SW Arterial North Cascade Road Reconstruction Change Order No. 4Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Southwest Arterial Project
North Cascade Road Grading & Paving Project
Change Order No. 4 - Extend Project Limits
Iowa DOT Project No. HDP -2100 (655) - -71 -31
DATE: May 3, 2012
Dubuque
bierd
All-America City
1
2007
City Engineer Gus Psihoyos is recommending approval of Change Order No. 4 for the
Southwest Arterial Project North Cascade Road Grading and Paving Project to extend
the project limits by 542 feet at a cost of $325,267.69.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Michael C. Van Milligen
MCVM:sv
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
THE CITY OF
Dui �" E
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
DATE: May 2, 2012
SUBJECT: Southwest Arterial Project
North Cascade Road Grading &Paving Project
Change Order No. 4 - Extend Project Limits
Iowa DOT Project No. HDP -2100 (655)- -71 -31
INTRODUCTION
Dubuque
krtrd
All-AmericaCity
11111!
2007
This memo is a request for City Council approval of Change Order No. 4 and request
concurrence to extend the limits of the Southwest Arterial -North Cascade Road
grading and paving project for a distance of 542 feet south of its current project limits.
The background, benefits and justification for extending the project are summarized in
this memo.
BACKGROUND
The North Cascade Road grading and paving project was let on July 20, 2010, and was
awarded to C.J. Moyna &Sons, Inc. for a contract amount of $1,591,521.32. The
current project limits include the reconstruction (grading &paving) and realignment of
North Cascade Road for a distance of 2,988 feet.
The original scope of work included the development of a project that was 3,530 foot in
length. However just prior to bid letting, the project limits were adjusted to 2,988 feet as
a result of a delay in one property acquisition. All project development activities included
the entire 3,530 foot project segment.
Project Development Activities
A summary of the project development activities is as follows:
1. The Environmental Assessment included the entire North Cascade Road project.
The original construction project (3,530 feet) is covered by the EA and FONSI,
which was approved on Dec. 20, 2004.
2. The original cultural resources clearances included the original 3,530 foot project.
The construction limits are within the clearance boundary.
3. The original Concept Statement was submitted to Iowa DOT on January 4, 2010,
and included the entire 3,530 foot project.
4. The Preliminary Plans were submitted to Iowa DOT on January 11, 2010, and
included the entire 3,530 foot project.
5. The Check Plans were submitted to Iowa DOT on March 23, 2010, and included
the entire 3,530 foot project.
6. Subsequent to the Check Plan submittal, there was a delay in obtaining one
property on the project (Parcel 147 - Tigges). The final plans were modified to
stop short of this property, and the project was let accordingly.
7. At the time of the project revision, it was discussed with Iowa DOT that the City
would like to extend the project by change order if the Parcel 147 - Tigges
property was acquired. The Parcel 147 - Tigges property was acquired through
eminent domain proceedings on September 28, 2011.
Benefits of the Project Extension
There are several benefits to the public for extending the project to include the entire
3,530 feet limits:
1. The overall public expected the project to include these limits, as presented in
earlier public informational meetings.
2. The traveling public will benefit from completing the project now. If it is not
extended now, it will need to be added to a future construction contract, thus
disrupting traffic a second time for all travelers on North Cascade Road.
3. The adjacent property owners will benefit from completing the project now,
rather than experiencing the impacts of construction traffic, noise, air emissions,
etc. a second time in the future.
4. The taxpayers will benefit from completing the project now. Duplicate work
elements will be required if the extended area is added to a future construction
contract, specifically including the following. (Note that the estimates of actual
cost savings would be speculative, and are not included. Cost savings to the
taxpayers, however, are expected to be substantial.)
a. The prime contractor, CJ Moyna & Sons, has agreed to maintain their
contract units costs (2010) for the additional quantities to extend the
project limits.
b. If the project were to be bid today at current market value, the cost of
construction for the additional 542 feet would be approximately $419,500,
or an increase of 29% based on the Iowa DOT average unit costs
between March 2011 through February 2012.
c. A second mobilization will be required to move a new contractor onto the
project in the future.
d. A second setup of traffic control (signs, barricades, temporary signals,
etc.) will be required in the future.
e. A second construction inspection crew will be required in the future,
adding cost to the project.
f. More administrative time and cost will be required of the City and Iowa
DOT in the future, to administer a second construction contract.
Additional time and cost will be needed to develop a new set of
construction plans and bidding documents. The current project was
originally developed to include the entire 3,530 foot project, so the
extended area can be added to the current construction contract much
more easily.
g.
h. A new NPDES Permit would be required in the future, along with the cost
of the additional permit, the cost of implementing and monitoring the
erosion control requirements, and the associated administrative time by
Iowa DNR and City staff.
i. Temporary pavement, and subsequent removal of that pavement, is
included in the current construction plans, to allow construction to stop
short of the Tigges property. If the project is extended, this work will be
eliminated altogether.
j. Temporary pavement markings would need to be added now, and later
removed and re- painted, when the final project is completed.
