Loading...
Grove Terrace and 11th Street Steps Award2007 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: 11th Street Steps & Grove Terrace Retaining Wall Reconstruction Project CIP: 2501029 -Stone Retaining Walls 3002022 -Foye/Merchants/Gold Street Reconstruction Historic Preservation Fund DATE: July 17, 2008 Sealed bids were received on the 11t" Street Steps and Grove Terrace Retaining Wall Reconstruction Project. City Engineer Gus Psihoyos is recommending award to the low bidder, Portzen Construction, in the amount of $589,175.50. This is 15.8% over the engineer's estimate. There was only $259,239 available in the City budget for stone retaining walls. Therefore, additional resources have been identified, including delaying the Foye/Merchant/Gold Street Reconstruction Project to a future year. I concur with the recommendation and respectfully request Mayor and City Council approval. ~~ M(chael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer THE CTTY OF DUB E Masterpiece on the Mississippi Dubuque AN-America City 2007 TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer (TQ~ SUBJECT: 11th Street Steps & Grove Terrace Retaining Wall Reconstruction Project CIP: 2501029 -Stone Retaining Walls 3002022 - Foye/Merchants/Gold Street Reconstruction Historic Preservation Funds DATE: July 17, 2008 INTRODUCTION The enclosed resolutions authorize the award of the construction contract for the 11tH Street Steps & Grove Terrace Retaining Wall Reconstruction Project. DISCUSSION The final design of the Grove Terrace Retaining Wall Project includes the installation of concrete backfill and geofoam blocks to limit the stresses on the new retaining wall and allow the reuse of a significant portion of the existing limestone block. The project will also include installation of reinforced concrete over the existing 11th Street stairs arch to stabilize the arch. The section of Grove Terrace around the stairs will be reconstructed with 7" concrete pavement with integral curb and gutter. The rest of Grove Terrace will be reconstructed with asphalt pavement and concrete curb and gutter. The existing 8" sanitary sewer will be reconstructed along with the replacement of 2 sanitary manholes. The 11th Street stairs retaining walls will be partially reconstructed with salvaged limestone blocks and new limestone. The stairs will be partially reconstructed along with the replacement of some handrail and the refurbishing of the remaining railing. Wrought iron hoop railing will be installed at the top of the stairs. The installation of a new historic street light will help illuminate the stairway and provide for roadway lighting at the top of the stairs. Because the project is in the 11th Street historic neighborhood, Engineering staff will be presenting an overview of the project to the Historic Preservation Commission on July 17 for concurrence. BID RESULTS Sealed bids were received on the project on July 16, 2008. Portzen Construction, Inc. of Dubuque, Iowa, submitted the low base bid in the amount of $589,175.50. This amount is 15.8% over the engineer's estimate of probable cost. A summary of the bid proposals received is as follows: Contractor Name Portzen Construction, Inc. Drew Cook & Sons Excavating Tschiggfrie Excavating Co. Connolly Construction, Inc. RECOMMENDATION Bid Amount $589,175.50 $590,214.00 $677,670.70 $799,846.90 I recommend that the contract be awarded to Portzen Construction, Inc. in the amount of $589,175.50. BUDGET IMPACT The estimate of probable cost for the 11th Street Steps & Grove Terrace Retaining Wall Reconstruction Project is as follows: Cost Estimate Bid Award Construction Contract $508,942.50 $589,175.50 Contingency 76,341.38 76,341.38 Construction Engineering & Inspection 87,792.58 87,792.58 Total Project Cost $673,076.46 $753,309.46 The project funding summary is as follows: CIP No. Fund Description Fund Amount Historic Preservation Funds $ 90,000.00 2501029 Stone Retaining Walls 259,239.00 3002022 Foye/Merchants/Gold Reconstruction 404.070.46 Total Project Funding $753,309.46 ACTION TO BE TAKEN I recommend that the City Council adopt the attached resolutions awarding the 11tH Street Steps & Grove Terrace Retaining Wall Reconstruction Project to Portzen Construction, Inc. in the amount of $589,175.50. Prepared by Robert Schiesl, Assistant City Engineer cc: Jenny Larson, Budget Director Jon Dienst, Civil Engineer CITY OF DUBUQUE ENGINEERING DEPARTMENT BID TABULATION RESULTS PROJECT: 11th STREET STEPS & GROVE TERRACE RETAINING WALL RECONSTRUCTION LETTING DATE: JULY 16, 2008 NO. DESCRIPTION 1 Mobilization & Miscellaneous GROVE TERRACE RETAINING WALL 2 Base Course Backfill 3 Concrete Backfill 4 Geofoam Backfill 5 Limestone (Salvaged) 6 Limestone (New) 7 4" Perforated CPE Draintile 8 4" Perforated CPE Risers g 4" CPE Outlet with Bar Guard 10 Structural Concrete (Barrier Rail) 11 TL-2 Barrier Rail Connection Hardware 12 Wrought Iron Hoop Railing 11th STREET RETAINING WALL 13 Removal of PCC Steps 14 Engineered Backfill 15 Drainage Course Backfill 1g Waterproofing Membrane 17 4" Perforated CPE Drain Tile 18 Limestone (Salvaged) 19 Limestone (New) 2p Tuckpoint and Repair Existing Wall 21 Repair Existing Tie Rods 22 TL-2 Barrier Rail Connection Hardware 23 Wrought Iron Hoop Railing 24 PCC Steps (Treads) 25 PCC Steps (Landings) 26 Stair Railing (Replace) 27 Stair Railing (Repair) SANITARY SEWER 28 8" DIP Sanitary Sewer 2g 48" I.D. Manhole Base 30 48" I.D. Manhole Sidewall 31 Manhole Frame and Cover 32 Select Trench Backfill, Sanitary Bidder: PORTZEN CONSTRUCTION QUANTITY UNIT PRICE BID PRICE LS 1 $50,000.00 $50,000.00 Bidder: DREW COOK & SONS EXC. UNIT PRICE BID PRICE $16,000.00 $16,000.00 Bidder: TSCHIGGFRIE EXCAVATING UNIT PRICE BID PRICE $20,928.00 $20,928.00 Bidder: CONNOLLY CONSTRUCTION UNIT PRICE BID PRICE $39,200.00 TONS 1900 $15.00 $28,500.00 $25.00 $47,500.00 $22.50 $42,750 .00 $32.00 CY 427 $190.00 $81,130.00 $255.00 $108,885.00 $252.00 $107,604 .00 $278.00 CY 223 $165.00 $36,795.00 $95.00 $21,185.00 $87.00 $19,401 .00 $144.00 SF 3040 $30.00 $91,200.00 $30.00 $91,200.00 $31.00 $94,240 .00 $40.00 SF 340 $48.00 $16,320.00 $48.00 $16,320.00 $55.00 $18,700 .00 $69.00 LF 450 $9.00 $4,050.00 $20.00 $9,000.00 $15.00 $6,750 .00 $18.00 LF 65 $20.00 $1,300.00 $30.00 $1,950.00 $27.00 $1,755 .00 $18.00 EA 3 $125.00 $375.00 $200.00 $600.00 $197.00 $591 .00 $225.00 CY 75 $300.00 $22,500.00 $400.00 $30,000.00 $739.00 $55,425 .00 $545.00 EA 65 $150.00 $9,750.00 $60.00 $3,900.00 $199.00 $12,935 .00 $500.00 LF 130 $100.00 $13,000.00 $82.00 $10,660.00 $87.00 $11,310 .00 $110.00 LS 1 $10,000.00 $10,000.00 $15,000.00 $15,000.00 $7,706.00 $7,706. 00 $12,220.00 TONS 410 $17.50 $7,175.00 $30.00 $12,300.00 $22.00 $9,020. 00 $25.95 TONS 30 $30.00 $900.00 $100.00 $3,000.00 $27.00 $810. 00 $32.00 SY 20 $50.00 $1,000.00 $100.00 $2,000.00 $79.00 $1,580. 00 $31.00 LF 460 $9.00 $4,140.00 $20.00 $9,200.00 $14.00 $6,440. 00 $13.00 SF 175 $30.00 $5,250.00 $30.00 $5,250.00 $183.00 $32,025. 00 $40.00 SF 515 $70.00 $36,050.00 $72.00 $37,080.00 $78.00 $40,170. 00 $69.00 LF 75 $40.00 $3,000.00 $35.00 $2,625.00 $26.00 $1,950. 00 $31.00 EA 4 $200.00 $800.00 $790.00 $3,160.00 $723.00 $2,892. 00 $950.00 EA 55 $150.00 $8,250.00 $60.00 $3,300.00 $221.00 $12,155. 00 $500.00 LF 107 $100.00 $10,700.00 $82.00 $8,774.00 $89.00 $9,523. 00 $110.00 LF 120 $80.00 $9,600.00 $80.00 $8,600.00 $109.00 $13,080. 00 $83.00 SF 60 $10.00 $600.00 $20.00 $1,200.00 $66.00 $3,960. 00 $14.75 LF 45 $75.00 $3,375.00 $62.00 $2,790.00 $63.00 $2,835. 00 $78.00 LF 30 $75.00 $2,250.00 $60.00 $1,800.00 $53.00 $1,590. 00 $66.00 LF 100 $35.00 $3,500.00 $70.00 $7,000.00 $62.00 $6,200. 00 $50.50 EA 2 $550.00 $1,100.00 $1,500.00 $3,000.00 $860.00 $1,720. 00 $690.00 VF 12.05 $150.00 $1,807.50 $200.00 $2,410.00 $274.00 $3,301. 70 $208.00 EA 2 $500.00 $1,000.00 $500.00 $1,000.00 $568.00 $1,136. 00 $660.00 LF 100 $10.00 $1,000.00 $19.00 $1,900.00 $13.00 $1,300. 00 $33.00 $39,200.00 $60,800.00 $118,706.00 $32,112.00 $121, 600.00 $23,460.00 $8,100.00 $1,170.00 $675.00 $40,875.00 $32,500.00 $14,300.00 $12,220.00 $10,639.50 $960.00 $620.00 $5,980.00 $7,000.00 $35,535.00 $2,325.00 $3,800.00 $27,500.00 $11,770.00 $9,960.00 $885.00 $3, 510.00 $1, 980.00 $5,050.00 $1, 380.00 $2,506.40 $1, 320.00 $3,300.00 CITY OF DUBUQUE ENGINEERING DEPARTMENT BID TABULATION RESULTS PROJECT: 11th STREET STEPS & G ROVE TERRACE RETAINING WALL RECONSTRUCTION LETTING DATE: JULY 16, 2008 Bidder: Bidder: Bidder: Bidder: PORTZEN CON STRUCTION DREW COOK 8 SONS EXC. TSCHIGGFRIE EXCAVATING CONNOLLY CONSTRUCTION NO. DESCRIPTION QUANTITY UNIT PRICE BID PRICE UNIT PRICE BID PRICE UNIT PRICE BID PRICE UNIT PRICE BID PRICE PAVING i 33 Removal of Pavement SY 790 $10.00 $7,800.00 $12.00 $9,480.00 $12.00 $9,480.00 $13.30 J $10,507.00 34 Base Course TONS 330 $15.00 $4,950.00 $25.00 $8,250.00 $17.00 $5,610.00 $21.00 $6,930.00 35 7" PCC Pavement w/Integral Curb SY 600 $42.00 $25,200.00 $48.00 $28,800.00 $41.00 $24,600.00 $48.00 $28,800.00 36 PCC Curb & Gutter LF 190 $26.00 $4,940.00 $17.00 $3,230.00 $20.00 $3,800.00 $20.30 $3,857.00 37 5" HMA Pavement SY 190 $32.00 $6,080.00 $35.00 $6,650.00 $33.00 $6,270.00 $42.00 $7,980.00 3g Structural Concrete (Slab & Abutment) CY 64 $1,000.00 $64,000.00 $480.00 $30,720.00 $1,014.00 $64,896.00 $1,355.00 $86,720.00 39 Payment Markings EA 2 $275.00 $550.00 $1,000.00 $2,000.00 $263.00 $526.00 $310.00 $620.00 40 Manhole Adjustment EA 1 $175.00 $175.00 $1,000.00 $1,000.00 $556.00 $556.00 $1,300.00 $1,300.00 41 Neenah 101-B Frame and Grate EA 1 $650.00 $650.00 $2,000.00 $2,000.00 $714.00 $714.00 $1,890.00 $1,890.00 42 Traffic Control LS 1 $2,063.00 $2,063.00 $2,375.00 $2,375.00 $1,969.00 $1,969.00 $2,380.00 $2,380.00 43 Regrade, Seed, Fertilize, Mulch ACRE 0.1 $12,000.00 $1,200.00 $10,000.00 $1,000.00 $15,750.00 $1,575.00 $12,700.00 $1,270.00 ELECTRICAL 1 44 Connection to Existing Electrical Service EA 1 $1,200.00 $1,200.00 $1,800.00 $1,800.00 $2,100.00 $2,100.00 $1,920.00 $1,920.00 J 45 Conduit, 2" PVC, Schedule 40 LF 60 $12.00 $720.00 $12.00 $720.00 $16.00 $960.00 $20.00 $1,200.00 46 Electric Cable, #10 XHHW LF 180 $2,50 $450.00 $1.00 $180.00 $1.00 $180.00 $1.10 $198.00 47 Ground Wire, #6 Bare Copper LF 60 $3.00 $180.00 $2.00 $120.00 $2.00 $120.00 $2.10 $126.00 4g Install Historic Streetlight inc. Foundation EA 1 $2,500.00 $2,500.00 $2,300.00 $2,300.00 $2,532.00 $2,532.00 $2,410.00 $2,410.00 TOTAL BASE BID ~ 5589,175.50 1 ~ 5590,214.00 ~ ~ 5677,670.70 ~ ' 5799,846.90 EngineeY's Cost Estimate: $ 508,942.50 ' 15.8% ~ ~ 16.0% ~ ' 33.2% ~ ~ 57.2% RESOLUTION NO. 246-08 APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED COST FOR THE 11th STREET STEPS & GROVE TERRACE RETAINING WALL RECONSTRUCTION PROJECT NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the proposed plans, specifications, form of contract and estimated cost for the 11th Street Steps & Grove Terrace Retaining Wall Reconstruction Project, in the total estimated amount $673,076.46, are hereby approved. Passed, adopted and approved this 21st day of July, 2008. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. 247-08 AWARDING PUBLIC IMPROVEMENT CONTRACT FOR THE 11TH STREET STEPS & GROVE TERRACE RETAINING WALL RECONSTRUCTION PROJECT Whereas, sealed proposals have been submitted by contractors for the 11 th Street Steps & Grove Terrace Retaining Wall Reconstruction Project (the Project) pursuant to Resolution No.222-08and Notice to Bidders published in a newspaper published in the City of Dubuque, Iowa on the 9th day of July, 2008. Whereas, said sealed proposals were opened and read on the 16th day of July, 2008 and it has been determined that Insert Portzen Construction, Inc. of Dubuque, Iowa, with a bid in the amount of $589,175.50, is the lowest responsive, responsible bidder for the Project. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That a Public Improvement Contract for the Project is hereby awarded to Insert Contractor Name and the City Manager is hereby directed to execute a Public Improvement Contract on behalf of the City of Dubuque for the Project. Passed, approved and adopted this 21st day of July, 2008. