TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Town Clock Renovation Project, #102-1215
DATE: March 24, 2008
Leisure Services Manager Gil Spence recommends City Council approval of the plans,
specifications, form of contract and estimated cost for the Town Clock Renovation
Project.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
V
~~ ~~
Mic ael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gil D. Spence, Leisure Services Manager
THE CITY OF Dubuque
DUB E
~ r
Masterpiece on the Mississippi
2007
TO: Michael C. Van Milligen, City Manager
FROM: Gil D. Spence, Leisure Services Manager
SUBJECT: Town Clock Renovation Project, #102-1215
DATE: March 20, 2008
INTRODUCTION
The purpose of this memorandum is to request City Council approval of the plans,
specifications, form of contract, and estimated cost for the Town Clock Renovation
Project.
DISCUSSION
The FY 2007 CIP budget contains $195,250 and the FY 2009 CIP budget contains
$200,000 for phase I of the Town Clock renovation project. Phase II of the renovation
will be completed in seven years when the clock will need repainting. The architect's
estimate for this project is $365,000.
Renovation of the Town Clock will include applying an E.I.F.S. finish to the pedestal
base of the clock, replacing the electrical system and interior lighting, repairing the
exterior of the clock, and painting the clock.
This project was bid last summer for fall and spring construction to avoid conflicting with
the many events held each year around the Town Clock. Low bid at that time was
$375,100. All bids were rejected and additional funding requested in the FY 2009
budget.
We are bidding the project now to allow construction over the summer, thinking that will
lower the price. Arrangements are being made to minimize conflict with events so none
of them will have to relocate. More time is being given for construction during good
weather.
continued
town clock renovation, page two
The estimate of probable cost is as follows:
Estimate
Construction contract $ 365,000
Design $ 30,250
Total $ 395,250
ACTION STEP
The action requested is that the City Council adopt the attached resolution giving
approval of the plans, specifications, form of contract, and estimated cost for the Town
Clock Renovation Project.
GDS:et
attachment
Preparers Gil D. Saence Address: 2200 Bunker Hill Rd Phone: (563) 589-4263
RESOLUTION NO. 111-08
APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED
COST FOR THE TOWN CLOCK RENOVATION PROJECT
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
That the proposed plans, specifications, form of contract and estimated cost for the
Town Clock Renovation Project, in the estimated amount of $365,000, are hereby
approved.
Passed, approved and adopted this 7th day of April , 2008.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, City Clerk