Setting a Public Hearing on Dubuque Fire Headquarters Bunkroom Remodel Project Initiate Public Bidding Copyrighted
June 15, 2026
City of Dubuque ITEMS SET FOR PUBLIC HEARING # 4.
City Council
ITEM TITLE: Setting a Public Hearing on Dubuque Fire Headquarters
Bunkroom Remodel Project Initiate Public Bidding
SUMMARY: City Manager recommending setting a public hearing for July
6, 2026, for the preliminary approval of the construction
plans, estimated construction cost of$640,354.00, and
specifications; and hereby authorized to advertise for bid
proposals for the Dubuque Fire Headquarters Bunkroom
Remodel Project.
RESOLUTION Dubuque Fire Headquarters Bunkroom
Remodel Project, Preliminary Approval of Plans,
Specifications, Form of Contract, and Estimated Cost; Setting
Date of Public Hearing on Plans, Specifications, Form of
Contract, and Estimated Cost; and Ordering the
Advertisement for Bids
SUGGUESTED Receive and File; Adopt Resolution(s), Set Public Hearing for
DISPOSITION: July 6, 2026
ATTAC H M ENTS:
1. MVM Memo Dubuque Fire Headquarters Bunkroom Remodel Project Initiate Public
Bidding Process and set date PH
2. Dbq Fire Headquarters Bunkroom Remodel Project - Council Staff Initiate Set PH
MEMO
3. Dbq Fire Headquarters Bunkroom Remodel Project - Council Staff Initiate
Resolution
4. Dbq Fire Headquarters Bunkroom Remodel Project - Notice of Hearing
Page 1126 of 1594
Dubuque
THE CITY QF �
All•li�eriea Ciry
DLT B E ��, . �
�� � �
MaSt� Z�C� alZ t�Q Mt55ZSSZ Z zoa�•zoiz•zai3
�' pp zai�*zaig
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Dubuque Fire Headquarters Bunkroom Remodel Project
Initiate Public Bidding Process and Setting Date for a Public Hearing
Project No. 1315000025
DATE: June 10, 2026
Fire Chief Amy Scheller and Project Manager Jim Bousley are recommending City
Council grant preliminary approval of the construction plans, estimated construction cost
of$640,354.00, and specifications; and establish July 6, 2026, as the date of the public
hearing; and hereby authorized to advertise for bid proposals for the Dubuque Fire
Headquarters Bunkroom Remodel Project through adoption of the attached resolution.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Amy Scheller, Fire Chief
Jim Bousley, Project Manager
Gus Psihoyos, City Engineer
Bob Schiesl, Assistant City Engineer
Page 1127 of 1594
Dubuque
THE CITY OF �
AI•Amenea Cil�
D V i! JJ i inx u eii
����� � ►
� �
Maste iece on the Mississi i �°°'�Z°iz"z°13
� pp zoi�*�oi9
TO: Michael C. Van Milligen, City Manager
FROM: Amy Scheller, Fire Chief
Jim Bousley, Project Manager
SUBJECT: Dubuque Fire Headquarters Bunkroom Remodel Project
Initiate Public Bidding Process and Setting Date for a Public Hearing
Project No. 1315000025
DATE: June 9, 2026
INTRODUCTION
This memorandum requests the City Council approval and authorizes the initiation of
the public improvement construction bidding process and sets a public hearing date for
July 6, 2026, for the Dubuque Fire Headquarters Bunkroom Remodel Project.
BACKGROUND
The Fire Headquarters bunkroom and bathroom improvements were identified as a
major project within the City Council's 2024-2026 Goals and Priorities and is intended to
modernize firefighter living accommodations that support personnel assigned to 24-hour
shifts. The project received budget support in the FY25 CIP budget process. The project
will renovate the existing bunkroom and bathroom areas by converting two open-
concept dormitory sleeping areas into up to twelve individual bunkrooms and
reconfiguring existing restroom facilities into four private, lockable bathroom and shower
rooms. The project is intended to improve privacy, firefighter health and wellness,
fatigue mitigation, and overall workplace functionality. The completed project will
provide a modernized living environment that better supports firefighter wellness,
operational readiness, and the long-term functionality of Fire Headquarters.