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk CITY OF DUBUQUE, IOWA IMPROVEMENT CONTRACT THIS IMPROVEMENT CONTRACT (the Contract), made in triplicate, dated for reference purposes the 22nd day of July 2008, between the City of Dubuque, Iowa, by its City Manager, through authority conferred upon the City Manager by its City Council (City) and Portzen Construction, Inc. of the City of Dubuque, Iowa. For and in consideration of the mutual covenants herein contained, the parties hereto agree as follows: CONTRACTOR AGREES: 1. To furnish all material and equipment and to perform all labor necessary for the 11tH Street Steps & Grove Terrace Retaining Wall Project (the Project). The Project shall be made to the established grade and to the grades as shown on the profiles and cross-sections on file in the City Engineer's office for this Project, in strict accordance with the requirements of the laws of the State of Iowa and ordinances of the City of Dubuque relating to public works, and in accordance with the Contract Document shall of which provisions and documents are each and all hereby referred to and made a part of this Contract just as much as if the detail statements thereof were repeated herein. 2. Contract Documents shall mean and include the following: All ordinances and resolutions heretofore adopted by the City Council having to do with the Project; the Notice to Bidders; the Contractor's Proposal; and the Plans,. Specifications, and General Requirements as adopted by the City Council for the Project. 3. All materials used by the Contractor in the Project shall be the best of their several kinds and shall be put in place to the satisfaction of the City Manager. 4. The Contractor shall remove any materials rejected by the City Manager as defective or improper, or any of said work condemned as unsuitable or defective, and the same shall be replaced or done anew to the satisfaction of the City Manager at the cost and expense of the Contractor. 5. Five percent (5%) of the Contract price shall be retained by the City for a period of thirty (30) days after final completion and acceptance of the Project by the City Council to pay any claim that may be filed within said time for labor and materials done and furnished in connection with the performance of this Contract and for a longer period if such claims are not adjusted within that time, as provided in Iowa Code Chapter 573. The City shall also retain additional sums to protect itself against any claim that has been filed against it for damages to persons or property arising through the prosecution of the work and such sums shall be held by the City until such claims have been settled, adjudicated or otherwise disposed of. 6. The Contractor has read and understands the specifications including General Requirements and has examined and understands the plans herein referred to and agrees not to plead misunderstanding or deception because of estimates of quantity, character, location or other conditions surrounding the same. 7. In addition to the .guarantee provided for in the specifications, the Contractor shall also make good any other defect in any part of the Project due to improper construction notwithstanding the fact that said Project may have been accepted and fully paid for by the City, and the Contractor's bond shall be security therefore. 8. The Contractor shall fully complete the Project under this Contract on or before November 1St, 2008. 9. To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the City from and against all claims, damages, losses and expenses, including but not limited to attorney fees, arising out of or resulting from performance of the Contract, provided that such claim, damages, loss or expense is attributable to bodily injury, sickness, disease or death, or injury to or destruction of property (other than the Project itself) including loss of use resulting there from, but only to the extent caused in whole or in part by negligent acts or omissions of the Contractor, the Contractor's subcontractor, or anyone directly or indirectly employed by the Contractor or the Contractor's subcontractor or anyone for whose acts the Contractor or the Contractor's subcontractor may be liable, regardless of whether or not such claim, damage, loss or expense is caused in part by a party indemnified hereunder. THE CITY AGREES: Upon the completion of the Contract, and the acceptance of the Project by the City Council, the City agrees to pay the Contractor as full compensation for the complete performance of this Contract, the amount determined for the total number of units completed at the unit prices stated in the Contractor's Proposal and less any liquidated damages provided for in the Contract Documents. The number of units stated in the plans and specifications is approximate only and the final payment shall be made by the work covered by the Contract. CONTRACT AMOUNT $589,175.50 FURTHER CONDITIONS The Contractor hereby represents and guarantees that it has not, nor has any other person for or in its behalf, directly or indirectly; entered into any arrangement or agreement with any other bidder, or with any public officer, whereby it has paid or is to pay any other bidder or public officer any sum of money or anything of value whatever in order to obtain this Contract; and it has not, nor has another person for or in its behalf directly or indirectly, entered into any agreement or arrangement with any other person, firm, corporation or association which tends to or does lessen or destroy free competition in the letting of this Contract and agrees that in case it hereafter be established that such representations or guarantees, or any of them are false, it will forfeit and pay not less than ten percent (10%) of the Contract price but in no event be less than Seven Hundred Fifty and 00/100 Dollars ($750.00) as liquidated damages to the City. The surety on the bond furnished for this Contract, shall in addition to all other provisions, be obligated to the extent provided for by Iowa Code § 573.6, relating to this Contract, which provisions apply to said bond. The Contractor agrees, and its bond shall be surety therefore, that it will keep and maintain the Project in good repair for a period of two years after acceptance of the same by the City Council and its bond shall be security therefore. CITY OF~D+U QUE, IOWA l ~~ ~ _ ~_ City Manager PRINCIPAL Portzen Construction, Inc. o tractor By: Sign re Kay ortzen Corporate Secretary Title CERTIFICATE OF CITY CLERK This is to certify that a certified copy of the above Contract has been filed in my office on the 22b day of July X08. -_ -- -F -~~irnefde~,-1~-G+#y-G~r-k Kevin SR Firnstahl, Assistant City Clerk ~~s THE CTTY OF D~ L E Masterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager Dubuque ~f C~'''~" n~-americacily 2007 SUBJECT: 11th Street Steps & Grove Terrace Retaining Wall Project CIP: 2501029 -Stone Retaining Walls, 3002022 - Foye/Merchants/Gold, Historic Preservation Funds DATE: July 1, 2008 City Engineer Gus Psihoyos is recommending initiation of the public bidding procedure for the 11th Street Steps and Grove Terrace Retaining Wall Project and that a public hearing be set for July 21, 2008. I concur with the recommendation and respectfully request Mayor and City Council approval. V Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer THE CITY OF DAB ~ Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Manager FROM. Gus Psihoyos, City Engineer SUBJECT: 11th Street Steps & Grove Terrace Retaining Wall Project CIP: 2501029 -Stone Retaining Walls, 3002022 - Foye/Merchants/Gold, Historic Preservation Funds DATE: June 30, 2008 INTRODUCTION Dubuque Aq-Ame~caCinl r 2007 The enclosed resolutions authorize the public bidding procedure for the 11T" Street Steps & Grove Terrace Retaining Wall Project. BACKGROUND In the West 11th Street Historic District, there is a City-owned limestone retaining wall around the 11th Street stairs at Grove Terrace that was known to be in deteriorating condition. Last year the Engineering Department noticed that the walls around the 11th Street steps were bowing and showing signs of distress. IIW Engineers & Surveyors PC (IIW) was hired to investigate the structural integrity of the walls and stairs. Preliminary plans were developed and engineering staff went before the Historic Preservation commission in December 2007 for a design review. City staff reviewed the comments made at that HPC meeting and directed IIW to incorporate those changes in subsequent plans. When the engineering staff was prepared to go to bid for the stairs and related retaining wall repairs, the retaining wall on Grove Terrace failed on April 1St, 2008 just north of the original project limits. Due to the record snowfall and heavy rains this spring, the structural integrity of the wall, Grove Terrace, and utilities were severely compromised. For public safety, this area has been closed to vehicular/pedestrian traffic since the initial collapse on April 1. In the interest of public safety, the resident of 1108 Grove Terrace had limited access to his home for approximately 7 days and the residents of the Teresa Shelter on Bluff Street were evacuated to temporary housing for a period of 2 weeks. On May 7, Tschiggfrie Excavating was hired on an emergency basis to begin the wall deconstruction work. This work included: the removal of a wall section and native earth material back to the existing rock shelf and natural bluff; the placement of plastic sheeting over the exposed slopes and temporary curbs to redirect water away from the excavated area; and the temporary bypass of the sanitary sewer on Grove Terrace to Bluff Street. Also, since the initial wall collapse, IIW was hired to provide ongoing inspection and to assist in the design of a replacement wall system. For the past two months the engineering department and IIW have discussed a comprehensive repair for the Grove Terrace retaining wall and the 11th Street Stairs. The final design includes the installation of concrete backfill and geofoam blocks to limit the stresses on the new retaining wall and allow the reuse of a significant portion of the existing limestone block. The project will also include installation of reinforced concrete over the existing 11th Street stairs arch to stabilize the arch. The section of Grove Terrace around the stairs will be reconstructed with 7" concrete pavement with integral curb and gutter. The rest of Grove Terrace will be reconstructed with asphalt pavement and concrete curb and gutter. The existing 8" sanitary sewer will be reconstructed along with the replacement of 2 sanitary manholes. The 11th Street stairs retaining walls will be partially reconstructed with salvaged limestone blocks and new limestone. The stairs will be partially reconstructed along with the replacement of some handrail and the refurbishing of the remaining railing. Wrought iron hoop railing will be installed at the top of the stairs. The installation of a new historic street light will help illuminate the stairway and provide for roadway lighting at the top of the stairs. DISCUSSION The 11th Street Steps and Grove Terrace Retaining Wall Reconstruction Project includes the following: PROJECT SCHEDULE The schedule for the project is as follows: Initiate Public Bidding Process July 7, 2008 Advertisement for Bids July 9, 2008 Notice of Public Hearing on Plans& Specifications July 11, 2008 Public Hearing July 21, 2008 Pre-Bid Conference July 10, 2008 Receipt of Bids July 16, 2008 Award Construction Contract Project Completion Date RECOMMENDATION July 21, 2008 November 1, 2008 I recommend that the City Council establish a date for the public hearing and authorize the City Clerk to advertise for proposals. BUDGET IMPACT Due to the fact the City has never bid a project of this nature with the Geofoam material and reinforced concrete backfill we have added a 15% contingency due to the complexity of the project. The