council proposes to
hear the plans, specifications, form of contract and estimated cost for the Southwest
Arterial / US 52 ITS Corridor Project.
Scope of project: provide for the installation and integration of Intelligent Transportation
System (ITS) infrastructure throughout the Southwest Arterial corridor, including fiber
optic communications infrastructure, traffic monitoring cameras, communications
equipment, dynamic message signs (DMS), associated electrical and network
infrastructure, conduit systems, handholes, cabinets, poles, and other related ITS
technologies intended to improve traffic operations, incident management, traveler
information, and corridor efficiency. The project includes a base bid and two alternate bid
packages associated with installation of fiber optic communications systems, conduit and
microduct infrastructure, traffic monitoring equipment, ITS field devices, and associated
electrical and communications infrastructure throughout the corridor.
At the meeting, the City Council will receive oral and written comments from any resident
or property owner of said City to the above action. The official City Council agenda will be
posted the Friday before the meeting and will contain public input options. The agenda
can be accessed at https://dubuqueia.portal.civicclerk.com/ or by contacting the City
Clerk's Office at 563-589-4100, ctyclerk@cityofdubuque.org.
Written comments on the public hearing may be submitted to the City Clerk's Office by
email at ctyclerk@cityofdubuque.org or by mail to City Hall, 50 W. 13t" St., Dubuque, IA
52001, before the scheduled hearing. The City Council will review all written comments
at the time of the hearing.
Documents related to the public hearing are on file in the City Clerk's Office and may be
viewed Monday through Friday between 8:00 a.m. and 5:00 p.m.
Individuals requiring special assistance should contact the City Clerk's Office as soon as
feasible. Deaf or hard-of-hearing individuals can use Relay lowa by dialing 711 or (800)
735-2942.
Published by order of the City Council given on the 18th day of May 2026.
Trish L. Gleason, Assistant City Clerk
Page 665 of 890