Loading...
Law Enforce C Exp - SupervisorsPHONE: 319-589-4441 FAX: 319-589-4478 The Honorable Terry Duggan Mayor, City of Dubuque 50 West 13th Street Dubuque IA 52001 Dear Terry: The Dubuque County Board of Supervisors has noted through the media that the Dubuque City Council, our partner in the construction of the addition to the Law Enforcement Center, has formally expressed concern about the design of the structure I ~nclose a copy of two October 5, 2001, responds facility, and notes that Bame, representatives of the City's COURTHOUSE DUBUQUE, IOWA 52001-7053 October 8, 2001 DONNA L. SMITH ALAN R. MANTERNACH JIM WALLER The first, dated about the design of the had met with the 1 Society in a The second, dated October alternates the Board ha: cost now at an and include ¢ costs for that that if Durrant 319 583-9131 Fax: 319 557~q078 A Part of The Durrant Group Inc. Architecture Engineering Construction Management Ptanning Interiors Austin, TX Colorado Springs, CO Denver, CO Dubuque, IA Eau C[alre, W~ Hat,land, WJ Madison, WI MinneapoJls, MN Pboeni×, AZ Sacramento, CA October 2, 2001 -REVISED, October 4, 2001 Mr. Jim Walleg Chairpemon Dubuque County Board ofSupervisom Dubuque County Courthouse Dubuque, lA 52001-7053 Re: Expansion - Dubuque County/City LEC Dear Jim: While meeting with Denise Dolan, Dubuque County Auditor, on Wednesday October 3 to review the status of dollars spent on project related work & professional services as compared to the total project budget, I noticed something that I overlooked when I prepared this odginal letter to the Supervisors. Specifically, in our last estimate dated 8/20/01 we had carried a line item cost of $175,000 for a Kitchen Equipment allowance from the previous estimate. This was identified as an allowance originally because we weren't cer[ain if the kitchen equipment would be purchased as part of this contract or by the food service provider the Sheriff's Office contracted with. Regardless, the dollars to equip the kitchen were identified, just not as part of the Base Bid dollars. As a result, we have modified the text in the letter to reflect this oversight. We have analyzed the bids that were opened and read aloud today and offer the following for review and subsequent action by the Supervisors. The last Estimate of Probable Cost submitted was on August 20, 2001 at the completion of the Construction Documents Phase. That estimate projected a Total Construction Cost of $7,746,197.00 which included a 7% Construction and Design Contingency of $506,761.00. Please note that at this stage of the project we would recommend reducing the 7% Construction and Design Contingency to a Construction Phase Contingency of about 4%. This would reduce the Contingency from $506,761 to $289,577. In addition, we included a separate line item cost for 2 Historic Preservation Issues; t) Sidewalk Upgrade at $4,000 & 2) Planters & Landscaping at $12,000 and a separate line item identified as Existing Building Renovation work in the existing LEC at $40,000. Additionally, there was a line item identified as Kitchen Equipment (Allowance) in the amount of $175,000.00. This last item was actually bid as part of the Base Bid work. Therefore, the total amount of dollars identified in our latest estimate for Base Bid Construction, Construction Phase Contingency and these aforementioned line item costs is $7,977,197.00. If our recommendation to reduce the contingency is approved as suggested above, the County could go to contract for $7,512,620 (Base Bid and Alternates 1 through 9) and still have $289,577 left for a construction contingency. In addition to the Base Bid, the bid documents also identified several Alternates: Expansion - Dubuque County/City LEC October 2, 200l Page 2 Alternate 1: increased the size of the footings to accommodate future third floor mezzanine; Alternate 2: Provided for decorative concrete sidewalks as suggested by the Histodc Preservation