estimate of probable cost for the 11 T" Street Steps & Grove Terrace Retaining Wall Project is as follows: Estimate Construction Contract $508,942.50 Contingency (15%) $76,341.38 Construction Engineering & Inspection $87.792.58 Total Project Cost $673,076.46 The current FY 2009 Capital Improvement Program includes funding for the reconstruction of Foye, Merchants and Gold Streets. Because there is a funding shortfall in the Stone Retaining Walls CIP, it is proposed that the Foye, Merchants, Gotd Reconstruction Project be eliminated to fund this project. The Foye, Merchants, Gold Reconstruction Project would be scheduled in a future CIP. The project funding summary is as follows: CIP No. Fund Description Fund Amount Historic Preservation Funds $90,000.00 2501029 Stone Retaining Walls $191,647.47 3002022 Foye/Merchant/Gold Reconstruction $391,428.99 Total Project Funding $673,076.46 ACTION TO BE TAKEN The City Council is requested to establish the date of the public hearing and to authorize the City Clerk to advertise for proposals through adoption of the enclosed resolutions for the 11th Street Steps & Grove Terrace Retaining Wall Reconstruction Project. Prepared by Robert Schiesl, Assistant City Engineer cc: Jenny Larson, Budget Director Jon Dienst, Civil Engineer NOTICE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED COST FOR THE 11T" STREET STEPS & GROVE TERRACE RETAINING WALL RECONSTRUCTION PROJECT NOTICE IS HEREBY GIVEN: The City Council of the City of Dubuque, Iowa will hold a public hearing on the proposed plans, specifications, form of contract and estimated cost for the 11th Street Steps & Grove Terrace Retaining Wall Reconstruction Project, in accordance with the provisions of Chapter 26, Code of Iowa, at 6:30 p.m., on the 21St day of July, 2008, in the Historic Federal Building Council Chambers (second floor), 350 West 6th Street, Dubuque, Iowa. Said proposed plans, specifications, form of contract and estimated cost are now on file in the office of the City Clerk. At said hearing any interested person may appear and file objections thereto. The scope of the Project is as follows: The 11th Street Steps and Grove Terrace Retaining Wall Reconstruction Project will provide for the reconstruction of existing limestone retaining walls, sanitary sewer, roadway sub-base, construction of concrete and asphalt roadway and concrete reinforcement of an existing limestone arch. This project also includes partial reconstruction of stairs, railing and fencing. The retaining wall reconstruction will include utilizing existing limestone block as well as new limestone block. The retaining wall backfill material will include a mix of reinforced concrete backfill, geofoam backfill and granular backfill. The retaining walls, arch and stairs are in a historic district of downtown Dubuque and are of particular historical significance. Any visual or hearing-impaired persons needing special assistance or persons with special accessibility needs should contact the City Clerk's office at (563) 589-4120 or TDD at (563) 690-6678 at least 48 hours prior to the meeting. Published by order of the City Council given on the day of , 2008. Jeanne F. Schneider, CMC, City Clerk NOTICE TO BIDDERS CITY OF DUBUQUE PUBLIC IMPROVEMENT PROJECT 11T" STREET STEPS & GROVE TERRACE RETAINING WALL RECONSTRUCTION PROJECT Time and Place for Filing Sealed Proposals. Sealed bids for the work comprising each improvement as stated below must be filed before 2:00 p.m. on July 16tH, 2008, in the Office of the City Clerk, City Hall -First Floor, 50 West 13tH Street, Dubuque, Iowa. Time and Placed Sealed Proposals Will be Opened and Considered. Sealed proposals will be opened and bids tabulated at 2:00 p.m. on July 16 , 2008, at City Hall -Conference Room A, 50 West 13tH Street, Dubuque, Iowa, for consideration by the City Council (Council) at its meeting on July 21St, 2008. The City of Dubuque, Iowa, reserves the right to reject any and all bids. Time for Commencement and Completion of Work. Work on each improvement shall be commenced within 10 days after the Notice to Proceed has been issued and shall be fully completed by November 1, 2008. Bid Security. Each bidder shall accompany its bid with a bid security as security that the successful bidder will enter into a contract for the work bid upon and will furnish after the award of contract a corporate surety bond, acceptable to the governmental entity, for the faithful performance of the contract, in an amount equal to one hundred percent of the amount of the contract. The bid security shall be in the amount of ten percent (10%) of the amount of the contract and shall be in the form of a cashier's check or certified check drawn on a state- chartered or federally chartered bank, or a certified share draft drawn on a state- chartered or federally chartered credit union, or the governmental entity may provide for a bidder's bond with corporate surety satisfactory to the governmental entity. The bid bond shall contain no conditions excepted as provided in this section. Contract Documents. Copies of the construction documents may be obtained at the Engineering Department, City Hall -Second Floor, 50 West 13tH Street, Dubuque, Iowa 52001. No plan deposit is required. Preference for Iowa Products and Labor. By virtue of statutory authority, preference will be given to products and provisions grown and coal produced within the State of Iowa, and to Iowa domestic labor, to the extent lawfully required under Iowa statutes. Sales Tax. The bidder should not include sales tax in its bid. A sales tax exemption certificate will be available for all material purchased for incorporation in the project. General Nature of Public Imarovement. 11T STREET STEPS & GROVE TERRACE RETAINING WALL RECONSTRUCTION PROJECT, CIP 2501029 AND CIP 3002022. The 11 t" Street Steps and Grove Terrace Retaining Wall Reconstruction Project will provide for the reconstruction of approximately 4070 SF of existing limestone retaining wall, 100 LF of sanitary sewer with two manholes, roadway sub-base, construction of 600 SY of concrete roadway, 190 SY of asphalt roadway and concrete reinforcement of an existing limestone arch. This project also includes partial reconstruction of stairs, railing and fencing. The retaining wall reconstruction will include utilizing existing limestone block as well as new limestone block. The retaining wall backfill material will include a mix of reinforced concrete backfill, geofoam backfill and granular backfill. The retaining walls, arch and stairs are in a historic district of downtown Dubuque and are of particular historical significance. Pre-Bid Construction Conference. Each prospective bidder is encouraged to attend the Pre-Bid Construction Conference to be held at 1:30 PM on July 10tH 2008, in Conference Room B, City Hall, 50 West 13t" Street, Dubuque, Iowa. Attendance by all prospective bidders is not mandatory but highly recommended. Published in the Telegraph Herald, July 9t", 2008. Planning Services Department City Hall 50 West 13~h Street Dubuque, IA 52001-4864 (563) 589-4210 phone (563) 589-4221 fax (563) 589-6678 TDD planning@cityofdubuque.org THE CITY OF DuB E Masterpiece on the Mississippi July 21, 2008 The Honorable Mayor and City Council Members City of Dubuque City Hall - 50 W. 13t" Street Dubuque, IA 52001 RE: W. 11t" Street Stairs and Grove Terrace Retaining Wall Dear Mayor and City Council Members: The City of Dubuque Historic Preservation Commission (HPC) has reviewed the above- cited request. The staff report and related materials are attached for your review. Background The project includes the repair and reconstruction of the W. 11t" Street stairs and the Grove Terrace retaining wall. On January 22, 2008 City Council approved $90,000 in HDPIP funds for the W. 11t" Street stair project. No HDPIP funds are requested for the Grove Terrace retaining wall project. Both the stairs and the retaining wall are in the W. 11t" Street Historic District, where the HPC conducts advisory design review for public works projects. Discussion The W. 11t Street stairs project will involve the removal of the street pavement on Grove Terrace around the upper portion of the 11th Street stairs, excavation above the existing arch, installation of a reinforced concrete bridge with ties to hold the existing arch in place, reshaping of the existing roadway subgrade to correct drainage deficiencies, installation of new curb and gutter and limestone barrier wall, installation of new concrete pavement and installation of new decorative fencing. The existing retaining walls along the 11th Street stairs will be repaired using native Dubuque limestone and properly tuckpointed. Existing materials will be used as much as possible with new materials matching the existing materials in size, color and material type. A historic pedestrian light is proposed to be placed at the top of the stairs on Grove Terrace. This will provide illumination for the upper portion of the stairs and Grove Terrace. The existing lighting under the arch will remain in place. The Grove Terrace Retaining Wall will be reconstructed using existing limestone block that was salvaged from the wall failure. New limestone block will be cut and placed where needed. The dimensional size of the new limestone will match the existing retaining wall block. Behind the new limestone the wall will be backfilled with W. 11th Street Stairs and Grove Terrace Retaining Wall Projects F:\Users\Djohnson\Council Items\W. 11th Street Stairs and Grove Terrace Retaining Wall Projects\Council Letter Page 2 reinforced concrete and Geofoam blocks. The Geofoam blocks are a high density styrofoam block that reduces the lateral earth pressure on the retaining wall and allows the use of less limestone (and reduces cost). Grove Terrace will be reconstructed with 7" concrete pavement around the stairs and behind the retaining wall. Asphalt pavement will be placed to match up with the existing pavement of Grove Terrace on each end of the project. Recommendation By a vote of 7 to 0, the Historic Preservation Commission recommends City Council approve the repair and reconstruction of the W. 11th Street stairs and Grove Terrace retaining wall projects with the condition that the coursework is horizontal, the proposed light fixture be centered in front of the tunnel, and the tunnel be up lighted. A simple majority vote is needed for the City Council to approve the request. Respectfully submitted, ~liGt-` Christine Olson, Chairperson Historic Preservation Commission Enclosures cc Gus Psihoyos, City Engineer A®VIS®RY ®ESIGV~ REll9EW STAFF REP®R`~ ftfleetirtg ®ate: July 17, 2®®8 Pr®perty Address: W. 11t" Street Stairs & Grove Terrace Retaining Wall Property ®wner: City of Dubuque Applicant: ~ City of Dubuque Pr®ject: To repair and reconstruct the W. 11t" Street Stairs.and Grove Terrace Retaining Wall. Hist®ric Preservati®r~ ®istrict: W. 11th Lartdmarl~: No Funding: HDPIP (Stairs) ®ate Built: 1883 Present ,arid Use: Public Physical Characteristics: A massive stone vaulted tunnel marks the point where the West 11t" Street Elevator passed through the wall. Today a recessed shaft located at the center of Grove Terrace and on the West 11t" Street right-of-way, marks the point where the Elevator continued up and out of that tunnel and above grade up to Highland Place to the west. The West 11t" Street Stairs, of concrete construction, now parallel the former course of the Elevator. They extend from Bluff Street to the east, up the bluff front, through the tunnel and along the south side of the retaining wall that defines the bluff that fronts east behind the houses along Grove Terrace. l~arrative Statement ®f Significance: The City of Dubuque West Eleventh Street Historic District takes its name from the Eleventh Street Elevator. In 1877, it was noted that it was becoming increasingly desirable to build and live on the Bluffs and many downtown people were moving to the bluffs. The trend inspired the establishment of the Julien Avenue Railroad Company, which, despite a 25 year charter from the city, never ran a car up the bluff. The real success and inspiration to those who resided on the Eleventh Street Hill was that of Jesse Farley's private inclined railway service. Farley started his own service in 1883 and then started letting neighbors ride for a quarter. By the mid-1880s it was a success and survived numerous fires. In 1887 the Eleventh Street Elevator Company was established, began service in 1888, and began to use electrical power in 1890. The Eleventh Street Elevator differed structurally from the 4t" Street model because it was elevated high above the ground surface. The upper station was at Highland Place. The wealthy residents on Grove Terrace were less than pleased with the noise from the operation and in mid-1895 the company put rubber tires on the cars. The Herald reported at least temporary success, "the noise is hushed, neighbors satisfied and babies sleep sweetly and undisturbed again." Already by 1889 the elevator was being hailed as "a great convenience to residents on the hill"with a magnificent view that made it "a place of public resort not only by residents but for strangers visiting the city". Due to financial difficulties, the elevator was finally abandoned in 1927 and concrete steps now pass through the surviving arch. Staff Analysis: ~/. 