POD Ice Harbor Transient Boat Dock ProjectTHE CITY OF DUB E Masterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager Dubuque ~~ ~~~.~ 2007 SUBJECT: Port of Dubuque -Ice Harbor Transient Boat Dock Facility Project (CIP 7001961) DATE: July 1, 2008 City Engineer Gus Psihoyos is recommending acceptance of the construction contract for the Ice Harbor Transient Boat Dock Facility Project, as completed by Newt Marine Services, in the final contract amount of $507,187.52, which is a 2.6% decrease from the original contract amount of $520,546.71. I concur with the recommendation and respectfully request Mayor and City Council approval. Mic ael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer THE CITY OF _~,,,. DUB E Masterpiece on the Mississippi Dubuque America Cit~ 2007 TO: Michael C. Van Milligen, City Man ~.~ FROM: Gus Psihoyos, City Engineer ~~~ SUBJECT: Port of Dubuque -Ice Harbor Transient Boat Dock Facility Project (CIP 7001961) DATE: June 24, 2008 INTRODUCTION The enclosed resolution provides for the acceptance of the construction contract for the Port of Dubuque -Ice Harbor Transient Boat Dock Facility Project. BACKGROUND The Ice Harbor transient boat docks at the Port of Dubuque are a component of the Vision Iowa grant for the America's River project. The incorporation of a recreational boat dock facility is a required component of the Vision Iowa grant. To satisfy the Vision Iowa grant requirements, the project was designed as a phased approach with the planning, design and construction of transient boat docks at two locations in the Port of Dubuque: Phase 1 -Ice Harbor and Phase 2 -Mississippi River main channel. This acceptance represents the completion of Phase 1 -Ice Harbor. The Ice Harbor Transient Boat Dock Facility is located adjacent to Ice Harbor Park and provides for the installation of 25 floating courtesy docks that includes: 8 - 30 foot slips; 15 - 40 foot slips; 2 slips for broadside dockage; and an 80-foot, ADA-compliant access gangway. In an effort to incorporate sustainable design and green community initiatives into the project, the floating docking system included the installation of solar-powered lighting located throughout the main walkway isles and recycled composite decking materials which replaced the conventional pressure-treated wood decking. The Ice Harbor Transient Boat Dock Facility has been designed to accommodate the ever-changing river stage water elevation within the Ice Harbor. The dock facility also included the installation of a floating wave attenuator wall and pile mooring dolphins to minimize the effects of wave action due to commercial vessels that navigate within the Ice Harbor. DISCUSSION The Port of Dubuque -Ice Harbor Transient Boat Dock Facility Project was completed by Newt Marine Service of Dubuque, Iowa, in the final contract amount of $507,187.52, which is a 2.6% decrease from the original contract in the amount of $520,546.71. Following the award of the construction contract, staff worked with Newt Marine to review and implement several value engineering design alternatives which included: allowing the dock manufacturer to provide a complete ADA gangway and floating platform system; and deleting the floating dock concrete deadman anchorage system and substituting with wood piles and roller pile brackets, which resulted in a project cost savings of $16,000. After accounting for all final quantity adjustments and change order/ extra work items, the net overall project savings was $13,359.19. RECOMMENDATION I recommend that the City Council accept the improvements and authorize the payment of the contract amount of $507,187.52 to Newt Marine Service for the Port of Dubuque - Ice Harbor Transient Boat Dock Facility Project. BUDGET IMPACT The final costs for the Port of Dubuque -Ice Harbor Transient Boat