groups; Alternate 3: Provided for historic lighting along Central Avenue in front of the addition as suggested by the Histodc Preservation groups; Alternate 4: Provided for planters and landscaping along Central Avenue in front of the addition as suggested by the Historic Preservation groups; Alternate 5: Provides a double bunk in lieu of a single bed at all non-handicapped cells along the west wall of second floor and second floor mezzanine and increases the rated bed capacity by 22; Alternate 6: Provides a second desk and clothes hook assembly at all non- handicapped cells along the west wall of second floor and second floor mezzanine; Alternate 7: Provides a second single bed, desk and clothes .hook assembly at all handicapped cells along the west wall of second floor and increases the rated bed capacity by 2; Alternate 8: Provides concrete topping at the precast concrete plank floor of second floor mezzanines in the dorm areas; Alternate 9: Changes the pattern of some of the exterior brick masonry as suggested by the Historic Preservation groups; Alternate 10: Provides scored joints in the concrete sidewalks along Central Avenue as suggested by the Historic Preservation groups. The joint patterning was consistent with City of Dubuque's requirements, however, since bid documents have been released to the contractors the City's requirements have changed. Consideration for this Alternate is, therefore, not appropriate. Alternate 11: Provides for a deep geo-thermat well in lieu of a shallow well. The status of this Alternate will not be known until after the test well has been completed and the contractor makes a recommendation. A description of the Alternates can be summarized thus: Group A: Group B: Group C: Group D: Alternates I and 8 provide/facilitate future construction; Alternates 2, 3, 4, 9 and 10 respond to issues raised by Historic preservation groups; Alternates 5, 6 and 7 provide for an increase in the number of beds; and Alternate 11 is really an informational bid to facilitate a deep well for the geo-thermal system in the event a shallow well is not appropriate. Ten firms submitted bids on this project. A copy of the final bid tally sheet is attached for you to refer to. All bids submitted (except for the high bid) are within 8% of one another. Two firms - Taylor Ball from Cedar Rapids and Tdcon from Dubuque didn't indicate whether or not Alternates 1, 2 and 3 were additive or deductive. Following the bid opening, I contacted representatives from each firm. Both Mr. Tony Badding, Taylor Ball, and Mr. Ron Richards, Tricon, indicated that the Alternates in question were additive. Tdcon Construction from Dubuque submitted the iow base bid of $7,418,000.00. Prism Corp, Southwest, Kieler, WI was next with a base bid of $7,502,189.00 - $84,189.00 :rnk, p:~revised dubuque [ec recommendation.doc Expansion- Dubuque County/City LEC Ocober 2,2001 Page 3 more than Tricon. Discounting Alternates #10 & #11 for the reasons listed above, the total value of Alternates #1 through #9 was $128,400.00 from Tricon and $122,955.00 from Pdsm. In analyzing the bids, we looked at both base bid and alternates. Contractor Base Bid Group A Alt. Group B Alt. Group C Alt Total (Less #10) Tdcon $7,418,000 $47,000 $54,200 $27,200 $7;546,400 Pdsm $7,502,189 $53,132 $42,607 $27,216 $7,625,144 As indicated above, Tricon is the apparent iow bidder both by Base Bid and any combination of groupings of Alternates. Tricon's total for Base Bid and Alternate groupings A, B and C at $7,546,400 is $33,780.00 in excess of the $7,512,620.00 identified above. Based on the above information, Durrant recommends that the Supervisors direct Durrant to contact Tricon and request that the Contractor's Qualification Statement, AIA Document A305 1986 edition and Dubuque County Project Payroll Information be completed and submitted to Durrant's office no later than Friday October 5, 2001. Barney A. Bishop, AIA p, AIA cc: Alan