99th Street Stair Project: This portion of the project will utilize $90,000 in HDPIP funds. City Council approved allocation of these funds to the W. 11t" Street Stair project on January 22, 2008. Advisory Design Review/HDPIP - W. 11t" Street Stair & Grove Terrace Retaining Wall Page 2 On September 20, 2007, the HPC reviewed and tabled the advisory design review for the repair and reconstruction of the W. 11t" Street stair project to a future meeting and requesting the Engineering Department evaluate the following options which are shown in bold. The City of Dubuque Engineering Department's response to the options is shown in italics. 1) Excavate the fill under the arch, remove the north facing stair, and consider a straight run of stairs. Historical photos show the stairs pretty close to their current configuration. It would also be cost prohibitive to replace the whole lower portion of the stairs and have them go straight out from the arch. 2) Limestone co~arseworl~ to run horizontal. The limestone course work will match what exists. Since the work involves replacing portions of the walls, we have to match the existing coursework. 3) ~p~light the arch instead of the pedestrian Sight fixture at the stair land'ang at the base of the arch. The light was moved to the top of Grove Terrace to provide security lighting to the top of the stairs and illuminate Grove Terrace. Engineering will look at an alternative way to illuminate the arch. This will probably be handled as a change order during the project. 4) combine the proposed decorative hoop railing with the existing style of handrail on the stair. The decorative hoop railing will be used along Grove Terrace at the top of the stairs. Limestone will be placed 2 feet above the street with the hoop railing above it to provide a crash barrier for cars. The existing style of hand railing will be used for the stairs due to cost and usability. The hoop railing is not very conducive as a hand railing on stairs. 5) A trash container is located at the bottom of the stairs. Engineering will coordinate the placement of a trash container at the bottom of the stairs. It will match the style we currently use in the historic districts. The proposed work will involve the removal of the street pavement on Grove Terrace around the upper portion of the 11th Street stairs, excavation above the existing arch, installation of a reinforced concrete bridge with ties to hold the existing arch in place, reshaping of the existing roadway subgrade to correct drainage deficiencies, installation of new curb and gutter and limestone barrier wall, installation of new concrete pavement and installation of new decorative fencing. The_ existing retaining walls along the 11th Street stairs will be repaired using native Dubuque limestone and properly tuckpointed. Existing materials will be used as much as possible with new materials Advisory Design Review/HDPIP - W. 11t" Street Stair & Grove Terrace Retaining Wall Page 2 matching the existing materials in size, color and material type. A historic pedestrian light is proposed to be placed at the top of the stairs on Grove Terrace. This will provide illumination for the upper portion of the stairs and Grove Terrace. The existing lighting under the arch will remain in place. The estimated project cost for the stairs portion of the project is approximately $200,000. Grove Terrace Retaining Wall: The Grove Terrace Retaining Wall will be reconstructed using existing limestone block that was salvaged from the wall failure. New limestone block will be cut and placed where needed. The dimensional size of the new limestone will match the existing retaining wall block. Behind the new limestone the wall will be backfilled with reinforced concrete and Geofoam blocks. The Geofoam blocks are a high density styrofoam block that reduces the lateral earth pressure on the retaining wall and allows the use of less limestone (an reduces cost). Grove Terrace will be reconstructed with 7" concrete pavement around the stairs and behind the retaining wall. Asphalt pavement will be placed to match up with the existing pavement of Grove Terrace on each end of the project. The construction cost for this portion of the work amounts to approximately $400,000 and the estimated completion date is the summer of 2008. The Grove Terrace retaining wall will not use HDPIP funds. The role of the Historic Preservation Commission in reviewing this project is to serve as an advisory design review body to the City Council for review of public works projects which have historic preservation implications at landmark sites. The Commission's recommendation will go on to the City Council with the application materials for their review and approval of the project. Minutes from the September 20, 2007 meeting are enclosed. Also enclosed are historical photographs of the stairs and plans for the projects prepared by IIW Engineers & Surveyors. Compliance with Guidelines: In 2002, the Streetscape and Landscape Guidelines were created to help provide recommendations for public improvements on public property. Prepared by: ~ °eviewed: G%~.-~-, Date: _ ~~~~ ~~ Minutes -Historic Preservation Commission September 20, 2007 Page 2 impact on the appearance of buildings. He stated slate was a very popular material on the larger, high style homes, and original materials should be retained and repaired whenever possible. He explained the guidelines state these materials can be prohibitively expensive, however, and substitute materials may be acceptable, if installed properly. He explained the guidelines suggest that if the original materials are no longer present, a severely deteriorated, or prohibitively expensive, substitute material, such as fiberglass, metal, or architectural asphalt shingles are acceptable. New materials should attempt to match the original in color, size and shape. He stated new asphalt or fiberglass material should be appropriate in color, such as black, gray, or dark brown. Dark red, blue/gray, and dark green are also appropriate if replacing slate or tile. The Commission questioned the percentage of roof that was slate. Mrs. Souto stated approximately 50% of the material on the mansard roof was slate prior to EIC Roofing removing the material. The Commission discussed the color and style of the shingles on 1655 Main Street and similar homes. Mr. Souto explained they would like to install laminated asphalt carriage house-style shingles on the mansard roof like those on the Ryan House, except in gray. Mr. Souto distributed photographs of mansard roofs found in Dubuque with the carriage house-style shingle that they want to install on 1655 Main Street. Motion by Wand, seconded by Bichell, to approve a Certificate of Appropriateness to install the laminated asphalt carriage house-style shingles as presented and gray in color. Motion carried by the following vote: Aye -Whalen, Olson, Wainwright, Bichell, Wand, Lundh and McDonell; Nay -None. ADVISORY DESIGN REVIEW: Request by City of Dubuque for Advisory Design Review of the project to repair and reconstruct the W. 11th Street Elevator/Stairs located at W. 11 t" Street in the W. 11 t" Street Historic District. Jon Dienst, City Engineering Department, reviewed the project. He described the project involves partial reconstruction and repair of the stairs and repair of the railing at the top of the West 11 t" Street stairs. He explained the project will involve the removal of the street pavement on Grove Terrace around the upper portion of the 11t" Street stairs, excavating above the existing arch, installation of a reinforced concrete bridge with ties to hold the existing arch in place, reshaping of the existing roadway subgrade to correct drainage deficiencies, installation of new curb and gutter and limestone barrier wall, installation of new concrete pavement and installation of new decorative fencing. The existing retaining walls along the 11t" Street stairs will be repaired and replaced where needed using native Dubuque limestone and proper tuckpointing. He explained the existing materials will be used to the greatest extent possible with new materials to match the existing materials in size, color and material type. He explained a historic pedestrian light is proposed to be placed along the sidewalk below the arch to provide illumination for the lower portion of the stairs as well as illuminate under the arch itself. He explained the City would like to begin this project in the spring of 2008 Minutes -Historic Preservation Commission September 20, 2007 Page 3 with an estimated completion date in the summer of 2008. He explained by removing the street above the arch and installing a concrete bridge to support the street over the arch, the arch will no longer support the weight of the street, consequently strengthening the arch. He explained that decorative hoop railings with limestone pillars will be installed at the top of the stairs. He explained the limestone pillars would be a bid alternate. He explained Engineering is also proposing a decorative pedestrian light on the limestone pillar to illuminate the arch and stairs. Commissioners discussed how the storm water will be handled. Commissioners reviewed which walls will be repaired and replaced. Staff Member Dienst explained how drain file will be installed and how the entrance at Grove Terrace will be changed. He noted the current stair entrance on Grove Terrace will be moved 90 degrees, and a vehicle barrier will be added. In response to the question by the Commission, Staff Member Dienst noted the course work will be horizontal and the plans are incorrect in this respect. He noted the project will take about two months and will block the entrance to one property. The Commission requested a trash can be added at the base of the arch. Staff Member Dienst explained that the existing rail would be sandblasted, painted and re-used where possible. The Commission requested that a more decorative hand rail or re-use of the existing rail with the hoop rail behind it. Staff Member Dienst explained that Engineering will evaluate how far the railing will be repaired and replaced, and a decorative railing may be a bid alternate. The Commission suggested using the decorative hoop railing proposed on the top of the stair entrance as the decorative rail to be used along to the stairs. Staff Member Dienst confirmed the existing arch supports will be cleaned and painted. The Commission discussed the proposed lighting at the base of the arch. The Commission recommended the historic pedestrian light fixture proposed at the stair landing at the base of the arch be relocated and fixed atop another of the proposed stone pillars. The Commission recommended discretely located and historically appropriate light fixtures to up-light and illuminate the under side of the arch as an alternative to the pedestrian light fixture. The Commission explained that would be a preferred lighting alternative since a pedestrian light fixture near the stair landing at the base of the arch would create an interruption in the sight line and distance as you look up or down through the arch. The Commission emphasized the lighting would have to be evenly distributed under the arch. The Commission discussed moving the switch back of the stairs under the arch. The Commission discussed the previous location of the West 11 t" Street elevator in relation to the stairs. Staff Member Dienst confirmed the stairs will follow the current alignment and be built to City Code. The Commission discussed whether the stairs could be rebuilt with a straight run without the dog leg by removing fill under the arch. The Minutes -Historic Preservation Commission September 20, 2007 Page 4 Commission discussed the added cost of excavation and removal of the north facing stairs. By consensus, the Commission tabled the Advisory Design Review for the repair and reconstruction of the West 11 t" Street stairs to a future meeting and requested Engineering evaluate the following options to be presented to the Commission at a later date: 1) Excavate the fill under the arch, remove the north facing stair, and consider a straight run of stairs. 