Prior to advancing the project, the departments worked with industry partners to develop
preliminary concepts and obtain an opinion of probable construction costs to better
define the project scope and budget requirements. Following this work, the department
selected an architectural firm (FEH Design) to complete the design, code review, space
planning, construction documents, specifications, and cost estimating identified within
the project scope.
The Architectural Consultant has completed the required design and project
development work, and the project is now prepared to move into the next phase,
including initiation of the public bidding process, review of construction proposals, and
award of a construction contract. Pending bid results and contract award, construction is
anticipated to be completed by November 20, 2026.
Page 1 of 3
Page 1128 of 1594
DISCUSSION
The scope of the project will provide for the remodeling of existing Fire Headquarters
second floor includes the removal of plumbing fixtures, walls, doors, ceilings, and tile
flooring in existing group shower/restrooms; removal of existing lockers and integral
bases; removal of one fire pole and enclosing of associated floor opening; construction
of new individual shower/restrooms in location of former restrooms and individual
sleeping rooms in locations of former bunkrooms and locker room; upgrades to existing
hot water system; installation of electrical, lighting, and fire alarm devices associated
with aforementioned new construction.
PROJECT SCHEDULE
The project development schedule for the project will be as follows:
Initiate Public Bidding Process June 15, 2026
Publish Notice to Bidders, Advertise for Bids June 19, 2026
Notice of Public Hearing on Plans and Specs June 19, 2026
Public Hearing on Plans and Specs July 6, 2026
Receipt of Bid Proposals July 9, 2026
Award Construction Contract July 20, 2026
Completion Date November 20, 2026
RECOMMENDATION
I recommend preliminary approval of the proposed plans, specifications, form of
contract and construction estimate for the Dubuque Fire Headquarters Bunkroom
Remodel Project. I further recommend establishing the date of the public hearing and
authorizing the Engineering Department to advertise for bids for the project.
BUDGET IMPACT
The estimate of probable cost for the Dubuque Fire Headquarters Bunkroom Remodel
Project is summarized in the following table:
PROJECT COSTS ESTIMATE
Construction Contract $ 532,440
Contingency 53,244
Architectural Consultant Services - FEH Design 49,670
Engineering Dept Staff Services - Project Management 5,000
Total Project Cost $ 640,354
The proposed funding for the project is summarized in the following table:
Project No. Fund Description Fund Amount
1315000025 DBQ Fire Dept HQ Bunkroom Remodel Project $ 640,354
Total Project Funding $ 640,354
Page 2 of 3
Page 1129 of 1594
Funding for this project was included in the Fire Departments FY25 Budget, and the
funds were carried over and now available in FY26.
ACTION TO BE TAKEN
I respectfully request that the City Council grant preliminary approval of the construction
plans and specifications; and establish July 6, 2026, as the date of the public hearing;
and hereby authorized to advertise for bid proposals for the Dubuque Fire Headquarters
Bunkroom Remodel Project through adoption of the attached resolution.
Prepared by Jim Bousley, Project Manager
cc: Gus Psihoyos, City Engineer
Bob Schiesl, Assistant City Engineer
F:\PROJECTS\Fire Station 1 HQ\2026 Fire Dept HQ Bunkroom Remodel Project\Council Documents
Page 3 of 3
Page 1130 of 1594
Prepared by Jim Bousley, City of Dubuque Engineering,50 W. 13th St. Dubuque, IA 52001 (563)589-4270
Return to Adrienne N. Breitfelder, City Clerk, 50 W. 13t St., Dubuque, IA 52001,(563)589-4100
RESOLUTION NO. 250-26
DUBUQUE FIRE HEADQUARTERS BUNKROOM REMODEL PROJECT
PRELIMINARY APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT,
AND ESTIMATED COST; SETTING DATE OF PUBLIC HEARING ON PLANS,
SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED COST; AND
ORDERING THE ADVERTISEMENT FOR BIDS
WHEREAS, the project will include the remodeling of the existing second floor
including removal plumbing fixtures, walls, doors, ceilings, and tile flooring in existing
group shower/restrooms; removal of existing lockers and integral bases; removal of one
fire pole and enclosing of associated floor opening; construction of new individual
shower/restrooms in location of former restrooms and individual sleeping rooms in
locations of former bunkrooms and locker room; upgrades to existing hot water system;
installation of electrical, lighting, and fire alarm devices associated with aforementioned
new construction.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
The proposed plans, specifications, form of contract and estimated cost for the
Dubuque Fire Headquarters Bunkroom Remodel Project in the estimated construction
amount $640,354.00, are hereby preliminarily approved and ordered filed in the office of
the City Clerk for public inspection.