Manternach, Supervisor Donna Smith, Supervisor :mk. p:\revised dubuque lec recommendation.doc , Durrant .Transmittal 7OOLocust. Suite942 Dubuque, LA 52001 (563} 583 - 9151 (563) 557 - 9078 www.durcant, corn Architecture Engineering Construction Management Planning Interiors A Part of The Durrant Group, Inc. Dubuque, LA Madison, Wl Eau CIafre, W[ Ha~and, W[ Date: To: August 27, 2001 Project: Jim Waller, Chair Dubuque County Board of Supervisors Dubuque County Courthouse Dubuque, IA 52001 From: Mike Ruden/ag Reference: CC: Donna Smith w/eric. Sent Via: Alan Mantemach w/enc. Jan Hess w/enc. Barney Bishop w/enc. File w/enc. Dubuque Law Enforcement Center Expansion Project No.: 01160.00 U.S. Mail Copies Description Remark Final Statement of Probable Cost I For Your Use Honolulu. HI Denver, CO Colorado Spdags. CO Minneapolis, MN Phoenix. AZ Sacramento, CA Comments: Durrant Dubuque City/County Law Enforcement Center cast Summary: Pre-Ref ~-- , 5/11100 duildinq Area (SF) 56,111 Div. Description I General Requirements 2 S[tework 3 Concrete, Fed & Structure ~t Masonry 5 Metals 0 Wood & Plastic 7 Thermal & Moisture Protection 8 Doors & Windows 9 Finishes 10 Speciaities 1 1 Equipment. Built-in Equipment 1 2 Furnishings. Casework 13 Special Construction t4 Conveying Systems 15 Mechanical Systems Sprinkler Plumbing HVAC 16 Electrical Systems Sub-Total Construction Cost Deslgn/Constr. Contingency SD 25% DO Final DD Final CD 3/12/0t 5/16/01 6/27/0I 8/20101 58,770 58,770 58470 58470 $514,509 $529,075 $542,225 $521,800 $521,800 $189,830 $299,406 $299,406 8299,406 $299,406 $1,269,318 $1,180,585 81,440,078 $1,440,078 $1,440,078 $843,191 $992,376 $1,064,249 $1,064,249 $1,064,249 $112,74I $119,194 $85,284 $85,284 $85.284 $I0,030 $11.754 $I1,754 $~1,754 $11,754 $79.475 $91,g30 $83,290 $83,290 $83,290 $327,503 $437,778 $346,093 $361,093 $36t,093 $272,074 $253.463 $219.297 $199,297 $199,297 810,453 $22,853 $8,228 $8,228 $8.228 $100.6t5 $62,194 $60,431 $92,989 $92,989 $I1,615 $23,508 $23,508 $23,508 $23,508 $38,813 $0 $0 $0 $0 $155,250 $125,000 $125,000 $125,000 $I25,000 $72,594 $91.530 ¢91,530 $91,530 $91,530 $546,699 $587,745 $627,095 $627,095. $627,095 $662,849 $996,061 $%072,462 $1,072,462 $1,072,482 $839,699 $949,038 $1,132,373 $1,132,373 $1,132,373 86,057,259 $6,753,489 $7,232,301 $7,239,436 $7,239,436 $664,458 $675,349 $542,423 $506,761 $506,76I $6,721,717 $7.428,838 $7,774,724 $7.746,197 $7,746,197 Total Construction Cost Additional Soft Cost: Performance Bond, L&M Payment Bond $64,286 $69,474 $69,474 $69,474 Site Survey & Sub-Surface investigation $7,500 $7,500 $7,500 $7,500 $7,500 A/E Design Fees $500,000 $465,000 $465,000 ¢463,858 $463.858 Kitchen Equipment (Allowance) $175,000 $175,000 $175,000 $175,000 $175,000 FF & E (Allowance) - Non Detention $150.000 $150,000 $150.000 $150,000 $150,000 $200,000 $200.000 ¢200,000 ¢229,4II $125,000 Incl. Above [nc[. Above Incl. Above $4,000 $4,000 $12,000 $I2,000 $12,000 840,000 $40,000 $40,000 Other: No work on Mote property is included. $0 Existing Building Abatement & Demolitic $229,4I 1 Foundation upgrade for additional story Incl. Above Historic Preservation Issues: Sidewalk Upgrade $4,000 Planters & Landscaping ¢ 12,000 Existing Building Renovations $40,000 Project Sub-Total $7,879.217 $8.546,62.4 $8,897,698 $8.897,44-0 $8.897,44-0 Special Foundation {Piles or Caissons) $0 $315,000 $0 $0 $0 Project Total $7,879,217 $8,861,624 $8,897.698 $8,897,440 $8,897,440 General Notes: Includes capabilities for vertical expansion of'Third Floor without mezzanine. Costs to relocate two (2) city water lines, Eighth S, treet, are not included.. 