2) Limestone coursework to run horizontal. 3) Up-light the arch instead of the pedestrian light fixture at the stair landing at the base of the arch. 4) Combine the proposed decorative hoop railing with the existing style of handrail on the stair. 5) A trash container be located at the bottom of the stairs. ITEMS FROM PUBLIC: Envision 2010 Rail Committee: The Commission discussed the memorandum from the Envision 2010 Rail Committee requesting support in bringing passenger rail service back to Dubuque. Motion by Bichell, seconded by McDonell, to direct staff to write a letter of support to bring passenger rail service between Dubuque and Chicago. Motion carried by the following vote: Aye -Whalen, Olson, Wainwright, Bichell, Lundh, Wand and McDonell; Nay -None. ITEMS FROM COMMISSION: Elect Vice Chairperson: The Commission discussed electing a new vice chairperson. Commissioner Wand stated the new vice chairperson should be someone who has not served as vice-chairperson or the chairperson of the Commission. He explained the vice chairperson position should be filled by a commissioner who would like to eventually become chairperson. Motion by Wainwight, seconded by Bichell, to nominate Commissioner Lundh to be vice chairperson for the Historic Preservation Commission. Motion carried by the following vote: Aye -Whalen, Olson, Wainwright, Bichell, Lundh, Wand and McDonell; Nay - None. HPC Meeting Location: The Commission discussed where future Historic Preservation Commission meetings will be located, given the recent renovation to the Historic Federal Building. The Commission noted that the old City Council Chambers in the Carnegie Stout ~; :~~,~ ~ irJ~"16 . A :.. _ . 1 r7. ' ~ r-~i _ _ i onn :~ ~'l .. e ~ .., f~ i ..~ ..L... ..1.. o~ r~nc.~narr~ 'V GJL 11 Ull 1. \.L lily V0.LV1, V.1 V~V, vii: vv yr von, ..uuav r.v .. a..v ..r......., .~.._.~__~.-» p--------- (internet source) ~- @LI_'f;NTYi `-+TIiEI;T ElF`JnTUH fSl_ISlfgllE ~'~'~~ West l lt' Street Elevator, postcard view to the northwest, c.1910-15 (website source) _ __ -_ _ - -- -`I >t , I s West 11th Street Elevator, c.1890, view southwest i , ,' `: i~ ~ "~ ' i ~ i ~ ~ `~ nS ,~~ ~ _, ' j~"~~~' Y , ~ 1 (~ ' Y ' ~ ` r ,I 1 (X'~ L ~'~ ij~ 17 '~ 1 _ ~- ~~ ~- _. ~ r ' 'r 1 J ~i } ~ S ~ ~ 11 ~ 5 ~__, ~~ t (~ . ~ ~, ~ ~ 1 i i ~ . - ( ~ ~'. ~ 1 f ' - - ". ~ -- :ter ~ ~$1 n. r+~ ~ nnn VVGJL 11 JL1GG1 DIGVQWI, 1:.107 V, V1GW WGSL, W1111G1 V1GW (Photo HAM 906, Center For Dubuque History, Loras College) THE CITY OF U~ ~' `~s ~~ City of Dubuque Planning Services Department Dubuque, IA 52001-4864 Phone: 563-589-4210 Fax: 563-589-4221 HILT I~ I~TRIC7° !J LC I E °T R LIC TI F PRO]ECT COMPONENTS (Check all that apply) ^ Historic Street Lights ^ Street Trees/Grates ^ Brick Sidewalks ^ Colored Concrete Sidewalks/Curbs ^ Benches ^ Landscaping/Plantings ^ Brick Crosswalks ^ Colored Concrete Crosswalks ^ Trash Receptacles X Decorative Fence/Rail ^ Brick Streets ^ Colored Concrete Street Paving ^ Planters ^ Decorative Bollards ^ Limestone Curbs X Other: Public Steps/Retaining Wall ^ Waysides/Plazas ^ Identification Signs X Retaining Walls ^ Other: Please type ®r print legibly in ink Type of Applicant: ^ Neighborhood Group ^ Neighborhood Association (Name: City of Dubuque) Representative: Bob Schiesl, Assistant City Engineer, City of Dubuque Phone: 589-4270 Address: 50 W. 13th Street City: Dubuque State: IA Zip: 52001 Fax Number: 589-4275 Mobile/Cellular Number: N/A Project Description: Repair the W. 11th St. stairs and Grove Terrace retaining wall. Project location/area: The W. 11th Street stairs & Grove Terrace retaining wall are located between Bluff St. and Grove Terrace. Total project cost: $600,000 Amount of Grant Request: $90,000 CERTIFICATION: I/we, the undersigned, do hereby certify that: 1. The information submitted herein is true and correct to the best of my/our knowledge and upon submittal becomes public record; 2. The undersigned representatives are authorized to sign this application on behalf of the neighborhood association or group; and 3. All additional required written and graphic materials are attached. Representative: 2cs~-1~ ~ ~tit~ Date: ~ ~3(? •- U~ Representative: Date: FOR OFFICE USE ONLY -APPLICATION SUBMITTAL CHECKLIST ---~_. Received by: z- ~- Submittal Date: ~ ~~ -~>~ HPC Meeting Date: 7-17-08 ®Site/sketch plan(s) ^ Petition/Signatures in Support ^ Photos ^ Catalog examples ® Project description ^ Budget Documentation ®Map(s) ^Other: ~~ -4_ i ~. 1, r _~ ~_ -- . _ Y • _r ~1" i -- ~, Ir ~ t _ F ' ~ r~ ~ ~~j c~• _~ ~ :-y _ _ ~ . _ ~ . ~ ~,:r. ' .v 1 / vk ~ ~ .. 71 n--~- ~~.~ ~L - ~'~.4; ...~' --=---- :~-- ~ J ~ "~ 5b t.ty~ t.~ ~ 3 i ~"F .~f ++kd +s ~t Sr ~t ~ht q N il~ {i, ~t i'w i9'N.y }},~~~ ~Ii -t- -r: t . ~I ~~ t 'r 4 .~' -. r ~~ ~ f ' , ` ' a , _"' _ _ ' ' ~ ~. ,.+," ;. ~, ~ ~. -• ~[ . ~ _ -~9 f --_ ,;;, ~ ,_ j; Y Jr1'; ~, r ~~, c.~^- --- ~-i ,~ ,, i•, . r5'. ~a #~; A "__ - 1 i --- - ~~ ,~ ~~ `~' ~~a ~c~~,;~c ~:• ~" } 11~ va ~-, 111br ~ p _ ~ g~~ ;.r,: t 11 `; ,-_ ~.-._ ~_ ~-= , ~ --. ~• <'~" - ~ _^~ _. _ _ ~/zT,A'~z:a~, ~: ::'i,, 'y' 15 :;(i , '~! `~ _ `~ 1 ~~ Yk ~ ' . y • ,- 1i I ' r ~. ' } F3 rL 3' ~. T ~~ .fi, ~!'s 'r 4` •' . ~, ~~~ r,~ r 1 r-F.~AF-- --T p} - ~. ~+ a •- v ~ F,~ - - ~ ? ,li k!° c~ i 3~.y c ^y •~.~ ~r~,r m-: ~ - , r a - 1 i s .f2 ~y :' ~. wr ~~~ ~ ~`~ P' 6. ,,:~_. _ ~. ,~ `~ ; .: F :.` +. ~f r -~ J_ Y _-~ I~_ - ~~,~ ~_~ ~ ~~, ~. :; ~ ~~~ ~;_ ~ li e ~ Jfti _ 'REF •. ~'_~~ ~~, , - ~~~ll,t a ~' i ;~ .u~ ,. ~~ i ~, ; .. .f. ~~ . ~~, % ,f ~~`'~ ~, "~ ~, ,i `~ ~ i ~ ~ 1 !~~~,~ ~_. ,. ~~~~ .'. . , - ~" t. '~~`~~.~. r y C• -__~ ~i ~ I- - - -'} - ~ -t _ i ~3 -~.s::. _ _ - ._ ~'~? f_ ~ 1 4 Af'~ ~ ~l ti ~ ~ 4 Vii' f( ,. ,~ ~,~, . ~~ ~~, ~=. ."` - ~ ia ~..~R-r 1~~, _b. ~ ~ Ili '~i . s'' t.. 1 - ~~ '~' ~ ~ ", ~ ~ o ~ _ ~ ~. i; ~ ° ~ j ~ e~®~.:°; ,spa - ~x ;~";I ~``' t'. ~ '~ •~ ~ ~ ~ ~ x~ ~ t ~ ( ,,,~. ' ' ~~ 1 _ _ r.. ~ '~~ z jtt • i S f ~ ! °y - ~! J y~ ..J. ~ . fi „~. ~ S '~..11471r L,f., :.i Y .4 ~ ~ L.i / ~ J; j. J f f f- .~ I ~~ri~ 1 1 ~J~ J /-~ J1~ r~rr frt. - F~-/ .rt ..?.t1 ~ 1 • J sift. 2!2! ~ ' - .~ .~.° ,~r. tip, ~ ~~: ~J .: ;,, j~ . ~ ~~ ~1i ~i ,t 1W Y 11 + ~' Ie,~ ~ ~}. ,f r rm'. c J '~ ~~ . v ,~. -~ I ' t ~t r i \y ~ ~ :~.~ f j `! l ~t , ~~ ~, ~,- j'~,1;. '~~ ' ~e'~ rti ,./ ,~ f ~,~~,.. ~~~, ' ~ _l ..~ .~, ~ ~;~~ <. ~~ '1 ~- ~~. ._;~, 4 ,rf}, }•1 G,V , ~. ,• 1 ~ ~i il°!rl ~ t~ : ' ~3 i ~ : j~ ~~ ~~~+ y , ..4 .1 F .Y ~, i 1 -- ~ i '` -iS ~ + 1 ,1' 1 ~: ~° , . - ~, x \ w_xf ~ F~ ! `~ F f 1 ~• r'!-' ys l~ ~~ ` t t ~ ~ t 1 :, t; ~ ! r... -. ~ ~~~ ^ ~j '' ~ ~r ~ t i{. ~.i .~ " ~ ri%,~ l d € ! ~-, w I~ e'• I ~ L'rf~~Tli Ct {~ In tt i -~ l ~ I } a/ ~ ~ ~ ~+.c k s4~'~4 ~' ~II II I I! i ~.jF .~t`E ~lt~ ~'L a ~ a '. _ r ~ a~'F i ~ ~ ' t . _ ~ Z ~ ~~ ~ r; ~ .,~r~ ~ t ~fYt p', ~y',',d'$~~ ti~tf 2~, ,L iw ~A ~ V- ._~ ." ~ ~ t ~..~ ~?""_~ - ~ iT= JIi ,~ • ~ .~ - r,, a ., ~. , r~~ l , .'r; ~' . '~ ,~ .._~ r ~.. ~ ~t' ,,. r - t-,. A n. t i It-.~~" s ~ r~rr ; ~-°' :~ ,; t ..~ ,r ~! - ~~ „ i. ,y~~.~ ~,~ .gyp .r - 4,, p: •t }5~~~~ y'am' > "~ 1 ~Y~~.~ ' ~ 5 ~~. a ~: '!' r .Y '~ ":-1 - ~ ~' ~ ~~ ~ .alb s Ti~ar~ : . _~ ~-.ate ~ r _ ~ ~ ~ i ..~~, f~`" .~-t• s~.s .- - ~..^' -•j ~'YIMr ~vfr r~Y ? .~ __ i'_ . jr . :, _ _ ,. - ,~ ,. >1 ,~ ~ ~ ~ ~ a (~f\, '', 7 ~ ~ ~. ..~. ~.=e ~ ~i 111 ~ 111 . ... .., RETAINING WALL REPAIR DUBUQUE, IOWA I~ P ~ ' ~ ~, ='t '" ~ ~~ ~ ,.~. ~; n ~ - ' Sy ~ i ~ ~ ~ ~ ~ ~ l ~ ~ .< i ~ e ~ ~ ~ ~ c P r ~ n ~ 4 ~ ,d ~ ~ IVY 1 ~ ~ _ ~' A _ - &1 1 . ~ c s ~, ._~'' t_ ~ ~ .. PRO~CT LCCADCN SHEET INDEX ----_ --- = - SHEET REVISIONS NOMEER~ SHEET TITLE _ 1I Gll Gt2 ~ COVERSERiET _ CIVIL AHBREVNTiONS ANDLEGEN_D _ ~ ` _ ~ G13 ~ Cl l ~ STRUCTURAL NOTES _ SITE PLAN __ _ _ _. _ C12 ~ SANITARY SEWER PLAN AMI PROPR,E -_ __- ._ ~ _ SIO ~ FOUNDATION PLAN AND DETAILS _ slt ~ L STRUCTURAL DETAILS ~.. 812_,~ _STRUCTURAL DETAILS __ _I 813 I STRUCTURAL DETAIlS 0 I X8850 ~ ~ 1+60 CROSS SECT[ONQ _ _ 52A1 STRUCTURAL DETAII.S _ _ 521 RETAINING WALL PLAN AND ELEVATION _ _ _ i C _ 52 2 RETAMMG WALL PLAN AND ELEVATION . S23 _ S24 _ RETARDING WALL PLAN AND ELEVATION RETAINNG WALL PLAN AND ELEVATION __ j ~ S26 RHTAN~MG WALL PLAN AND ELEVATION 52.6 RETAMMG WALL PLAN AND ELEVATION _ _ 52.7 RETARDING WALL PLAN AND ELEVATION J _ S28 RETAINING WALL PLAN AND ELEVATION RETAINRDO WALL PLAN AND ELEVATION _ _~ 82.10 RETANING HALL PLAN AND ELEVATION - - - _ --- ~- _ __ I - __ H W x .. ~ v W p1O m U w N~ W A 0 0 N I 0 W a a z 0 Q z N ~ W C' a h a ~] rl ~ x ~o ~ th ~ .~ W ~ ,~ ~,~zc~ ~FaA `~U° ws F ~ ~ ~ n W o da® WAN ~Q~ ~OW z~~ s" N W s~„ !~y~ ., ~_ F-~ ~ ~ a ~Z w r-~ iA z o „ °> PROJECT LOCATION NO SCALE Project Mgr: HSM Project Number: 08148-04 © 111 L n q v v D V 9 CIVIL ABBREVIATIONS d CENTRAL ANGLE EL ELEVATON L LENGTH OF CURVE AC ACRES ELEC ELECTRICAL LAT LATERAL AO ALGEBRAIC DIFFERENCE ELY EASTERLY LB/~ POUND AGG AGGREGATE ENGR ENGINEER LF LINEAL FOOT ALT ALTERNATE/ALTERATION/ALTERNATING ENTR ENTRANCE LP LIGHT POLE ARCH ARCHITECT/ARCHITECNRAL EOP END OF PROJECT LPT LOW POINT ASPH ASPHALT FOR END OF RADIUS LT LEFT AVG AVERAGE E/P EDGE OF PAVEMENT MAX MAXIMUM B-B BACK OF CURB TO BACK OF CURB EQ EDUAL ME MATCH EXISTING B/C BACK OF CURB E/S EDGE OF SHOULDER MECH MECHANICAL B/DITCH BOTTOM OF DITCH ESMT EASEMENT MFR MANUFACNRER B/L BASE LINE EST ESTIMATE MH MANHOLE B/S BOTTOM OF SLOPE E%C E%CAVATE/EXCAVATION MIN MINIMUM BFP BACKFLOW PREVENTOR E% EXISTING M1SC MISGELlANE0U5 BOP BEGINNING Of PROJECT EW EACH WAY MOD MODIFY BV BUTTERFLY VALVE FD FLOOR DRAIN MON MONUMENT B.M, BENCH MARK FDN FOUNDATION N NORTH BOT BOTTOM FE FIELD ENTRANCE N/A NOT APPLICABLE, NOT AVAILABLE 8RG BEARING FES FLARED END SECTION NE'LY NORTHEASTERLY ESMT BASEMENT F-F FACE 70 FACE NIC NOT IN CONTRACT C&G CURB AND GUTTER FFE FINISH FLOOR ELEVATION N'LY NORTHERLY CATV CABLE TELEVISION F&I FURNISH & INSTALL NO/# NUMBER CB CATCH BASIN FG FORM GRADE NOM NOMINAL C-C CENTER TO CENTER FIN GR FINISHED GRADE NTS NOT TO SCALE CF CUBIC FEET FL FLOWLINE NW'LY NORTHWESTERLY CH CHORD FLR FLOOR OC ON CENTER CH BRG CHORD BEARING FM FORCE MAIN OD OUTSIDE DIAMETER CIP CAST IRON PIPE FND FOUND PC POINT OF CURVE CISP CAST IRON SOIL PIPE FT FOOT/FEET PCC PORTLAND CEMENT CONCRETE CJ CONTROL JOINT OR CONSTRUCTION JOINT FTG FOOTING PCF POUNDS PER CUBIC FOOT CL CENTERLINE FUT FUTURE PED PEDESTAL/PEDESTRIAN CLR CLEAR FV FIELD VERIFY PERF PERFORATED CMP CORRUGATED METAL PIPE G GUTTER PERP PERPENDICULAR CO CLEAN OUT GA GAGE PI POINT OF INTERSECTION CONC CONCRETE GC GENERAL CONTRACTOR P/L PROPERTY LINE CONST CONSTRUCTION GND GROUND PM PRINCIPAL MERIDIAN CONT CONTINUOUS GV GATE VALVE PO8 POINT OF BEGINNING COR CORNER HMA HOT MIX ASPHALT POC POINT ON CURVE CP CONTROL POINT HORIZ HORIZONTAL POT POINT OF TANGENT CPE CORRUGATED POIYETH YLENE PIPE HP HORSEPOWER PRC POINT OF REVERSE CURVE CRST CRUSHED STONE HPT HIGH POINT PROP PROPOSED CSP CORRUGATED STEEL PIPE HT HEIGHT PRV PRESSURE REDUCING VALVE CTR CENTER HYD HYDRANT PSF POUNDS PER SQUARE FOOT CU CUBIC ID INSIDE DIAMETER/INSIDE DIMENSION PSI POUNDS PER SQUARE INCH CULT CULTIVATED IE INVERT ELEVATION PT POINT OF TANGENCY CV CHECK VALVE IMP IMPROVEMENTS PVC POLYVINYL CHLORIDE CY CUBIC YARD IN INCHES PVMT PAVEMENT D DEGREE OF CURVE INFO INFORMATION R RADIUS DIA DIAMETER INSP INSPECTION R&R REMOVE AND REPLACE OIM DIMENSION INST INSTALLATION R&5 REMOVE AND SALVAGE DIP DUCTILE IRON PIPE INSUL INSULATION RCB REINFORCED CONCRETE 80% (CULVERT) DN DOWN INTR INTERSECTION RCP REINFORCED CONCRETE PIPE DRWY DRIVEWAY INV INVERT RD ROAD DS DOWNSPOUT IP IRON PIPE R.D. ROOF DRAIN E EAST JB JUNCTION BOX REBAR REINFORCING BAR EA EACH JT JOINT LENGTH REF REFERENCE EJ EXPANSION JOINT K RATE OF VERTICAL CURVANRE REINF REINFORCED REQ REQUIRED VERT VERTICAL REV REVISION VOL VOLUME RIM RIM ELEVATION VPC VERTICAL POINT OF CURVE ROW RIGHT-OF-WAY VPI VERTICAL POINT OF INTERSECTION RP RADIUS POINT VPT VERTICAL POINT OF TANGENCY RR RAILROAD W WEST RS RESILIENT SEAT W/ ~N' RT RIGHT W/D WITHOUT S SOUTH WLY WESTERLY 5= SUPERELEVATION Whf WATER MAIN SAN SANITARY W'50 WATER SHUT OFF SANS SANITARY SEWER NR WEIGHT SB SOIL BORING WM WATER VALVE SCH SCHEDULE WWF WELDED WIRE FABRIC SD SUB DRAIN % CROSS SEC SECTION YD YARD SE'LY SOUTHEASTERLY SF SQUARE FOOT SHT SHEET SLY SOUTHERLY SPEC SPECIFICATION SQ SQUARE ST STREET STA STATION i EXISTING SU RFACE PROP SED ~ AT PROPOSE D ~ 0.EV .