5. The Sustainable Design objectives of the project will be met by extending the
project now. Unnecessary construction work (such as constructing and later
tearing out temporary pavement; moving in and out additional construction
equipment; and removing and later re- establishing traffic control) will be
eliminated, along with the resources and energy associated with those activities.
DISCUSSION
Based on the significant public benefits of extending the project now, and the lack of
any identified negative considerations, the City requested that the Iowa DOT and FHWA
approve the project limits extension.
On March 29, 2012 the City received concurrence from the Iowa DOT and FHWA to
extend the project limits extension for the Southwest Arterial - North Cascade Road
Grading & Paving Project which is compliant with the original project development
concept statement.
RECOMMENDATION
I recommend that the City Council approve Change Order No. 4 which will extend the
project limits an additional 542 feet to the south which will allow the Southwest Arterial -
North Cascade Road Grading & Paving Project to be fully completed under the current
construction contract as originally intended per the project development concept
statement.
BUDGET IMPACT
The estimate of probable cost for the Southwest Arterial - North Cascade Road Grading
& Paving Project, including Change Order No. 4 is as follows:
Original Construction Contract
Change Order No. 1
Change Order No. 2 - Deduct
Change Order No. 3
Change Order No. 4
Revised Construction Contract :
Amount
$ 1,591,521.32
6,351.00
- 17,500.00
1,500.00
325,267.69
$ 1,907,140.01
The project funding summary is as follows:
CIP Funding Source Amount
3001287 Federal SAFETEA -LU Funding (80 %) $ 1,525,712.01
3001287 City - Local Funding (20 %) 381,428.00
Total Project Funding $ 1,907.140.01
ACTION TO BE TAKEN
I respectfully request City Council approval and authorization for the City Engineer to
sign Change Order No. 4 which authorizes the project limits to be extended an
additional 542 feet to the south which will fully complete the Southwest Arterial - North
Cascade Road Grading & Paving Project as originally intended, Iowa DOT Project No.
HDP -2100 (655)-- 71 -31.
Prepared by: Robert Schiesl, Assistant City Engineer
cc: Jenny Larson, Budget Director
Kent Ellis, Iowa DOT
Bob Lentz, AECOM
F \PROJECTS \SW ARTERIAL - IA HYW 32 \North Cascade Road (655) - Grading & Paving \Change Orders\
SW Arterial - N Cascade Road Reconstruction (655) - Change Order No 4 - Council Approval Memo
Form 830240wd
7/06
'MUD` Iowa Department of Transportation
Non -
Change Order Part Part
Non - Substantial: ❑ ❑
No. 4 Substantial: ® ❑ March 30, 2012
Contract
Accounting ID No.: 28197 County Dubuque
Concurrence Date
Project No: HDP- 2100(655)- -71 -31
Kind of Work: P.C.C. Pavement — Grade / New Date Prepared: 03 -21 -12
Contractor: C.J. Moyna & Sons, Inc.
You are hereby authorized to make the following changes to the contract documents.
A - Description of change to be made or extra work to be done:
7003 Increase item for "Clearing and Grubbing ".
7004 Increase item for "Special Backfill ".
7005 Increase item for "Excavation, Class 10, Roadway and Borrow ".
7006 Increase item for "Excavation, Class 10, Unsuitable or Unstable Material ".
7007 Increase item for "Topsoil, Strip, Salvage and Spread ".
7008 Increase item for "Modified Subbase ".
7009 Increase item for "Granular Shoulders, Type B ".
7010 Increase item for "Paved Shoulder, Hot Mix Asphalt Mixture, 6 In. ".
7011 Increase item for "Shoulder Construction, Earth ".
7012 Increase item for "Excavation, Class 13, For Widening ".
7013 Increase item for "Standard or Slip Form Portland Cement Concrete Pavement, Class C, Class 3 Durability, 9 In. ".
7014 Increase item for "Hot Mix Asphalt, Driveway ".
7015 Decrease item for "Detour Pavement ".
7016 Increase item for "Surfacing, Driveway ".
7017 Increase item for "Excavation, Class 20, For Roadway Pipe Culvert".
7018 Increase item for "Aprons, Concrete, 24 In. Dia. ".
7019 Increase item for "Culvert, Concrete Roadway Pipe, 24 In. Dia. ".
7020 Increase item for "Aprons, Unclassified, 18 In. Dia. ".
7021 Increase item for "Culvert, Unclassified Entrance Pipe, 18 In. Dia. ".
7022 Increase item for "Subdrain, Longitudinal, (Shoulder) 4 In. Dia. ".
7023 Increase item for " Subdrain Outlet, RF -19E ".
7024 Increase item for "Engineering Fabric ".
7025 Increase item for "Erosion Stone ".
7026 Increase item for "Removal of Pavement ".
7027 Increase item for "Temporary Traffic Signals ".
7028 Increase item for "Concrete Slab Pipeline Protection ".
7029 Increase item for "Turf Reinforcement Mat ".
Extend the project 542 feet farther to the southwest. Project work will now begin at Station 2002 +60 instead of 2008 +02. The
work will conform to the design details shown in the Plans on various pages and denoted as "Parcel 147 ", "Future Construction ",
"NCR SR -1 ", "NRC SR -2 ", etc. All work is described by items that are already in the contract.
