University Avenue Embankment Stabilization AcceptanceTHE CTTY OF I~~~ E Masterpiece Qn the Mississippi TO: The Wonorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: University Avenue Embankment Stabilization Projection Iowa DOT No. ER 2100 (636)--8R-31 CIP No. 3001080 DATE: January 15, 2008 Dubuque AN America City :~ 2007 City Engineer Gus Psihoyos is recommending acceptance of the University Avenue Embankment Stabilization Project, as completed by Connolly Construction, in the final contract amount of $356,739.39, which is a 16.9% increase from the original contract. Funds are available in the project budget to pay this additional expense. I concur with the recommendation and respectfully request Mayor and City Council approval. ~1. l~ .~~ Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Gus Psihoyas, City Engineer THE CITY OF Dubuque ._. DT TR ~ Ap•AmericaCity V l.J Masterpiece an tl~e Mississippi 2007 TO: Michael C. Van Milligen, City Mana FROM: Gus Psihoyos, City Engineer - SUBJECT: University Avenue Embankment Stabilization Project Iowa DOT No. ER 2100 (636)--8R-31 CIP No. 3001080 DATE: January 14, 2008 INTRODUCTION The enclosed resolution provides for the acceptance of the construction contract of the University Avenue Embankment Stabilization Project. BACKGROUND The completed project site is located in the 3300 block of University Avenue. On May 22, 2004 heavy rains resulted in a flooding event that adversely affected approximately 500 feet of embankment on the north side of University Avenue. The existing creek located along the bottom of the slope became flooded and caused the toe of the slope to erode, which caused the embankment slope to fail. The failed slope was in a near vertical position which had encroached within approximately four feet of the existing curb line at several locations. Within the road right-of-way there are several existing underground and overhead utilities in the immediate area of the embankment failure. These utilities are main service lines for much of the west end of Dubuque. Since the slope failure damages to University Avenue occurred on a minor arterial, as per the Federal Functional Classification System map for Dubuque, repairs were not FEMA eligible. Thus the City requested approval for Federal Emergency Repair (ER) Funding to complete the permanent repair work. In January 2006, the City received notification that the FHWA had approved the use of ER program funding for the University Avenue Embankment Stabilization Project. The University Avenue Embankment Stabilization Project provided for the relocation and realignment of the existing stream away from the existing embankment toe of slope. A new embankment was reconstructed to create a more stable 2.5:1 slope. The project also provided for the placement of stabilization stone and riprap on the embankment slope which will reinforce and prevent future erosion and scour. The project also required the removal and replacement of a section of the existing curb and gutter, asphalt pavement and guardrail along the top of the embankment supported roadway. RIGHT-OF-WAY ACQUISITION Due to the limited right-of-way adjacent to the project site and the need to relocate the existing stream to accommodate the construction of the armored slope, the acquisition of property from the abutting property owners was required. Permanent construction/ maintenance easements were acquired from two land owners. DISCUSSION The University Avenue Embankment Stabilization Project has been completed by Connolly Construction, Inc. of Peosta, Iowa, in the final contract amount of $356,739.39, which is a 16.9% increase from the original contract in the amount of $305,082.40. The following is a brief summary of the pre-existing deteriorated condition and justification to support the additional project related costs that were required to restore the embankment and roadway to an acceptable pre-damage condition. The existing embankment was in a near vertical slope and did not allow the contractor to properly bench the embankment without the potential risk of additional slope failure. Also, the potential impact to the existing overhead and underground utilities which are located along the top of the embankment also created an additional risk for slope failure. As a result, construction methods were modified and the contractor was directed to place additional stabilization stone as fill along the toe of the slope which reduced the potential for