- ~ n ~ a $ 0 o a n o 0 n 0 n STD STANDARD 21+20 21+60 STL sTEEL PROFILE LEGEND STM STORM STMS STORM SEWER STR STRUCNRE/STRUCNRAL SW'LY SOUTHWESTERLY SY SQUARE YARD SYM SYMBOL SYMM SYMMETRICAL T TANGENT LENGTH T/B TOP OF BANK T/DITCH TOP OF DITCH T/C TOP OF CURB TCE TEMPORARY CONSTRUCTION EASEMENT TEL TELEPHONE TEMP TEMPORARY T/GRAV TOP OF GRAVEL THK THICK /THICKNESS T/WALL TOP OF WALL T/P TOP OF PAVEMENT T/S TOP OF SLOPE T/SUB TOP OF SUBGRADE T/W TOP OF WALK TNP TOWNSHIP TYP TYPICAL U UTILITY VAC USE AS CONSTRUCTED UE UTILITY EASEMENT UL UNDERWRITERS LABORATORIES, INC. ULFM UNDERWRITERS LABORATORIES FACTORY MUNAL VAR VARIES VC VERTICAL CURVE VCP VITRIFIED CLAY PIPE EXISTING LEGEND - - - - PROPERTY LINE -~ ~-~ ~- EASEMENT - - - CENTERLINE - 0 - STORM SEWER -SD- SUB GRAIN - S SANITARY SEWER - FM - FORCE MAIN - W - WATER LINE - G - GAS LINE -OHE- OVERHEAD ELECTRIC - E - UNDERGROUND ELECTRIC -OHT- OVERHEAD TELEPHONE - T - UNDERGROUND TELEPHONE -OHN- OVERHEAD TELEVISION - N - UNDERGROUND TELEVISION -OHU- OVERHEAD UTILITY -FIB- FlBER OPTIC - % - WIRE FENCE - 0 CHAINLINK FENCE - ^ - WOOD FENCE ---p00--- CONTOUR LINE ~I il~j- 1~~~~~~~~ RAILROAD TRACKS GUARDRAIL + O.OD SPOT ELEVATION ~~.i DIRECTION OF FLOW ivv~.-... TREE LINE ® CATCH BASIN ® AREA INTAKE ® STORM MANHOLE QS SANITARY MANHOLE QU UTILITY MANHOLE 0 WATER VALVE MANHOLE FIRE HYDRANT ~o° waTER srluT aFF WATER VALVE 0 YARD HYDRANT cv pQ GAS VALVE -~ slcN ~ UTILITY POLE r~ UTILItt POLE WITH LIGHT t~ TRAFFIC SIGNAL POLE 4 GUY ANCHOR }~ t1GHT POLE ^ UTLITY PEDESTAL ® WELL ® MAILBOX ~ WATER LEVEL i0~ BOLLARD SOIL BORING 1 DECIDUOUS TREE ~ W/ TRUNK DIA. CONIFEROUS TREE /~ W/ TRUNK DIA. SHRUB OR BUSH ® FOUND IRON ROD i FOUND IRON PIPE Q SET IRON ROD 0 CONTROL POINT - D - -SD- - S - -FM- - W - - G - -OHE- - E - -OHT- - T- -OHN- - N - -OHU- -FlB- - X - - 0- - ^ - -DDO- t 0.00 r 0 0 r~ U DQ rD.+ 0 A 0 c N I a w 5 a a w 0 d m a ro 7 "o w 0 z O F d az .. PQ CO ~ ~ a Ha m ~ A v.,z m U d W O Ch A z a E a W ~ a ~ ~ h r] ~ „~ d ~" ~ O ~ ~~ r-i W Z ] ~,~z~ ~W~A Z 3h~ ~~~ ~s tea; ~ e Ri ~ ~a° W~ ~~~o WR~.ra, °~ wm z~~ ~ w ra W ~; 3~N~ ~a aN~ H C/1~ o~> Project Mgr: &1M Project Number: D8I4A-04 1, Stmctural Design Criteria 1. Building Codes. A. Governing Building Cade: 2096 International Building Code. 2, Llve Loads. A. Uniform; Traffic Surcharge: 50 psF 3. Soil Loads A. Design lateral soil load: 4D psF/k B. Allowable passive pressure: 345 psi/k C. Sall unit weight: 115 pcf D. Design coefficient of friction: 0.35 Earthwork 1. Comply with applicable provisions of the following specifications and documents: A. OSHA 29 CFR, Part 1926, Subpart P 2. Material Properties: A. Silt Fence: Iowa DOT Section 4196.01A Engineering Fabric. 8. Satisfactory Soils: ASTM D 2487 5011 Clossifcation Groups GW, GP, GM, GC, SW, SP, 5M, SC, CL, ML, or a comhinatlon of these groups; free of rock or gravel larger than 3 inches In any dimensions, debris, waste, frozen moteriols, vegetation, and other deleterious matter; liquid limit less than 45; and a maximum plasticity index of 211. C. Unsatisfactory Soils; ASTM 0 2487 Soil Classifications Groups OL, CH, MH, OH, and PT, or a combination of these groups; ar soils not maintained within 2 percent of optimum moisture content at time of compaction. D. Subbase Material: Iowa DDT Section 4122.02 Macadam Stone Bose Material, Gradation 13 with choke stone material retained on a Y" sieve included with no more than 10% passing a #200 sieve (Modifed Macadam). E. Base Course; Iowa DOT Section 4120.04 Class A Crushed Stone, Gradation 11. F. Engineered Fill: Iowa OOT Section 4132, Special Backfill, Gradation 30. G. Drainage Course: ASTM D 448, narrowly graded mixture of washed or crushed stone, ar crushed and uncrushed gravel; course-aggregate grading size 57; with 100% passing a 1~' sieve and less than 5% passing a No. 8 sieve. H. Fllter Material: IDwa DOT Section 4131, Porous Backfill, Gradation 29. I. Sand: ASTM C 33, fns aggregate, natural, ar manufactured sand. J. Perforated Polywthylene SubdroN: ASTM F 405 or AASHTO M 252, Type CP; corregated, far coupled joints. 3. Provide temporary erosion and sedimentation control measures to prevent so7 erosion and discharge of soil-bearing water runoff or oirbarn dust to adjacent properties and walkways. Inspect, repair, and maintain erosion control and sedimentation control measures until permanent vegetation has been established. 4. Do not interupt utilities sen4ng facgities occupied by the Owner or others unless specifically permitted. If permitted, temporary utility services shall be provided. 5, Topsoil Stripping: Remove sod and grass before stripping. Strip topsoil to whatever depths are encountered and stockpile away from edge of excavation. Do not stockpile within tree protection zones. 6. Protect structures, utilities, sidewalks, pavements, erosion and sedimentation control, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards caused by earthwork operations. 7. Uniformly grade areas to a smooth surface, free of irregular surface changes. Slope grades io direct water away from buildings and to prevent ponding. 8. Plow, scarify, bench, ar break up sloped surfaces steeper than i vertical to 4 horizontal sa fill material wBl bond with existing material. Place and compact fill material In layers to required elevation and as follows: A. Under walks, pavements, building slobs, footings, and foundations: Engineered Fill. B. Under all other areas: Satisfactory Soil. 9. Excavations shall comply with the fallowing: A. All excavations should comply with the requirements of OSHA 29 CFR, Part 1926, Subpart P, 'Excavations and Trenches" and other applicable codes. B. Excavate todimensions and elevations indicated. C. Footings and Foundations: Excavate by hand to final grade and compact soil at bearing surface prior to placing footings to firm up all loose material from excavation, fanning, etc. 1D. Place backfill on subgrades free of mud, frost, snow or Ice. Place and compact backfll In excavations promptly. it. Subbase and Base Course: Shape Subbase and hose course to required crown elevations and cross-slope grades. For subbase or base courses less than 6 inches in compacted thickness in a single layer, far subbase or base courses greater than 6 inches in compacted thickness in multiple layers of equal thicknesses, with no compacted toyer less than 3 inches or greater than 6 inches. 12 Contractor shall notify project engineer to obtain samples and perform laboratory density testing and to conduct compaction tests as required. Compaction requirements are subject to adjustment depending upon the material density. A. Compact sag materials to not less than the following percentages of maximum dry unit weight according to Standard Proctor Compaction Test (ASTM D 698): (Q Under structures, building slabs, steps, and pavements, scarify Dnd recampact top 72 inches of exlsting subgrade and each layvs of backfll ar fill soil material at 98 percent. (2) Under walkways, scarify and recampact top 6 inches below subgrade and compact each layer of backfill or fill soB material at 92 percent. (3) Under lawn or unpaved areas, scarify and recampact {op fi inches below suhgrode and compact each layer of backfill or fill soil material of 85 percent. (4) Place backfill and fill soli materials In layers not mare than 8 inches In loose depth for material compacted by heavy compaction equipment, and not more than 4 inches in loose depth for material compacted by hand-operated tampers. (5) Place backfill and fill soil materials evenly on all sides of structures to required elevations, and uniformly along the full length of each structure. 13. Foundation design (s based upon on allowable soli bearing capacity of 3000 psf and a subgrade modulus of 100 psi/mch. Contractor shall notify Engineer prior to commencing with formwork for field verification of bearing capacity. Contractor shall make madifcations os directed by the Engineer 14. Protect newly graded areas from traffic, freezing, and erosion. Wnere settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surface. 15. Legally dispose of surplus soil material and waste materials off Owner§ property. Cement Concrete Pavement 1. Perfarnance Requirements: Class C concrete. 2. Comply with applicable prousions of the following specifcations and documents: A. City of Dubuque Standard specifcations Section 74 Portland Cement Concrete (P.C.C.)", as published by the Clty of Dubuque Engineering Division, except as follows: (1) Protect freshly placed concrete from premature drying and excessive cold or hat temperatures. Cure concrete by moisture curing, moisture-retaining-cover curing, curing compound, ar a combination of these methods. B. City of Dubuque Standard Specifcations Section 18 Pavement Marking', as published by the Ciiy of Dubuque Engineering Division, except as follows (1) Allow pavement to age 30 days before starting pavement marking. Cast-in-place Concrete i. Induded Items: A. Footings B. Concrete Backfill C. Abutment Walls 0. Structural Slabs 2. Testing/Inspection Requirements A. Owner will engage a qualified Independent testing and Inspection agency to sample materials, perform tests, and submit test reports during concrete placement according to ACI 307. B. Contractor shall notify Engineer-a minimum of 24 hours prior to any pour for field testing and inspection to be conducted as necessary. 3. Comply with applicable provisions of the following specifications and documents: A. ACI 301, Specificotian for Structural Concrete,"Sections 1 through 5 B. AG 318, ~ullding Code Requirements for Stmctural Concrete." C. AG 117, 5pecificatlons for Tolerances for Concrete Construction and Materials." 4. Material Properties: A. Reinforcing Bars: ASTM A 615 Grade 60 (#4 and larger), Grade 40 (#3) B. Anchor Rods: ASTM A 307 or A 36 threaded rod C. Portland Cement: ASTM C 750 Type I or II. Supplement with the following: (1) Fly Ash: ASTM C 618, Class C or F. (2) Ground Granulated Blast-Furnace Slag: ASTM C 989, Grade 10D or 120 D. Aggregate: ASTM C 33 (furs and coarse), uniformly graded, from a single source E. Water: AS1M C 94 and potable F. Air Entraining Admixture: ASTM C 260 G. Other Admixtures: ACI 212 & ASTM C 494 (chloride admixtures not allowed). Use only with written approwl of the Engineer. 