Minutes Main St 8 6 01 Session700 Locust St.
Suite 942
RO. Box 509
Dubuque, lA
52001
319 583-9131
Fax: 319 557-9078
ww'~v, durrant.com
A Part of The
Durrant Group Inc.
Architecture
Engineering
Construction
Management
Planning
interiors
Austin, TX
Colorado Springs, CO
Denver, CO
Des Moines, IA
Dubuque, IA
Eau Claire, WI
Madison, WI
Minneapolis, MN
Phoenix, AZ
Sacramento, CA
San Antonio, TX
St. Charles, iL
St. Louis, MO
Vancouver, S.C.
Durrant
MEETING NOTES
01386.00
August 6, 2001
PROJECT:
Town Clock Plaza
Opening Main Street from 5th to 9th
City of Dubuque, Iowa
PARTCIPANTS:
Mayor Terry Duggan
John Markham
Cindy Steinhauser
Kevin Eippede
Mike Van Milligen Roy Buol Pat Cline
Ann Michalski Dan Nicholson Joe Robbins
Jeanne Schneider Barry Lindahl Mike Koch
Chris Wand Pat Norton
DISCUSSION:
The purpose of the meeting was to review the design development level plans and receive
direction from the council.
Mike Koch reviewed the design process leading up to the work session.
Mike Koch explained the basics of the design approach.
Mike Koch discussed the schedule, indicating that plans will be issued for bid in
November with bids received and contracts awarded in December.
Mike Koch introduced Kevin Eipperle of Durrant.
Kevin Eipperle presented the proposed plans. Specific points made:
a. Plans now show existing building entrances based on the survey information.
b. Three basicpremises.
L Two-way traffic.
ii. Parking on both sides of the street tailored to property owners.
iii. Town Clock to stay in its current location.
Additiona} gate kiosks added at 6th and 9th Streets.
Amenities:
i. Rhythm of light poles, trees, waste receptacles, benches, etc. in an
effort to recreate the feet of Main Street.
ii. Aluminum tree grates with bdck pavers as were installed on 5~h to
prevent tripping hazards and for a cleaner appearance.
iii. Ornamental railings similar to those at 3"~ and Main. They are nicely
designed and their use here would create continuity along the street: it
was noted that these are also similar to some of the railings in the
odginal library building.
iv. Use of limestone at the bases of the gate kiosks and planters as a way
to introduce this matedal native to the area into the project.
Kevin discussed the results of the public meetings of August 2.
a. The only main alteration as a result of those meetings was the conversion of
the parking spaces in front of American Trust from metered to drop-off.
Kevin discussed the variables that would influence the overall design as well as the
project cost.
Meeting Notes
August 6, 2001
01386.00
a. Paving for the sidewalks curbs and street:
i. Brick Pavers.
ii. Historic Brick Pavers.
iii. Colored Concrete.
iv. Standard Concrete.
v. Stamped Concrete.
b. Base of the Town Clock:
i. Paving Materials.
ii. Size.
iii. Existing versus similarly sized new.
Kevin discussed the area around the Town Clock, indicating how the current oval
shaped scheme provides room at the Tdlog and NICC buildings (10 to 12-feet and
15-feet respectively) and prevents people from being ab!e to easily make U-turns or
drive completely around the clock.
Pat Cline asked about the comparison between the oval at the clock as shown and
the roundabouts on Washington Street.
Both Mike and Kevin indicated that the oval would be much more
maneuverable.
10.
11.
Ann Michalski said she likes the use of regular concrete for the drive lanes of the
street, thereby accenting the other areas.
Joe Robbins expressed concern about the intersection at 8th and Main. He felt it
appeared uncontrolled.
Kevin indicated that stop signs would be installed to stop the traffic on 8t~ while
allowing traffic on Main to flow freely. He suggested that, as an exampte, the
council look at the intersections as they were constructed for 8th Street. He
pointed out that the colored concrete in the street actually helps to denote
where the crosswalks are and serve as a traffic calmer.
12.
Pat Cline asked about the cost difference between colored and standard concrete.
a. Kevin indicated that the cost is about double for colored.
b. Mike Koch confirmed that the cost for the concrete at the River's Edge Plaza
was more than double that of standard concrete.
13.
Ann Michalski asked about the diagonal parking in front of Graham's. She
questioned whether it would be a hazard.
Mike Koch stated that with the Iow volume and speed of the traffic as
envisioned on this street, he did not see the diagonal parking as a big concern.
He indicated that if it became a problem in the future, that the diagonal parking
could be eliminated and parallel stalls put in its place.
14.
Ann Michalski commented that she liked the amenity example photos as provided in
the council packet and the inclusion of existing elements in the plans. She stated
that she likes the area at 3~ and Main.
Meeting Notes
August6,2001
01386.00
15.
John Markham asked about how a light rail system might impact the design.
a. Kevin commented that sections of the paving would need to be removed if a
light rail system was to be installed in the future but that it could be
accommodated. He also stated that the radius of the oval under the clock
should be okay for it as well.