disturbance to the existing embankment and utilities. This stabilization stone quantity increase resulted in approximately $20,000 in additional costs to the project. When originally calculating plan quantities for the curb and asphalt pavement items based on the original July/August, 2004 survey data, the pavement repairs specified were approximately 3 ft. x 240 ft. of removal and replacement. However, by the time construction began in April 2007, the area that needed replacement grew to approximately 12.5 ft. x 310 ft. of pavement along the northerly curb line. As a result, additional quantities for curb and asphalt pavement repairs were necessary to restore the pavement due to the continuing failure of the unstable embankment. These quantity increases resulted in approximately $18,500 of additional costs to the project. Due to the steep embankment slope, the modification in construction methods and the inability for the contractor to maintain access from the bottom side, the contractor was required to work from the top side of the embankment. As a result of the top side construction, this required the removal and replacement of additional guardrail and the staging of construction equipment along the edge of the existing deteriorated pavement. The additional guardrail work resulted in approximately $11,000 of additional costs to the project. RECOMMENDATION I recommend that the City Council accept the improvements and authorize the payment of the contract amount of $356,739.39 to Connolly Construction, Inc. BUDGET IMPACT BUDGET IMPACT The project cost summary for the University Avenue Embankment Stabilization Project is as follows: Estimate Construction Contract $ 415,000.00 Contingency 41,500.00 Right-of-Way Acquisition 15,360.00 Engineering Design 22,936.00 Project Administration 20,000.00 Construction Engineering & Inspection 20,000.00 Total Project Cost $ 534,796.00 Bid Award $ 305,082.40 41,500.00 15,360.00 22,936.00 25,000.00 25,000.00 $ 434,878.40 Final $ 356,739.39 15,852.00 24,452.75 15,366.20 37,484.50 $ 449,894.84 The project funding summary is as follows: CIP No. Fund Description Amount Federal Emergency Relief (ER) Funding $ 223,543.93 3001080 University Slope Failure 226,350.91 Total Project Funding $ 449,894.84 The City budgeted funds for the project (University Slope Failure CIP - 3001080) that was used as the local match and for expenses that are not eligible for ER participation, such as right-of-way acquisition, engineering design, project administration, construction engineering and inspection services. ACTION TO BE TAKEN The City Council is requested to adopt the attached resolution to accept the improvements and to authorize the payment of the contract amount of $356,739.39 to Connolly Construction, Inc. Prepared by Robert Schiesl, Assistant City Engineer cc: Jenny Larson, Budget Director Ken TeKippe, Finance Director Ken Yanna, Assistant District Engineer, Iowa DOT Roger Walton, District Staff Engineer, Iowa DOT RESOLUTION NO. 16-08 ACCEPTING THE UNIVERSITY AVENUE STABILIZATION PROJECT (IOWA DOT NO. ER 2100 (636)--8R~31) AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE CONTRACTOR Whereas, the Public Improvement Contract for the University Avenue Stabilization Project (Iowa DOT No. ER 2100 (636)--8R-31) (the Project) has been completed and the City Engineer has examined the work and filed a certificate stating that the Project has been completed according to the terms of the Public Improvement Contract and that the City Engineer recommends that the Project be accepted; and NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor from the University Slope Failure Capital Improvement Project and the Federal Emergency Relief Funding for the contract amount of $356,739.39 less any retained percentage provided for therein as provided in Iowa Code chapter 573, and to pay such retainage only in accordance with the provisions of Iowa Code chapter 573. Passed, approved and adopted this 22nd day of January, 2008. Ric W. Jones, Mayor Pro-Tem Attest: Jeanne F. Schneider, CMC, City Clerk CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE UNIVERSITY AVENUE STABILIZATION PROJECT (IOWA DOT NO. ER 2100 (636)--8R-31) The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has inspected the University Avenue Stabilization Project (Iowa DOT No. ER 2100 (636)--8R-31), that the Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $449,894.84. Dated this 22nd day of January, 2008 Gus Psihoyos, City