Dock Facility Project is summarized as follows: Construction Contract -Alternate Bid Contingency Consultant Services -Engineering Design Consultant Services - Geotechnical Award $ 520, 546.71 42,500.00 24,675.00 0 Final $ 507,187.52 0 22,898.50 6,627.00 Construction Engineering & Inspection Total Project Cost The project funding summary is as follows: CIP No. Fund Description 7001961 Ice Harbor Transient Boat Docks Boating Infrastructure (Tier 1) Grant Total Project Funding 20,000.00 $ 607,721.71 13,351.07 $ 550,064.09 Fund Amount $ 450,064.09 100,000.00 $ 550,064.09 ACTION TO BE TAKEN The City Council is requested to adopt the attached resolution to accept the improvements and to authorize the payment of the contract amount of $507,187.52 to Newt Marine for the Port of Dubuque -Ice Harbor Transient Boat Dock Facility Project. Prepared by Robert Schiesl, Assistant City Engineer cc: Jenny Larson, Budget Director Laura Carstens, Planning Services Manager RESOLUTION NO. 210-08 ACCEPTING THE PORT OF DUBUQUE -ICE HARBOR TRANSIENT BOAT DOCK FACILITY PROJECT AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE CONTRACTOR Whereas, the Public Improvement Contract for the Port of Dubuque -Ice Harbor Transient Boat Dock Facility Project (the Project) has been completed and the City Engineer has examined the work and filed a certificate stating that the Project has been completed according to the terms of the Public Improvement Contract and that the City Engineer recommends that the Project be accepted; and NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor from the Ice Harbor Transient Boat Docks Capital Improvement Project and the Federal Boating Infrastructure (Tier 1) Grant appropriation for the contract amount of $507,187.52 less any retained percentage provided for therein as provided in Iowa Code chapter 573, and to pay such retainage only in accordance with the provisions of Iowa Code chapter 573. Passed, approved and adopted this 7th day of July , 2008. t. x ~;: ,~,~.. Roy D. Buol, Mayor Attest: eanne F. Schneider, CMC, City Clerk CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE PORT OF DUBUQUE - ICE HARBOR TRANSIENT BOAT DOCK FACILITY PROJECT The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has inspected the Port of Dubuque -Ice Harbor Transient Boat Dock Facility Project, that the Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $550,064.09. Dated this 2nd day of July, 2008. S City Engineer Gus Psihoyos Filed in the office of the City Clerk on this 2nd day of July, 2008. Jeanne F. Schneider, CMC, City Clerk City of Dubuque -Engineering Division Final Payment Form PARTIAL PAYMENT NO: COUNCIL FINAL PROJECT NAME: PORT OF DUBUQUE ICE HARBOR TRANSIENT BOAT DOCK FACILITY PROJECT DATE: June 24, 2008 CONTRACTOR: NEWT MARINE SERVICE CONTRACT AMOUNT: $520,546.71 BID ITEM DESCRIPTION UNIT UN T COST QUANTITY FINEARNED NT ': 'ALTERIVATE,BID 1 Mobilization LSUM $ 16,818.00 1.0 $ 16,818.00 2 ADA Gangway, 80' long LSUM $ 51,868.80 1.0 $ 51,868.80 3 Floating Dock Main Walkway (Composite Decking) SFT $ 46.83 4,624.0 $ 216,541.92 4 Floating Dock, 30' long (Composite Decking) SFT $ 102.39 360.0 $ 36,860.40 5 Floating Dock, 40' long (Composite Decking) SFT $ 80.18 960.0 $ 76,972.80 6 Pile Cluster Dolphins EA $ 9,715.20 3.0 $ 29,145.60 7 Spring Piles (12" dia.), Wood EA $ 1,465.64 11.0 $ 16,122.04 8 ADA Handrail LFT $ 63.44 52.0 $ 3,298.88 9 Floating Wave Attenuator SFT $ 61.03 816.0 $ 49,800.48 10 Fixed Platform LSUM $ 10,016.40 1.0 $ 10,016.40 11 Dock Lights, Solar EA $ 66.73 74.0 $ 4,938.02 AMOUNT EARNED TO DATE -ALTERNATE BID: $ 512,383.34 (Bid Items No.t to 11 Total) `CHANGE ORDE,R~S);-~EXTRA,V,fORK ; ., _. , . ;, 12 Remove & Salvage, 4 x 4 Wood Posts LSUM $ 2,000.00 1.0 $ ' 2,000.00 13 Furnish & Install Rubber Rub Rail Along Finger Slips LSUM $ 3,820.00 1.0 $ 3,820.00 14 Furnish & Install PVC SCH 80 Posts to Mount Dock Lights EA $ 67.35 74.0 $ 4,984.18 TOTAL AMOUNT EARNED TO DATE -CHANGE ORDERS: l a 10,804.18 (Bid Items No.12 to 14 Total) D,~DUCTS ... -~. _ ._ .