5. Concrete design shall utilize the above specified materials and be designed as follows: A. Cementitious Materials: Umlt percentage, by weight, of cementitlous moteriols other than poriland cement in concrete as follows: (1) Fly Ash: 15 percent. (2) Ground Granulated Blast-Fumace Slag: 30 percent. (3) Combined Fly Ash and Ground Granulated Blast-Fumace Slag: 45 percent with fly ash not exceeding 15 percent. B. Footings and Concrete PoI: Proportion normal-weight concrete mixture as follows: (i) Minimum Compressive Strength: 3000 psi at 28 days. (2) Maximum Water-Cementitious Materials Ratio: 0.50. (3) Slump Limit: 5 Inches, plus or minus 1 Inch. (4) Air Content: 6 percent, plus ar minus 1.5 percent at point of delivery. C. Abutment WDlis: Proportion normal-weight concrete mixture as follows: (1) Minimum Compressive Strength: 4000 psi of 28 days. (2) Maximum Water-Cementitious Materials Ratio: 0.45. (3) Slump Limit: 4 Inches or 6 inches for concrete with verified slump of 2 to 4 Inches before adding high-range water-reducing admixture or plasticizing admixture, plus or minus 1 inch. (4) Alr Canteni: 6 percent, plus or minus 1.5 percent ai point of delivery. D. Structural Slabs: Proportion normal-weight concrete mixture as follows: (1) Minimum Compressive Strength: 4000 psi at 28 days. (2) Minimum Cementitious Materials Content: 540 Ib/cu. yd. (3) Slump Limit: 4 inches, plus or minus 1 inch. (4) Air Content: 6 percent, plus or minus 1.5 percent at point of delivery. E. Limit water-soluble, chloride tan content in hardened concrete to 0.15 percent by weight of cement. 2. Maintain continuity of reinforcement with staggered lap splices. Reinforcing lap splices shall be in accordance with-'Reinforcing Steel Lap Splice Oetails'shown elsewhere on this plan. 3. Standard hooked bars shall be in accordance with Standard Nook Details'shown elsewhere on this plan. 4. Maintain continuity of reinforcement at all discontinuities. Refer to the typical corner reinforcing, wall, and footing details. Limestone Retaining Wall 1. Material Properties: A. Limestone; Sound, horizontally bedded limestone in naturally occurring layers. Reuse sound salvaged materials stored an site or in Becker quarry on Kaufman Ave. where possible. (1) Abrasion Loss: AASHTO T 9fi, no greater than 50 percent (2) Size: As shown on plan (3) Finish: Guillotine cut, na projections ar depressloms greater than 2 Inches from the plane of the face, or face planes more than 2 Inches In 12 Inches out of square with adjacent face planes. B. Engineering fabric: Nan-woven polypropylene fabric intended for subsurface drainage purposes, UV stabilized, ozone resistant. (1) Minimum Grab Strength: ASTM 7682, 100 pounds (2) Equivalent Opening Size: 50-100 U.S. Standard Steve C. Mortar: Type M or 5 D. Geofoam: Foam-control expanded polystyrene (EPS) Geafcam treated by the manufacturer with a tested and proven termfte treatment for below grade applications, 3 year minimum field exposure. The treatment shall be EPA registered, meet requirements of ICC ES EG239, and he recognized In an ICC ES report. {i) Type, ASTM D6817 Type EPS15 (2) Warranty 2D year physical property warranty (3) Submittals: Manufacturer's product literature and technical data. 2. Set footing forms to line and grade as shown on the plans ar specified elsewhere. Footing top elevation shall normally be set level, with changes In grade being made as steps in the footing for a full course height of the bottom course thickness. The footing shall be cast on a 1:12 slope so the wall Is battered into the backfill. The footing shall project as shown with the top sloped to drain away from the wall. The footing top finish shall be roughened to receive and band to the mortar bed. 3. Stone shall be set to the sizes and dimensions shown on the plan. Bed joints far each course shall be a uniform layer of mortar to receive the next course of stone, and placed just prior to placing the stone so each course (s set in fresh mortar. Mortar beds shall be a minimum of 6 inches wide on each face of the stone. The front (ace mortar bed shall be set back 2" ar as determined by the Engineer to give appearance of dry set stone similar in appearance to undisturbed existing wall. Head joints between stones shall be set tight with no more than a'h inch gap of the narrowest point. Only mortar head joints in the cap stone course. 4. Mortar shall be allowed to cure at least 3 days before placing backfill against courses placed. Fabric shall be placed over the entire surface of the wall, with minimum laps of 1'-0". Horizontal joints in the fabric shall be "shingled"ta d'vect water away from the wall. 5. Backfill shall be placed in lifts and compacted as shown above behind the wall, but no closer than 3 feet to the wall. Drainage course aggregate shall he placed In a maximum thickness of 12 Inches and compacted with at least two passes of a hand N6ratory compactor. Materials may be wetted to obtain optimum moisture, but flushing in place will not be allowed. Do not urn heavy compaction equipment within 3 feet of the wall. STANDARD HOOK DETAILS HOOK DETAILING AA 0~ v DIMEN ION ___d ~ ~D 4db OR 9/J2' M1N. L D =FINISHED INSIDE BEND DIAMETER BAR SIZES STANDARD HOOKS STIRRUP/TIE HOOKS #3, #4, #5 6db 4db #6, $7, #8 6db 6db #9, #10, $11 Bdb Bdb #14, #18 lOdb tOdb rib =NOMINAL BAR DIAMEIEI 9)0' 8AR SIZE DIMENSIONS OF STANDARD 180-DEG HOOKS, ALL GRADES DIMENSIONS OF STANDARD 90-DEG HOOKS, ALL GRADES AORG J D AORG D 5„ 3,. ~,,, 6" 2Ya" #4 6„ 4„ 3„ 8. 3. #5 7„ 5„ 33'a° 10" 33'4 #9 1,_3„ 113a° 9Y2° 1'-7° 9Yz„ #10 1'-5" 1'-tYa'~ 103a 1-1 D" 103a" #11 1'-7° 1'-23'1 12" 2-D 12° #14 2'-3" 1'-93'a 16Y4 2'-7" iBYa" #18 3-0 2'-4)rZ" 24° 3-5 24° D =BEND DIAMETER D,DaO °oo xQ OW A OR G,~- o G w a rib ~ Z i „ w ~D ~ BEAM 90. STIRRUP HOOKS (TIE BENDS SIMILAR) BAR 90' 135' SIZE D A OR G A OR G APPROX. H #3 1Nz° 4° 4„ ~" #4 2° 4$" 4$" 3" #5 ~° 6 5Jru" 33'4 #8 6 1'-4' 10Ya" 6" °oo =a SEISMIC STIRRUP/TIE 135' SEISMIC HOOK SIZE D A OR G APPROX. H #3 iNu° 4Ya" 3° 4 2" 4Nz° 3" 5 2Yt° 6$° 3'/(~ 4Yz" 73"' 4Yt„ #7 5Y: 9" 6Y° #B 6" tOYa' 6° Reinforcing Steel Laps Maintain continuity of reinforcing with staggered lap splices. Refer to the typical corner reinforcing, wall and footing step details. Reinforcing lap splices shall he in accordance with the chart below. Splice lengths are specified in inches. arras e p ice stren th t e 3000 psi. Class A Top 29 36 43 63 72 81 Class A 22 28 33 48 55 62 Class B Top 38 47 56 81 93 105 Class B 29 36 43 83 72 81 4000 psi Class A Top 25 31 37 54 62 70 Class A 19 24 29 42 48 54 Class B Top 33 41 49 71 81 91 Class D 25 31 37 54 62 70 5000 psi Class A Top 23 26 34 49 56 63 Class A 17 22 26 38 43 46 Class B Top 29 36 44 63 72 81 Class B 23 28 34 49 56 63 Defnition of use: Class A: Slab reinforcement Class B: All other concrete and masonry reinforcing a. Bar spacing and bar clear cover must satisfy one or both of the following requirements: 1. Clear spacing between spliced bars must not be less than the diameter of the bar being spliced, the clear cover to the spliced bars must not be less than the diameter of the bar, and code required stirrups or ties must be placed throughout the splice length . 2, Clear spacing between spliced bars must not be less than two times the diameter of the bar being spliced and the clear cover to the spliced bars must not be less than the diameter of the bar. b. Horizontal reinforcement with more than 12° of fresh concrete below shall be considered as top bars, except wall reinforcing. c. These splice lengths have keen developed specifically for the conditions of this project in accordance with ACI 318-95 sections 12.2 and 12.15 and shall be used for this project only, d. Horizontal reinforcement splices shall be staggered a minimum of 4'-0". e. Chart applies to ASTM A615, grade 60 reinforcing only. DETAILING ~ DIMENSION u 0 rc ~ O N '~_ A 0 i 0 N I 0 a a a W E O z a P'i Y F F ] ma m (E/] Ix t~ Q z (~ ~ W ~ P. ~' R+ (~ ~ a ¢' x ~a zw W .y .7 E 6z~° ~waa Z 3". ~Uo ~S~ ~i a ~ o wa„ W~; ~p~ ~~ht w V~N ~~ zWw W~~ s~ ~~ aHw ~°'~z q~> Project Mgr: BTM Project Number: 00146-04 ©I 1, BEAM L BEAM 135. h ~ N \ NEW z a m ~ a° INTERGAL FULL DEPTH 1 CURB/GONG N®RTH ~ m SAW-CUT r^ SIDEWALK a c c 1 HORIZONTAL SCALE IN FEET y ~ SLOPE CONC AWAY O tD 20 m ° ~~ FROM EX WALL ~ SEE DETAIL 3/5201 CJ o` 1'69 ~IaN oy DRAWING MAY NAVE BEEN REDUCED 1~ pJ T/ROCK CURB ~ ~ T1 END 719.36 ` SALVAGED LIMESTONE RETAINING WALL W/ TL-2 BARRIER RAIL do WROUGHT IRON RAILING SEE SHEETS 52.01 TO 52.10 UTILITY NOTE tJP y0 ~' THE LOCATIONS OF THE EXISTING UTILITIES SHOWN ARE OJ fig' CONC PAVEMENT SHALL OJ T P \ ~ COMPLY WITH CITY OF APPROXIMATE ONLY. THE UTILITIES PRESENT MAY NOT EXIST Gad ~~ t g6 DUBUQUE STANDARD SPECS, AS SHOWN. ADOIiIONAL FACILITIES OTHER THAN THOSE SHOWN MAY BE PRESENT. IT SHALL BE THE RESPONSIBILITY OF t 3 ANYONE USING THIS DOCUMENT TO ASCERTAIN THE EXACT aP n~~ \ RECONSTRUCT SANITARY SEWER TO LOCATION, SIZE, TYPE, MATERIAL, AND ELEVATION OF ALL c a PAVEMENT MARKING AND CJ ~~ 7" p p~VEMENT ORIGINAL ALIGNMENT AND GRADE, SIZE UT11mES THAT MAY BE PRESENT. w a JOINTING SHALL COMPLY d~ VMTH CITY OF DUBUQUE ~ MATCH TOP OF v~ t~ .yy OVER d' B SE AND MATERIAL TO MATCH EXISTING 7 STANDARD SPECS. GJ o EX WALK VAiH ~ G' COURS ~ ~ ° ~ ADJUST MANHOLE CASTING v ~ CJ IXPANSONROJOINT ~~tioay t a GJ ' ,~ R ~ 0 NEW PAVEMENT GRADE L i t ~ `" o RECONSTRUCT LIMESTONE RETAINING \I d` ~ T/END 720.95 ~, t P 9o s~"\I F~ WALL SEE SHEETS 52.1 TO S2.10 L v v 'o 9 ~I ~~ HORIZONTAL SCALE IN FEET STRIPE CROSS WALK PER D 20 40 CITY OF DUBUQUE STANDARDS 1 DRAWING MAY HAVE BEEN REDU JOINTING/PAVEMENT MARKING PLAN IF SLIP FORMS\1' VARIES MACHINE USED PLACE 3' OF STONE O.B3' + INTEGRAL CURB AND BEHIND CURB GUTTER TO MATCH 0.25' PAVEMENT THICKNESS n~ m / ~ d ~ ~ ~ ;~. i~ L '~~. L STANDARD CURB Cl.l 11:17 3ClLE:N.T.9. 2Z:94 SCALE: N.T.9. UNLESS NOT ED ®B° i' VARIES p,83~ « INTEGRAL CURB AND GUTTER TO MATCH ,,,,~, ~ PAVEMENT THICKNESS I _' ~. I I ti w N L' ~ 0 i~ '7 - \Y ryh" v . r. `~ d r= 2 REJECT CURB CLL Ilst7 SCAIE:N.T.9. E7s9t 9CALS: N.T.9, Iyl~ PAVEMENT ~ NEW INTERGAL CURB c P AO BASE STONE -~;-~ i_ ~ SHAPE SUBGRADE~- ~ B" TALL CURB TO SLOPE TO ~ I DRAIN ' ~ c FILTER MATERIAL ~'.~ ~: T/GONG CURB 4" END 723,81 4" PERFORATED MATCH TOP OF DRAIN TILE tQ" EX WALK W/ T/C `~ N E%PANSION JOINT TUBING) CORRUGATED HISTORIC STREEIIJGHT W/ L E 3 SECTION PROVIDED LIGHPOLE NSTALL CLi PAVEMENT SUBDRAIN xoT Tc scALE BY CITY NEW INIERGAL CURB NEW 2.5' CkG y, 0 FULL DEPTH SAW-CUT ~ ~ D o ~ \ \ 1 ~~~ ff Pl ~. ~ .~ ~~~'S s 5 t~T51 2313 v ~ (\~\\\ M' ~~ ~, 11 ti 5 J/,\~ 1'~~ ~, 1 >2J ,~ - PCC PANNG~ " p 9y ~ t~ti 21 ~ ~ 3 `L = ~ ~i ~i. ~~ /~ 9 0 "1lP~ .~~~~, 0~'~~%'~G~s~~^~~~~NEWCkG INTECURB OV`E/ Q i CAE/ j/ ! // h D 2.5' &r SITE PLAN LIMESTONE TAINING WALL W/ TL-2 BA TER RAIL k ~7//pp WROUGHT IRO RAILJNG 729.55 CAST-IN-PLAC CONC STAIRS MATCH TOP OF EX WALK W/ T/C EXPANSION JOINT ADJUST MANHOLE CASTING TD NEW t O~TH6 PAVEMENT GRADE ~ PSPM,P~ E RECONSTRUCT TOP OF EX LIMESTONE z RETAINING WALL W/ 1L-2 BARRIER ~ a RAIL SEE DETAIL 4/S1.1 i~ v W d ~ ~ N ~ ~~ 7~' W ~Y S ~ T O a'i C'J Q 2° PVC CONDUIT [~ W/ (3) #10XHHW W P ELECTRIC CABLES . 0 / Il+' P'+ 0 / ~ a6 d' r~ :PER TO SHEET o0 c F ~ O ICON TO EX CE a m ,-I U' ,-I W H ] W " ip NE ' I TERGAL r a F ~ Z ~ ~ ~ ~ RB/GONG SIDEWALK v [ ~ Ga \y w ~r h ai A ~ 3„. ~~o ~~ 0 TED CONC SLAB ~ p.i o u ~" REMOVE EX Wo an ~A ASPHALT CURB w ~j O a ~i ~ t ~y$E W z ~ ¢rv:: ~" W W ~' PCC CURB Y ~ ~ ~ s ~ 'a ~ ~ z o„ REGRADE TO PROVIDE MIN ' f 4X SLOPE TOWARDS CURB, SAD, FERTILIZE AND ~ MULCH ALL DISTURBED ~,2~ AREAS. Project Mgr: BJM Project Number: 96146-94 © 111 L q S O 0 7 J V V D a~ ~ SUPPORTED CONC SLAB g / 5 p1 EXTEND CONC ABUTMENT N®RTI°I m c 1~ ~ TO BACK FACE OF q I fig' 'L LIMESTONE HORIZONTAL SCALE IN FEET b N WROUGHT IRON HOOP ~8~1" ~~~ 1 0 4 8 m c RAILING NOT SHOWN FOR / CLARITY ~/~ / / / / ` DRAWING MAY NAVE BEEN REDUCED / 1 / ~ / renvP TERRACE WALL NOTES• g ~5' 5 ~ / / ~ / 1 , 1, SALVAGED LIMESTONE SHALL BE USED WHERE 11„ t~ / ~ POSSIBLE. REFER TO SHEET G1.3. 2. STRUCTURAL CDNCREfE (SLAB & ABUTMENT) SHALL ~ / ~ ~+ 1 ` a INCLUDE THE COST OF STEEL REINFORCEMENT AND 3 / \ 1 '~• DOWELS INTO LIMESTONE. 