Engineer Filed in the office of the City Clerk on the 22n day of January, 2008 Jeanne F. Schneider, CMC, City Clerk City of Dubuque -Engineering Division Final Payment Form PAYMENT NO: COUNCIL FINAL PROJECT NAME: UNNERSITY AVENUE EMBANKMENT STABILIZATION PROJECT EMERGENCY REPAIR -EROSION IOWA DOT PROJECT NO. ER-2100 (636)-8R-31 DATE: January 11, 2008 CONTRACTOR: CONNOLLY CONSTRUCTION, INC. CONTRACT AMOUNT: S305,082.40 NO. ITEM CODE CONTRACT ITEM DESCRIPTION UNIT CONTRACT UNIT COST FINAL QUANTITY AMOUNT EARNED TO DATE 1 2101-0850001 CLEARING & GRUBBING ACRE $ 17,600.00 0.80 $ 14,080.00 2 2102-2710070 EXCAVATION, CLASS 10, ROADWAY & BORROW CY $ 6.44 5490 $ 35,355.60 3 4 2104-2713020 2105-8425015 EXCAVATION, CLASS 13, CHANNEL TOPSOIL, STRIP, SALVAGE, AND SPREAD CY CY $ $ 9.37 7.35 1700 1247 $ $ 15,929.00 9,165.45 5 6 7 2107-0875000 2210-0475290 2303-0021500 COMPACTION WITH MOISTURE AND DENSITY CONTROL MACADAM STONE BASE HOT MIX ASPHALT MIXTURE (300K ESAL) ,BASE COURSE, 1/2 IN CY TON TON $ $ $ 1.00 15.95 81.45 5490 534.71 94.10 $ $ $ 5,490.00 8,528.62 7,664.45 8 9 10 2303-0023500 2303-0246422 2303-0247028 HOT MIX ASPHALT MIXTURE (300K ESAL) ,INTERMEDIATE OR SURFACE COURSE, 1/2 IN, NO SPECIAL FRICTION REO ASPHALT BINDER, PG 64-22 ASPHALT BINDER, PG 70-28 TON TON TON $ $ $ 81.45 463.50 721.00 53.70 8.40 0.00 $ $ $ 4,373.87 3,893.40 _ 11 12 13 14 2307-0025003 2312-8260051 2401-6745650 2505-4008100 AGGREGATE, ROADWAY COVER, 318 IN. GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE REMOVAL OF EXISTING STRUCTURES REMOVAL OF GUARDRAIL TON TON LS LF $ $ $ $ 17.85 15.00 4,700.00 5.60 225.57 196.26 1.0 312 $ $ $ $ 4,026.42 2,943.90 4,700.00 1,747.20 15 16 17 2505-4008200 2507-3250005 2507-6800061 INSTALLATION OF GUARDRAIL ENGINEERING FABRIC REVETMENT, CLASS E LF SY TON $ $ $ 24.00 1.50 18.60 312 7531 3800.97 $ $ $ 7,4gg,00 11,296.50 70,698.04 18 2507-8029000 EROSION STONE TON $ 18.60 3963.80 $ 73,726.68 19 20 21 22 23 2510-6745850 2512-1725256 2526-8285000 2528-8400048 2528-8445110 REMOVAL OF PAVEMENT CURB AND GUTTER, PC, CONCRETE, 2.5 FT CONSTRUCTION SURVEY TEMPORARY BARRIER RAIL, CONCRETE TRAFFIC CONTROL SY LF LS LF LS $ $ $ $ $ 5.60 21.10 4,130.00 15.70 4,060.00 443 312 1.0 398 1.0 $ $ $ $ $ 2,480.80 6,583.20 4,130.00 6,248.60 4,060.00 24 25 2528-8445112 2533-4980005 FLAGGERS MOBILIZATION DAY LS $ $ 255.00 7,150.00 17 1.0 $ $ 4,335.00 7,150.00 26 2601-2634100 MULCHING ACRE $ 350.00 1.14 $ 399.00 27 28 2601-2636044 2602-0000020 SEEDING AND FERTILIZING (URBAN) SILT FENCE ACRE LF $ $ 1,570.00 2.40 0.24 795 $ $ 376.80 1,908.00 29 2602-0000060 REMOVAL OF SILT FENCE LF $ 1.05 1353 $ 1,420.65 30 2602-0000090 CLEAN OUT OF SILT FENCE LF $ 2.00 0.00 $ TOTAL AMOUNT EARNED TO DATE -BASE BID: S 320,199.18 CF#ANGE ORDER(S) -EXTRA VIIORK ITEMS 31 32 2507-6800061 2505-4008100 7001 -REVETMENT CLASS E (ITEM 0170 INCREASE) 7002 -REMOVAL OF GUARDRAIL (ITEM 0140 INCREASE) TON LF $ $ 18.60 5.60 1062.0 277.0 $ $ 19,753.20 1 551 20 33 34 35 2505-4008200 2599-9999017 2599-9999010 7003 -INSTALLATION OF GUARDRAIL (ITEM 0150 INCREASE) 7004 -REMOVAL & INSTALLATION OF FIELD FENCE (DELETE 8002) 6001 -REMOVABLE BLACK TAPE LF STA LS $ 24.00 $ (1,609.53) $ 700.00 202.0 0.84 1.0 $ $ $ , . 4,848.00 (1,352.00) 700.00 36 37 38 2599-9999017 2601-2636043 2102-2710080 8002 -REMOVAL & INSTALLATION OF FIELD FENCE 8003 -SEEDING & FERTILIZING (RURAL) 8004 -EXCAVATION, CL 10 UNSUITABLE STA ACRE CY $ $ $ 1,609.53 1,200.00 12.88 0.84 0.90 49.5 $ $ $ 1,352.00 1,080.00 637.56 39 40 2599-9999010 2599-9999017 8005 -REMOVAL OF EXCESS EMBANKMENT STOCKPILE MATERIAL 8002 -REMOVAL & INSTALLATION OF FIELD FENCE LS LS $ $ 6,618.25 1,352.00 1.0 1.0 $ $ 6,618.25 1,352.00 TOTAL AMOUNT EARNED TO DATE • CHANGE ORDERS: S 36,540.21 TOTAL AMOUNT EARNED TO DATE: S 356,739.39 TOTAL DUE CONTRACTOR: S 356,739.39 RIGHT-OF-WAY ACQUISITION: S 15,852.00 ENGINEERING DESIGN: S 24,452.75 PROJECT ADMINISTRATION: S 15,366.20 CONSTRUCTION ENGINEERING & INSPECTION: S 37,484.50 TOTAL IMPROVEMENT COST: S 449,894.84 CERTIFICATE OF THE CITY MANAGER: improvement. APPROVED Michael Van ' igen, City MM~ager,~ City of u e, Iowa APPROVED: Gus Psihoyos, City Engineer City of Dubuque, Iowa CERTIFICATE OF THE CONTRACTOR: The undersigned, CONNOLLY CONSTRUCTION, INC. conVactor for the above improvement, does hereby accept the accept the above "Total Due ConVactor", as full settlement for all claims for said improvement. CONTRACTOR: BY: CONNOLLY CONSTRUCTIO ,INC. TITLE: ~ •: ~~ DATE: _ /' /~ ~~ (]~