16.
Roy
a.
Buol asked about curbing in the area of the Town Clock.
Kevin indicated that there would be a standard curb around the oval. At the
outside of the area, the curb would be slight or eliminated and that it would
most likely be of a different color and texture to the street. He commented that
bollards would be used as a way to control traffic.
17.
Ann Michalski asked about snow removal in the area around the Town Clock.
a. Kevin commented that the reduced curb to the outside would allow snow to be
stockpiled as it currently is in the festival area.
18. Mike Koch explained the limits of the project; reiterating that the area on 7~h Street is
not included in this phase.
19. Roy Buol commented that he likes the design elements and the use of standard
concrete in the street.
20. Ann Michalski asked if these elements and amenities could be used in other areas of
downtown, especially north and south along Main Street.
a. Mike Koch indicated that, yes, these themes could be continued though some
minor variations may occur from block to block. He commented that the street
right-of-ways are pretty consistent, lending itself to the continuation of this
theme.
21.
22.
Dan Nicholson asked about the boltards.
a. Kevin pointed them out on the large plan, explaining that the bollards around
the clock within the oval would be lighted, the remainder would be unlighted.
John Markham raised the issue of relocating the Town Clock.
a. Pat Cline said it should stay where it is, that it gives the downtown an identity
and makes us different than other cities. She commented that the design of
the area around the c~ock was beautiful.
b. Mayor Duggan commented that moving the clock took the "heart" out of this
project.
c. John Markham agreed with Mayor Duggan's statement.
d. Ann Michalski indicated that she had received 20 phone calls regarding the
Town Clock: 13 in favor of leaving it in place, 7 in favor of moving it because it
was more historically accurate. She commented that all of the calls were very
positive in nature and the arguments for both sides were intelligently
presented.
Meeting Notes
August 6, 2001
01386.00
Joe Robbins pointed out that a fund raising effort was undertaken to pay for
the relocation when it was originally moved in 1971.
23.
24.
25.
Mayor Duggan summarized the discussion to this point. He stated that it seemed
there was consensus for the standard concrete in the street, the buff colored
sidewalk and red pavers or stamped concrete around the amenities.
Ann Michalski pointed out that ADA compatibility was very important to her and that
whatever surfaces were used needed to be easily traversed by people with
disabilities.
Dan NichOlson expressed a preference for colored concrete over the brick pavers
and asked about maintenance.
Kevin commented that the brick would be easier to repair if damage occurs.
He stated that colored concrete when damaged requires removal and new
concrete which would be difficult to match to the old. He pointed out that brick
pavers can be individually removed when broken and entire sections can be
removed and reinstalled when ground heaving causes uneven surfaces.
26.
27.
Mike Van Milligen commented that maintenance staff has indicated that stamped
concrete is easier to maintain and therefore preferred.
Ann Michalsid asked what would happen to the Continuum sculpture.
a. Mike Van Milligen stated that it is being removed as a part of this project, that it
would not be reinstalled in this general area and that a suitable location had
not yet been chosen for it.
28.
29.
Mike Koch stated that if the Town Clock is relocated, that another piece of public art
might need to take its place as a focal point on the street and as a backdrop for
festivals.
Mayor Duggan reiterated the question as to whether the Town Clock should stay or
go and asked whether the decision needed to be made at that time.
a. Mike Van Milligen stated that the decision can wait as long as it does not
cause a standstill in the plaza design process.
b. Kevin indicated that a one or two week delay in making that decision would not
delay the project.
30.
John Markham asked if the clock pedestal is in good condition or if it will require
major repair. He also inquired as to what the costs to the City might be to repair or
replace the pedestal as compared to moving the clock.
a. Mike Koch commented that the clock pedestal does have some spalling
concrete and cracks but that it is repairable.
b. Mike Koch and Kevin made the following points:
i. The cost would depend on fundraising efforts, successful grant
applications, etc.
ii. The demolition and removal of the existing pedestal and base would be
approximately $20,000.
Meeting Notes
August 6, 2001
01386.00
iii. The cost would be the same for the oval design as presented and a
straight street as the amount of specialized paving would remain about
the same.
iv. A repaired clock pedestal may appear patched though precautions could
be undertaken, such as requiring mock-ups ahead of time, which would
ensure the best match possible.
31.
Mayor Duggan concluded the meeting by thanking the design team and Ci~7 Staff
and deferring a decision on the relocation of the Town Clock until the regular council
meeting to follow.
The preceding constitutes our interpretation of matters discussed and decisions reached.
Please contact the undersigned for any omissions or discrepancies.
Project Architect
CC;
T. Duggan M. Van Milligen R. Buol P. Cline
J. Markham A. Michalski D. Nicholson J. Robbins
C. Steinhauser J. Schneider B. Lindahl M. Koch
K. Eipperle P. Norton D. Waugh L. Hawks
A. Holm E. Reiss
:mk. p:\projects\01\01386.00\wp~ntg\design\city coucil work session 8.6.01.doc