8/22/01 FinalDO%SPC.xts Durrant 700 Locust Street Suite 942 P.O. Sox 509 Dubuque, IA 52004-0509 319 583-9131 Fax: 319 557-9078 wv~v.d u rraet.corn A Part of The Durrant Group Inc. Architecture Engineering Construction Management Planning Interiors Colorado Springs, CO Denver, CO Eau Claire, Wi Madison, WI Minneapolis, MN Phoenix, AZ Sacramento, CA San Antonio, TX St. ChaHes, IL St. Louis, MO Vancouver, B.C. October 5, 2001 Mr. Jim Waller, Chairpemon Dubuque County Board ofSupervisom Dubuque County Cour[house Dubuque, lA 52001-7053 Re: Expansion - Dubuque LEC Dear Jim: I am in receipt of your letter dated October 1, 2001 and the attachment from Mr. Steve Hardie regarding the design of the proposed jail expansion. You have asked for my reaction to Mr. Hardie's letter as well as from phone calls one of the Supervisors has had from the membership of the City's Histodc Preservation Commission. Following is my response. At the Supervisods earlier request, I met with representatives from the City's Histodc Preservation Commission, The County Historical Society and other members of the community representing both the City and the County on February 14th at City Hall. The time and date of this meeting was coordinated through Mr. Guy Hemenway, City of Dubuque. I have attached a copy of the meeting notes and sign-in sheet for your reference. Chadie Glab, one of the participants, remarked that he thought the design elevation exhibited dudng this meeting was on the right track and that it only needed some relief on the Central Avenue elevation to break up the mass. At the conclusion of the meeting 6 items were identified by the audience that were thought to be of primary importance to the design of the jail. Those items are identified in the attached meeting notes. Durrant indicated at the conclusion of that meeting that we would investigate the cost impact of each of these items and report back to the Supervisors. Each of these items was subsequently reviewed with the Supervisors for cost impact and, as a result, all but 2 of the 6 items were incorporated into the bid documents - either as part of the Base Bid or by an Alternate. The 2 items that were abandoned as being too costly or inappropriate were Nos. 2 and 5. Item No. 2 involved consideration of either multiple colors of brick masonry or changing some brick to limestone. As par[ of the Base Bid, we specified multiple brick colors, however, since we are using the same brick that was used on the existing LEC, we want to be certain that the colors that are offered in this particular brick will compliment one another if we actually decide to introduce more than one color on the exterior fa(;ade. With respect to the limestone, we first felt that because of the mass of the addition, limestone in significant enough quantity would need to be introduced to have any type of impact and as such, cost became a real issue. On the other hand, Introducing limestone simply as ornamentation around windows would either be too insignificant in it's quantity to impact the elevations and/or have no relationship to the existing LEC. I woutd like to remind everyone that this project is an addition to the existing LEC - not the courthouse - and also that the area is not par[ of a historic district. Since no limestone has been used on the existing LEC and, considering that Dubuque LEC October 5, 2001 Page 2 the facility is remote from the courthouse but is a direct connection to the present jail, I suggest that there isn't any reason to introduce it on this addition. I also note by reviewing the photos of the buildings that were demolished that there was no limestone on these facilities either. Neither does the Central Fire Station at the corner of 9th and Central or any of the structures along the west side of Central Avenue in the vicinity of the Cour[house. As to the statement that there has been a lack of communication on Durrant's part about the plans (design), I would like to remind everyone that Durrant's contract is with Dubuque County - not the City or the various historic groups. Our first responsibility is to the County. In fact, it was the County that suggested Durrant participate in a meeting with the histodc preservation groups to review and discuss vadous issues of