~, '':gyn. , _ 1 , 15 ADA Gangway, 80' long LSUM $ (8,000.00) 1.0 $ (8,000.00) 16 Floating Dock Main, Delete Concrete Deadman Anchorage LSUM $ (8,000.00) 1.0 $ (8,000.00) and Replace with Wood Piles and Roller Pile Brackets AMOUNT EARNED TO DATE -DEDUCTS: $ 16,000.00 (Bid Items No.15 to 16 Total) TOTAL AMOUNT EARNED TO DATE: ~$ 507,187.52 TOTAL DUE CONTRACTOR: $ 507,187.52 CONSULTANT SERVICES -ENGINEERING DESIGN: $ 22,898.50 CONSULTANT SERVICES - GEOTECHNICAL: $ 6,627.00 CONSTRUCTION ENGINEERING & INSPECTION: $ 13,351.07 TOTAL IMPROVEMENT COST: $ 550,064.09 CERTIFICATE OF THE CITY MANAGER: APPROVED: Michael Van Milligen, City Manager City of Dubuque, Iowa ---- CERTIFICATE OF THE CITY EDfGINEER: APPROVED: / J~---.~ /~~ V`' /~ b Gus Psihoyos, City Engineer City of Dubuque, Iowa CERTIFICATE OF THE CONTRACTOR: The undersigned, NEWT MARINE SERVICE contractor for the above improvement, does hereby accept the above "Total Due Contractor", as full settlement for all claims for said improvement. CONTRACTOR: NEWT MARINE SERVICE BY: Q.ec TITLE: //QOT~-°7-~/~ip/-N/~~ DATE: lo/ ~/~(J City of Dubuque -Engineering Division Final Payment Form PARTIAL PAYMENT NO: COUNCIL FINAL PROJECT NAME: PORT OF DUBUQUE ICE HARBOR TRANSIENT BOAT DOCK FACILITY PROJECT DATE: June 24, 2008 CONTRACTOR: NEWT MARINE SERVICE CONTRACT AMOUNT: $520,546.71 BID ITEM DESCRIPTION UNIT UN T COST QUANTITY FINEARNED NT s'::' ALTERNATE.BID' ;, :: ,:. 1 Mobilization LSUM $ 16,818.00 1.0 $ , ._ 16,818.00 2 ADA Gangway, 80' long LSUM $ 51,868.80 1.0 $ 51,868.80 3 Floating Dock Main Walkway (Composite Decking) SFT $ 46.83 4,624.0 $ 216,541.92 4 Floating Dock, 30' long (Composite Decking) SFT $ 102.39 360.0 $ 36,860.40 5 Floating Dock, 40' long (Composite Decking) SFT $ 80.18 960.0 $ 76,972.80 6 Pile Cluster Dolphins EA $ 9,715.20 3.0 $ 29,145.60 7 Spring Piles (12" dia.), Wood EA $ 1,465.64 11.0 $ 16,122.04 8 ADA Handrail LFT $ 63.44 52.0 $ 3,298.88 9 Floating Wave Attenuator SFT $ 61.03 816.0 $ 49,800.48 10 Fixed Platform LSUM $ 10,016.40 1.0 $ 10,016.40 11 Dock Lights, Solar EA $ 66.73 74.0 $ 4,938.02 AMOUNT EARNED TO DATE -ALTERNATE BID: $ 512,383.34 (Bid Items No.1 to 11 Total) F RANGE ORDER ~S - E TRA WORK .: ..~. . ~ O ~ ,~ , . k,}" ,_ z . ~ ~ _~ ..,.:. . 12 Remove & Salvage, 4 x 4 Wood Posts LSUM $ 2,000.00 1.0 $ 2,000.00 13 Furnish ~ Install Rubber Rub Rail Along Finger Slips LSUM $ 3,820.00 1.0 $ 3,820.00 14 Furnish & Install PVC SCH 80 Posts to Mount Dock Li hts EA $ 67.35 74.0 $ 4 984.18 , TOTAL AMOUNT EARNED TO DATE -CHA NGE ORDERS: $ 10,804.18 (Bid Items No.12 to 14 Total) ;~ DEQUC.TS '' - Vti 15 ADA Gangway, 80' long LSUM $ (8,000.00) 1.0 $ (8,000.00) 16 Floating Dock Main, Delete Concrete Deadman Anchorage LSUM $ (8,000.00) 1.0 $ (8,000.00) and Replace with Wood Piles and Roller Pile Brackets AMOUNT EARNED TO DATE -DEDUCTS: $ 16,000.00) (Bid Items No.15 to 16 Total) TOTAL AMOUNT EARNED TO DATE: $ 507,187.52 TOTAL DUE CONTRACTOR: $ 507,187.52 CONSULTANT SERVICES -ENGINEERING DESIGN: $ 22,898.50 CONSULTANT SERVICES - GEOTECHNICAL: $ 6,627.00 CONSTRUCTION ENGINEERING 8 INSPECTION: $ 13,351.07 TOTAL IMPROVEMENT COST: $ 550,064.09 CERTIFICATE OF THE CITY MANAGER: APPROVED: Michael Van Milligen, City Manager City of Dubuque, Iowa CERTIFICATE OF APPROVED: Gus Psihoyos, City Engineer City of Dubuque, Iowa CERTIFICATE OF THE CONTRACTOR: The undersigned, NEWT MARINE SERVICE contractor for the above improvement, does hereby accept the above "Total Due Contractor", as full settlement for all claims for said improvement. CONTRACTOR: NEWT MAR E SERVICE BY: Ce.a.~ TITLE: ~'li~N/~~ ~~~_ / DATE: / r~~f/~t~