The working days for the project will be increased by 26 days, resulting in a new total of 156 working days. The added working
days are based on the ratio of the increased project costs to the awarded contract value (($325,267.69 / $1,591,521.32) x 130
working days).
Accounting ID No. 1 12 18 I 1 19 17
1 2 3 4 5 6
B — Reason for change or extra work:
The original Concept Statement for this project included this work. Due to a delay in acquiring one property, the as -bid project
limits were reduced to avoid this property. This Change Order extends the project limits to the original limits, as was shown in
the Public Informational Meetings and earlier project development documents. See letter dated 3/26/2012, located in the
project file, from the city of Dubuque to the District Local Systems Engineer that provides the benefits of performing the work
now versus later, validates that the various clearances are valid for the area of the added work, and provides a cost analysis of
of the added work.
Ci f D bugye, IA %
Approved j(% 'Ad
District Local Systems Engineer Date Project ngineer
Receipt is acknowledged of this change or extra work and terms of settlement are hereby agreed to.
Approved contingent upon funds being available under the existing
project agreement or upon additional Federal -aid funds being
made available by a modified project agreement.
Date For the Division Administrator
Federal Highway Administration
B
Approved
C.J. Moyna & Sons
Date
3/.30//2-
Date
Cr
4
Assistant Construction Engineer Date
DISTRIBUTION: Project Engineer — Forward original to District.
District — Nonsubstantial —Forward original and one copy to the Office of Construction and two copies back to the Project Engineer.
- Substantial - Forward original and two copies to the Office of Construction.
C -1 — Settlement for cost of work to be made as follows:
7003 -7029: Contract unit prices
C -2 — Justification for cost(s)
D - ITEMS INCLUDED IN CONTRACT
If Credit
Add "CR"
Change
No.
Line Item Number
Unit Price
xxx
Quantity
xxx
Amount
xx
7003
0020 Clearing and Grubbing
10.000
74.500
745.00
7004
0030 Special Backfill
13.000
410.900
5341.70
7005
0040 Excavation, Class 10, Roadway and Borrow
2.250
3574.000
8041.50
7006
0050 Excavation, Class 10, Unsuitable or Unstable
Material
2.250
452.000
1017.00
7007
0090 Topsoil, Strip, Salvage and Spread
3.500
2201.000
7703.50
7008
0100 Modified Subbase
27.000
1021.100
27569.70
7009
0110 Granular Shoulders, Type B
13.000
272.700
3545.10
7010
0140 Paved Shoulder, Hot Mix Asphalt Mixture, 6 In.
22.680
1593.200
36133.78
7011
0150 Shoulder Construction, Earth
175.000
19.000
3325.00
7012
0160 Excavation, Class 13, For Widening
15.000
73.000
1095.00
7013
0190 Standard or Slip Form Portland Cement Concrete
Pavement, Class C, Class 3 Durability, 9 In.
33.250
5225.200
173737.90
7014
0220 Hot Mix Asphalt, Driveway
23.460
191.700
4497.28
7015
0230 Detour Pavement
29.340
234.500 CR
6880.23
CR
7016
0250 Surfacing, Driveway
13.100
42.800
560.68
7017
0270 Excavation, Class 20, For Roadway Pipe Culvert
6.500
50.000
325.00
7018
0280 Aprons, Concrete, 24 In. Dia.
1000.000
2.000
2000.00
7019
0300 Culvert, Concrete Roadway Pipe, 24 In. Dia.
43.000
84.000
3612.00
7020
0310 Aprons, Unclassified, 18 In. Dia.
300.000
4.000
1200.00
7021
0320 Culvert, unclassified Entrance Pipe, 18 In. Dia.
25.000
210.000
5250.00
7022
0360 Subdrain, Longitudinal, (Shoulder) 4 In. Dia.
5.500
3550.000
19525.00
7023
0380 Subdrain Outlet, RF -19E
125.000
10.000
1250.00
7024
0460 Engineering Fabric
2.700
52.900
142.83
7025
0480 Erosion Stone
20.650
40.800
842.52
7026
0490 Removal of Pavement
4.300
2940.100
12642.43
7027
0650 Temporary Traffic Signals
1500.000
2.000
3000.00
7028
0690 Concrete Slab Pipeline Protection
180.000
40.000
7200.00
7029
0780 Turf Reinforcement Mat
11.250
164.000
1845.00
TOTAL
325267.69
E - ITEMS NOT INCLUDED IN CONTRACT
If Credit,
Add "CR"
Change
No.
Item Description
Item Number
Function
Code
Unit Price
.xxx
Quantity
.xxx
Amount
.xx