concern. I also believe the Supervisors have been quite diligent in posting notices of public hearings when formal reviews of the documents in a public forum have taken place. Yet I don't recall one time since that February 14 meeting seeing anyone at these public meetings reviewing the progress of the documents, asking questions or offedng comments. I would also remind those cdtical that the design reminds them of a "penitentiary" that this is first and foremost a jail. In addition to the normal and customary life safety issues as directed by building codes, there are additional requirements mandated by the Iowa Jail Standards - Standards that weren't even introduced until after the existing LEC had been designed and constructed. These codes and standards combined with the method of supervision of inmates, the constricted site and availability of funds, have all played a significant part in the design. As I suggested at the conclusion of our meeting on Tuesday, if you think it would be beneficial to understanding the architecture of the addition, Durrant can construct a model of the existing LEC, the .addition and the site for approximately $5,000.00. Upon notifi, ;a)ion to proceed we could have it completed in approximately one week. // S fCely, in ; y ~Bishop, AIA clos~ule cc: Alan Mantemach, Supervisor Donna Smith, Supervisor :mk. p:tprojects\01\01160.00\wp~corr~owner\waller october 5.doc 700 Locust Street Suite RO. BoxS09 Dubuque,~A 52004*0509 319 583~9131 Fax: 319 557-9079 A Part of The ant Group Inc. Architecture Engineer]rig Constructlo~ Management Planning Interiors Austin, TX Cotorado Springs, CO Denver, CO Dubuque, IA Eau Claire, WI Madison, WI Minneapolis, MN Phoenix, AZ San Antonio, TX St. Charles, iL St. Louis, MO MEETING NOTES 01160.00 FEBRUARY 14, 2001 PROJECT: Expansion - Dubuque LEC PARTICIPANTS: See Attached DISCUSSION: The purpose of the meeting was to review the concept design with the City and County historical groups and other interested citizens and receive their comments for further evaluation. Those in attendance offered the following comments and suggestions. 1. Some relief in the building mass should be accommodated at the Central Avenue facade. Minimal corbelling of the masonry might be considered as a recall of the existing LEC. 2. Consider a change in either color of masonry or partial change from brick to Dubuque Limestone. 3. Consider the use of a couple of colors of bdck; one for the main mass and one more subtle to help relieve the mass. 4. Consider detailing at window and door surrounds that wilt break up the massing. 5. Consider detailing ornamentation at roof edge that caps the top of the masonry in a more histodc nature. Consider the introduction of trees and other planting areas along Central Avenue. In part, this might include the elimination of one or more metered parking spaces to "open" up the front of the building. Barney Bishop will discuss the issue further with'the City. Note: Bamey Bishop received a phone call from Mike Van Milligen, City Manager, following the meeting suggesting that the issue of landscaping might include sidewalk treatment similar to that being accomplished along Eighth Street. This involves either colored and/or pressed concrete. This could also include "grated" tree planting areas. As the design efforts continue, Durrant will explore the application and cost impact of these various possibilities and discuss them further with the County Supervisors. The preceding constitutes our interpretation of matters discussed and decisions reached. Please contact the undersigned for any omissions or discrepancies. DUR/~ANT Barney A Bishop, AIA Principal c~.' J. Wailer, Supervisor M. Van Milligen, City Manager G. Hemenway (for distribution) A. O'Hare :mk.p:~rojects\01\01160.00\wp~mtg\desig n Ynt g 2.14.doc b Kennedy, Sheriff K. Runde, Chief Deputy K. Wadding, Police Chief T. Lambert, Assistant Chief M. Ruden J. Kolf Durrant