A public hearing will be held on the 6th day of July, 2026, at 6:30 p.m. in the
Historic Federal Building Council Chambers 350 W. 6th Street, Dubuque, Iowa, at which
time interested persons may appear and be heard for or against the proposed plans and
specifications, form of contract and estimated cost of said Project, and the City Clerk be
and is hereby directed to cause the attached notice of the time and place of such
hearing to be published in a newspaper having general circulation in the City of
Dubuque, Iowa, which notice shall be published not less than four days nor more than
twenty days prior to the date of such hearing. At the hearing, any interested person
may appear and file objections to the proposed plans, specifications, form of contract, or
estimated cost of the Project.
The Dubuque Fire Headquarters Bunkroom Remodel Project is hereby ordered
to be advertised for bids for construction.
The amount of the security to accompany each bid shall be in an amount which
shall conform to the provisions of the Notice to Bidders hereby approved.
The Dubuque Fire Headquarters Bunkroom Remodel Project is hereby directed
to advertise for bids for the construction of the improvements herein provided, by
publishing the Notice to Bidders to be published on the City of Dubuque website and a
contractor plan room service with statewide circulation, which shall be published not
less than thirteen but not more than forty-five days before the date for filing bids before
2:00 p.m. on the 9th day of July, 2026. Bids shall be opened and read by the City Clerk
at said time and will be submitted to the City Council for final action at 6:30 p.m. on the
20th day of July 2026, in the Historic Federal Building Council Chambers 350 West 6th
Street, Dubuque, Iowa.
Passed, approved and adopted this 15th day of June 2026.
� . i
d M. agh, Mayor
Attest:
Trish L. Gleason, Assistant City Clerk
CITY OF DUBUQUE, IOWA
OFFICIAL NOTICE
PUBLIC NOTICE is hereby given that the Dubuque City Council will conduct a public
hearing on the 6th day of July, 2026, at 6:30 p.m., in the Historic Federal Building, 350
W. 6t" Street, 2nd floor, Dubuque, lowa, at which meeting the City Council proposes to
hear the plans, specifications, form of contract and estimated cost for the Dubuque Fire
Headquarters Bunkroom Remodel Project.
At the meeting, the City Council will receive oral and written comments from any
resident or property owner of said City to the above action. The official City Council
agenda will be posted the Friday before the meeting and will contain public input
options. The agenda can be accessed at https://dubuqueia.portal.civicclerk.com/ or by
contacting the City Clerk's Office at 563-589-4100, ctyclerk@cityofdubuque.org.
Written comments on the public hearing may be submitted to the City Clerk's Office by
email at ctyclerk@cityofdubuque.org or by mail to City Hall, 50 W. 13t" St., Dubuque, IA
52001, before the scheduled hearing. The City Council will review all written comments
at the time of the hearing.
Documents related to the public hearing are on file in the City Clerk's Office and may be
viewed Monday through Friday between 8:00 a.m. and 5:00 p.m.
Individuals requiring special assistance should contact the City Clerk's Office as soon
as feasible. Deaf or hard-of-hearing individuals can use Relay lowa by dialing 711 or
(800) 735-2942.
Published by order of the City Council given on the 15t" day of June 2026.
Trish L. Gleason, Assistant City Clerk