91.D / ~ 3. 4" PERF CPE DRAINi1LE SHALL INCLUDE COST OF 4 5 • / 1 ` FILTER MATERIAL AND FITTINGS. W / ~ 5 FUTURE LANDSCAPING & T'O'W' 4 ` 4. TL-2 BARRIER RAIL CONNECTON HARDWARE SHALL 725.07 INCLUDE COST OF STAINLESS STEEL RODS, STEEL "o a TERRACING BY OTHERS 1 ~•3 ~ ~ h ` PLATES AND HARDWARE, AND 6"x6° LIMESTONE b w T.O.W. N BLOCKOUT W11H FILLER. v 2 1 3 724.68 '~ \ 51• ` m o PROVIDE REINF IN q / PAVEMENT WITHIN 5'-0" ~ X~G //~ ~ ~ ~ ~ ~ DF RETAINING WALL, TYP. ~~ ~ / ~ ~~ ~~ REFER TO DETAIL 3/57.1. T.O.W. 726.97 ~ ~ ~0 3 ~ 3iP) ~ ~ / REMOVE AND S~1 ~6 ~ ~'A / '~ z RECONSTRUCT OR ~ ~ REPLACE EX LIMESTONE ~~ ~ 0 ~ ~~~ ~ ~~ / RETAINING WALL TO ~OX~ , 1 \1 / ,~ Z EXTENTS SHOWN, / / 1 ~~ 1f 1 T.0.. ` ` ~ O' 1T / '~yT~ ,~. 'L 724.7 ~ V' ~• a REMOVE AND REPLACE ~~ `~ / ~, STEEL PIPE RAWNG ) g 05 C / •'~ 5 ~, z ~ TT ~~/ '~~ G 57.3 ~ T p 7 'YA // / $1 611 / O, F 0 9 / M1 `~° ,60.9 51 50 ~a.1 a 0 ~ A «a+ 1P'~0 5 / / REMOVE AND REPAIR, F z Q' y/ 9 / / SANDBLAST, PAINT & u ~ W ~/~~ / 1Y ~/ REINSTALL EX STEEL (3) Yz"mx4Yi' GALV. h fs+ A / XXX111 ~" ~ T.O.W. 2~8 / PIPE RAILING EXPANSION ' ~• / 725.15 ANCHORS - 3" 3` /~ 50 /,~9" :.n '" EDGE DISTANCE 4 0 / / / DPPI / 11. " 34" GALV. STEEL R - ~ • ~a~a ~/ ~ /s~ s1.o ryo- PAINTED ~ • . ~,, / a s1.z o A C ~ \\\1` 5p ~"EXP JOINT , 1 / REMOVE AND REPLACE ~ Z ' ' "r.o.w. (1 / ~ EX cDNC srAlRS + RAILING CONNECTION ~ 734.Da // i1z17 BCAICN.4S. ~' • / / / / 2 RECONSTRUCT OR 31.0 E?Jd4 SOIfE: N.TS• W ~ ' ~ / 51~ REPLACE EX LIME E Q+ ... Std / 50 RETAINING W TO W EXTENT OWN ~ ~" ' ' o'• ~ ~• EDGE OF PAVEMENT ~ a ' ~ yc ~ BELOW ~ ~ • ' • T.O.W. SEE PLAN a x ~ ~ ' ~ 5 50 731.06 4" P RF CPE ~ 2% MIN ,,~ ~FJ.I SEE PLAN a ~ ~ . .. ~ U ///~~~ 1Y4 m scH. 4D (IY~" D.D.) m ~ W z w ' St. TOW ~, / \ __ 1'_p^ GALV. STEEL PIPE RAILING U .w ~ ' 731.39 / 1 8' MAX SPACING -PAINTED q F ~ Z CD' . /50 Ya'~ RADIUS ~ ~ ~ F ~ ~ w ~r Ha+A FOUNDATION PLAN ' ~ o,~ CONNECT TD EX POST z d ~~0 1Y;'m SCH. 40 (1Ye" 0.0.) GALV. ~ ~ ~e BENEATH ARCH °~ U Q ~ S Q STEEL PIPE RAILING -PAINTED I o U1 ~ ~ o N I ~ 0'w d~ N P WV~ ~e )z" EXP AN JOINT ~ Fj 4,_0,. 1 _ ~i ~ °~ .. E't w 6Ns CONC CURB ~ 3'-6 3/4" 5 1/4" ~ ~ ~ a ~ ' ~ ~ CJ~P~ EDGE OF WALL BELOW ~ <.,c ,, .,~,,< ,. i~;. ~ ~ ~ ~ q~ 3 N¢N W 5~~ ~. EX LIMESTONE N i~/n//i~/i~/i~/n//i~Ti,/T//,//n//i~~a ~0~.; ~ LENGTH ~_°~' r~~~ d"o o, RETAINING WALL FUNRE LANDSCAPING ~ \ i ;~ \ G c7 m AND TERRACING BY h~ i i f I rcNN i-I ~ H Q mN ~ 1 Yr" EXP JOINT OTHERS \\i 'j : z .~ TOP STONE NOT 11~ SAND ~\\!~~~;_, <`'' < SHOWN FOR ~ \j~ ~ i s [_ `~ CLARITY ~ 'a ~ ~ SUBGRADE r ~ ,_. :} i~ l / / ./.• ~'4 ®12° O.C. / 1 LIMESTONE PAGING E.W. ~ <" BLOCKS ~a % ~'~'.~ SAND ~. _ a SLOPE Ya~IFT. % : ` • , THICKENFA EDGE CONC. TYPICAL EDGE OF CONC -Project Mgr: BdM PAVEMENT STAIR AND PLATFORM W/ #4 ®12" O.C. E.W. E% LANDING Project Number: 1 -D" D8148-04 EDGE OF ARCH BELOW (2) #4xCONT. REINF. ~NNtAG TOP AND BOT 9 TYP CONC STAIR 1 DETAIL °~' x TYP CONC STAIR 91.0 11x17 BGIL`N.4.& 91.0 11x17 ttCAI,6:N.T8. ~' 2'm84 BCIIE: N.S,9. 91.0 gyrg{ BDIIE:•N.TB. ESL BC11d: H.RB. L n 0 0 v 0 STEEL HOOP RAWNG NANRAL LEDGE REFER TO DETAIL 3/51.1 ROCK, LAID IN ~ ®~ '~ RUNNING BDND, MIN. 3' LONG I 3 I 5 1 CONC PAVEMENT T.O.W. SEE SITE PLAN SEE PLAN I TYPE M OR 5 MORTAR ` :~'.vyr;.:, ;:?:,.,~:;a,[. <';~tx+~st..°c; (BED JOINTS ONLY, LEAVE "" ;' HEAD JOINTS OPEN FOR DRAINAGE) fit.. MIN. INSIDE FACE ROCK Z o PROFILE ~ ~ w ~~ 8° ~~~ IN . ~1 ICKNESS~~":,'~:"~` ENGINEERING FABRIC I 1 CONTINUOUS BETNEEN w `,.c.7>";~.> 12 DRAINAGE BLANKET & ~ BACKFlLL a ~ - LIMIT OF EXCAVATION _ COMPLY W/ OSHA 29 CFR 1926.6, SUBPART P. ENGINEERED FILL V 1z F 1 ::: ~^ a :%>, `ia:p,;;y:;:r ~..:., ..,.. ~ '~~'':` DRAINAGE COURSE ' ~~ ~ '~+'~~ ~~1":~>:~+' " i. :4:~i F DRAINAGE BLANKET CONCRETE FOOTING . ~ MU #5 ®18" O.C. LONGIT, #5 ®10" O,C. REINF. TRANSVERSE REINF. 2D" "A" ¢" 1 SECTION 91.1 BLOCK llai7 SCALE: N.T.S. RETAINING WALL 22x34 SCALE: N.T.S. RAILING ELEVATION SL1 - Ilzl7 SCALE:3/B' = 1'-Q 22z94 SCA~LE:3/4° = 1'-0" III~II / REFERTTOHSHEET C1.1 (Al1 THREADIP RSSTONEL W/ NUT WELDED TO END LIMESTONE FACING BLOCK 1f #5 ®12"O.C. E.W. CENTERED IN SLAB - PROVIDE IN ALL PAVEMENT 7 DETAIL WITHIN 5'-0° OF WALL 51.1 11z17 SCALE: 3° = 1'-0' 22x34 SCALE: B" = 1'-0" ARCH ELEVATION SHOWN AT C.FNTFR DF ARCH 1/2" STEEL SOLID ROUND 1/2" STEEL SDLID RDUND - 1 1/2" STD STEEL CHANNEL 1~,0 SCH 40 STEEL PIPE POST WITH CAP 1 1/2" SCH 40 STEEL PIPE POST I I W/CAP iv '~ 6„ 1,_0„ 2 51 1 1 1/2" STD STEEL CHANNEL . . 3" CORE HDLE ANO a GROUTED - R 4x4xYq W/ NUT. 6x6 STONE FILLER, - ~~~' m ~ SCORE THREADS FOLLOWING ~'v ~,-~ ~< GROUT TO MATCH STONE. a INSTALLATION ! F CORE GRILL AROUND BOLT ~ °# `'%~ 'i.c,~ HEAD AS REQ'D, DO NOT ~:~'x"%~'~'~"L~'% (2) ~'('0 STAINLESS STEEL PLACE ADJACENT TO POST. '~ ~~~~~(>~ ALL-THREAD PER STONE ° '~'t'S„ "'``' LIMESTONE FACING BLOCK ~ - R 4x4xYq W/ NUT AT END TRANSITION AS REQb #5 ®12"O.C. E.W. CENTERED IN SLAB - PROVIDE IN ALL PAVEMENT 3 TL-2 BARRIER RAIL SECTION WITHIN 5'-0" OF WALL 9L1 I1a17 SCALE:3/B° = 1'-0° ~gj 22a34 SCALE: 3/4 = L'-0" TOP DF NEW WALL TOP OF EX WALL~"~ _„~ WALL TO BE REMOVED AND RFPI ACED REFER TO DETAIL 2/51.3 FDR WALL REMOVAL EXTENTS ~-WALL TO REMAIN. NCKPDINT AND/OR REPAIR ALL CRACKED MORTAR BEDS. SOUTH WALL ELEVATION ]1x17 SCALC: I:B 5tc54 aCJ1E: 1:4 -'1 L,. __ ~ - __~ ~~ ''- _,____ ~ L_ ___ CONC FOOTING--~ SEE DETAIL 6/51,1 FOR REINF AT FOOTING STEP, TYP BLOCK THICKNESS TABLE COURSE STONE WIDTH "A" 1 18 2 20 3 22 4 24 5 26 6 28 7 32 8 36 9 4D 10 44 11 48 12 52 11x17 $C4LC: 1.6 7tY9q 9C/Ia: Ito CONTINUOUS HORIZ WALL REINF "Z" BAR SAME SIZE & QUANTITY AS WALL REINF MIN CLASS B LAP SPLICE FOOLING REINF PER WALL SECTIONS ~'n,J ad. n a< a < EX LIMESTONE WALL ~ CLR ~, a ~ BEYOND ~ ~ '~ ' 3" - 4 ;. cLR 1L d 1 <, a', ~ ~ e~ ~ "Z" BAR SAME SIZE & n ; ~ ' a' ~ QUANTITY AS FOOTING ~ . " ~ M REINF --11,. MIN CLASS B LAP SPLICE -11- C NESS THI 6 FTG STEPS Sl.l 11x17 SCALE:3/B" = 1'-a' 22x94 SCALE:3/4° = 1'-d' c 0 w v P a Y 6 F a 7 a b ~ m o w l r] F W A a .. ~ ~ H U F va E ~~ W O Q h ~ W ~ w a ~ a F a d o x ~~ a, ,1 L7 u +'{ W Z 'FW7 F E ~ZQI vWaF~ a, P LW'~ ~I G ~Uo ~~ ~ ~ v ~~o aN W~; ~~~o ~o~ Qwm F ~,3 ~~~ a" z w s~3 W~„s~ ~~~ a~w U I~i~z owl Project Mgr: BIM Project Number: 66148-64 1.1 ~(741EK Q SZl~U NORTH WALL ELEVATION ARCH ~ z S12 ~ T.O.SLAB x SEE SITE PLAN b< s w m BASE MATERIAL TO,SLAB ^ 1 ~ SEE SIZE PLAN j ENGINEERED FILL I r 2%yMIN- - - - - - --~2~~MIN- - a ~1 I w s ~, ;;; I ~: W as > I j I ENGNEEREDC FILL 1'-D" EXISRNG STEEL TYP I TIE RODS. EXISTING LIMESTONE SANDBLAST AS ARCH TO REMAIN. I REO'D & PAINT. TUCKPOINT AND/OR T.O.F. ~ TYP (4) REPAIR ALL 711.17 "= r>;^: I LOCATIONS CRACKED MORTAR I _ BEDS -REFER TO DETAIL 3/Si.3 AND 4/51.3 I SECTION 31.2 11:17 9CAfE:1/9" = 1'-C' 29x94 SCALE: 1/4° = 1'-C' / ° ° ° 3 51.2 ° ° T.O.SLAB SEE SITE PLAN BASE MATERIAL ENGINEERED FlLL 4 ~ ' 0 D 0 I D 0 0 D D D D D D G 0 0 0 D 0 0 0 0 0 0 0 0 0 0 0 0 0 °~ ~ 0 0 0 0 0 0 0 0 0 ~ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Q O 0 EXISRNG 0 LIMESTONE ARCH NCKPOINT ~ AND/OR REPAIR ALL CRACKED O MORTAR BEDS 4 SECTION 51.2 11:17 9CALE:f/9' = 1'-V 22x9k 9CAiE: 1/C = 1'-0' COMPLY WITH OSHA 29 CFR 1926.6, 3tIRPART P 4" PERF. CPE DRAIN TILE - SEE PLAN WATERPROOF MEMBRANE .a a: < < "d ' y e q I a' < ~~ ~ J U 6x6 STONE FILLER GROUT TO MATCH STONE iV ~II II d II II II ~ c ~ ~ I . ~. ~ a -- II II v -d ~= n a:~ a I ,I , d I I .. ~; 'o °~® ® C 4 711.17 ~- 6" OVERHANG EQUAL 1'-4" EQUAL 5'-0" 2 SECTION OF TYP ABUTMENT 3L2 ux17 scALE:sIe' = r-C 22x34 9CAfE: s/4' = 1'-0' SLOPE BOTTOM OF SLAB AS REO'D EX LIMESTONE ARCH ~ SECTION 31.2 ~ I1z17 9CAL@9/S = 1'-C' 22x94 9C1LE:1 t/Z = 1'-tl' Cn a L"~ W A ~,' .. ~ u [-i U ~ ~ va m ~ W NQN rW ^V H (~ ~ W ~ ~ R'i ~ i-7 F '~ O a .1 C7 "u ~(xaz~ A~,~zo~ a ~rER'iG m 3h z ~iJo ~S ~ia~' ~~~ Waa ~~~o ~ N off ~<v C7~~ a~> 'ZWw ~~ W~~ Sad; ~ awl ~ m~ f..i CllZ ow>° Project Mgr: HJM Project Number: 001498-04 © I1 TRANS TOP & BOT #fi ®4" o I ~ O.C. VERT. FIN GRADE ,a EE SITE PLAN ° ' e '° '~° `v STEEL RAILING - CONC ~ ~~ ~ I SEE DETAIL PAVEMENT - :.~, ~, ° ~ ~ ~ 2/51.1 AND SEE SITE PLAN ~ ' ' M ~ 3/51.1 Y2° EXP JOINT ' '° ~ BASE MATERIAL T.D.SLAB ^ SEE STE PLAN 2x4 KEYWAY '~~ ENGINEERED ° . 0 0 ~ FILL a a ~ Q ~ SEE DETAIL ~ ~~ 3/51,7 FOR TOP 4° PERF CPE P-0" ~ ®4 b ;a '- ° '~a #8 ®6" O.C. STONE CONNECTION DRAIN TILE - SEE SITE PLAN O.C. VERT ~ ~ LONGIT DRAINAGE FlLL " tO° WATERPROOF #4 ®i6" O.C. ,a , ' ~ #5 ®12 4° PERF CPE MEMBRANE HORIZ EA FACE , O.C. VERT ~o I ~ SEE SITE PLAN (2) LIMESTONE ~ •A,~ 2., FACING BLOCKS ~ CLR TYP -COURSING TO DOWELS I L `, ~ MATCH SIDE WALLS ®12" O.C. ~ , „ ~ a ~ ° ~ #5 DOWELS I " M 1 _D : ®12 O.C. 70" LIMITS OF (5) #4xCONT #4 ®1B" O.C. EXCAVATON. ~, a'< TRANS T.O.F. v .. A 0 i N i m 0 a "o _~FlN GRADE ~ w a ~, d _ SEE SITE PLAN9~ b _ y a m a. ®~ 31.2 11:17 9CALE:N.7.9. 22x91 9CAIE; N.S.S. .._ ~ ~ ) Y ~`T y~~a ~ ~ , poe, P a- ~ ~~ - ~ ~,~ ~ e~ w~"-' .k > a ~k c+t ' ,ter.' ~ r . ~: N r w + ~ 15 ~ w w~,t<, ~ , ~ ~ act :6v T~f~ '4C~. ~ M~ ~ ,'~rF4~ ~A IF' ~ F ~'`'~I WALL TO BE REMOVED ~ -~~, '~" ,, ~~ ~ j L ~~_~ AND REPLACED ie__ _ ! 4' .# ' , ~. . . -. ~ - 1' ~ ~ ~ 3~~ y ., 9 ~ ~:r~ ~ >, WAIL TO REMAIN ~~ ~ o +, ~„r. -_~~ ~ ~~+r~A'`j'S" ~~~. M. , ~ ~~, 3 / ~ I t~ ~ +11 4 h~S LA' _'. is " f 9 ~ ~r`_ ~ ~_ ~ i ~' ~~ 1 ~ ~ ~~ r ~T ~ r. '_~ ~ ~ ~I ~ `' I ~ ~ 3 ti ., i~ ~ ~ r ,. ~ f h l ~ ~ - r'. !~ ~~ ,~1 mod' n ,~`~ ~ r ~r ~ y~' ~~ r , r ~; 1 ~ >" ~~ ~; 1, a F WALL TO BE REMOVED AND REPLACED WALL TO REMAIN i r ~ / ~l 1 T 1 ~$, ~ 3 '_ y r ~~~, a~ aq , t w~ n y -Y~~ ' , ~- k l..~ '~ 'y} ~' r ~.d -., g"~ "~ gi tN' r~ f[' { ~ ~ A~ v _. ' ~~~~ / 1 ~ ~~ ~ ~" ;¶ ~ ~ ~ ~a 3, , l , ~. ~~ ~ y: ' ~ w ~yf~(x 3 t} Ty~y' y a~ /l ~, - ~ . . ~ ~ r ~~ "~~~ /~ ~..r v" %. t` i ,- 4 `~ ~ a ~ ~~ ~ ~ € ' C ~fti .V ti 1 ~ ' ~I Win". J Y s ~ t r~~s ,~ a 1. ~~~ rg ~ ~~ '~tL ~ l 2 PHOTO 2 51.9 11x17 SCALE: N.T.S. 22x94 SCALE; N.T.S. . s .-~ ~ ~ ~ L -e` ~. M ~.~~~ .~ ~~' ,:,I v r ~ ~ ~.~ - ~` t ~' ~~ r~""~=' ~' i ,K ~. rl ~ ~ ~~ ~ ~~ _ 4 _ .~' i' ~ f s ~~-~ ~ ~ .h,'1 Pjb~ ~~ ~~ 8 ~ w~'- ~~ r, .S.~. N. G w' p sT ~ ~ 'y+a ~`~,a' ~~ ~ ~ j 4' j W t,°i`s. . S ~'f ~ t' ~ 1 3 i R ~ f ~,, -..i r ~~ „s i a j i ,~ ~ _ „~.. ~_ _._ _ ~~~~, ~ I ~ e P dr ~ ~ ~,~ ~ A ~~ it ~ ' ~~ ~ ~„''" ,~ ,~ r ~ ~ ~ ~ ~ 7UCKPOINT AND/ORS REPAIR ALL CRACKED MORTAR BEDS 9 PHOTO 3 51.9 11x17 SCALE: N.T.S. 22x34 SCALE:N.T,S. 4 PHOTO 4 51.3 ilxt7 SCALE: N.T.S. 22x34 SCALE: N.T.S. m a ', w 7 N A m a N i a 5 a 0 ~] F w Q N~i W E U E~ w [] G4' C7 Q z ~ ~ W ~' a F ~ ~ a~ H ~o .-I W Z ~ ~,~z~ ~Hxa y 3" ~//Uo ~s Wa~ ~~„ Wow ~Q~; F4 ~ ~~~ ENE ~ s„; W~,; s~~, ~~ amw xz~ H~~ Oyu Project Ngr; BJM Project Number: 08149-04 © 1. 1 PHOTO 1 51.9 11x17 SCALE: N.T.S. 22x94 SCALE: N.T.S. __.. _._ .......-..~ ._~ I _._..__..._ .._ `- v A a m A ° HORIZONTAL SCALE IN FEET ro N 0 5 10 d m ~ o DRAWING MAY HAVE BEEN REDUCED w U F10 ~ W Z~Z Z W 0~8~.00 f 1111 m i -~ ~ ~ ~ ..~ _~ _ __ ~ ~h __ i. ~__ __ ~ ~ I I I t- --- - 730 ~ 6 a 6 ~ I I ~ I.... I -i ~ ~ ~~ ~ ~ ~ --- ~~ L i G~EOFO ~ ~ ~ - I I~ ~_ ~ < w ~ ~ ' ~ a z _ _ - -HACKFI ~ I ~ _ ._ __ ~ - i I I --'I- i ~-- i i _. I I I I- i~ j i --'r T.0 ~ ~-~ I.--..~ ,_- _ i ~ o ~ V 1 i ~ ~ 1 i ~~ ~ i I I ~~ ~ 23.1 i I ~ I 720 ---I~-~~ i ~ ~_ - J~ ~ ~~.~--~~ i ~ i~ i FO:GEOFOAM ~ Wit- ~ 720 I ~ ~ ~ ~ f~~ ~ .~ v i v d u,l "4-~ ~ i , ~ err ) ~ ~ / I , 719.6 ~ ~ ~ ~ -- ~ ~ I _ _ ~ ~_ ~ ~ ~_ ~Ir_ i ~~~~7C1 01 ~d`,~}1~-~Fjy, ~ ' ~ A ~ ~I~- ~ OMP CTED~ DRAI(JA-EEA~CKFld ~ _._ i ~ 3H>lA'WxB t _ n~j ,nn L_I I i _ ICI- %~i~!~ ~~~v`~~~~n /~~ :_.~_/ I It ~~ I-T.OtXMJC ~ _ .._I-I! _ .~-~ + g ~ 1 ,~~ I ~~ ~ ~ COMpAC BASE COURSE ~ ~ ~ ~ ~~(~~~~ )(fY~ , ~k ~ ~ ',~ ~ 713.5 ~_ ~ ~ p ~ ~~ i ~~ ~ ~ -~~ i_ i~ \', ~ ~~~~CYJ )GJ~ _) )d a~ ry16'MAX 1~ ~ -~ REINFORCED C~iONC_T~ i E-~ i i 710 ' ~ ~ - ~- ~ I ~ ~ "~-r i~ O~~~`l ~ ,~'~ ,, ,/ 1 , ~ I 710 ~ ! ~ ~)C ~ ~ t3Hx4Wx / T ~~~Ur L Oj~~16AlAX : T:O.GE_ )~ -~ i ~ ~- v O ~I 7 1 _ __ i ~ 6=1 ~ 8! - I _. ~_ ?- ' ~ 3+Ix4'Wx /2 i f ~ II I ~ ~_ I I I ;,T~,r ~~~jG? J ~G~Ci(~0 AA, / ".. ~%/ ? ~T.O.CONC 7071 .. __ ~_I ~ F U -r -~ I ,~~ i ~ -~ T ~ 7F ~~ ~~ ~ _ W _ J~ e MAx ; ~ ~ I I v I I ~ I I ~ ~ ~ ~ _ ~ ~ ~~~ ~ ~ ~ _~ ~ ~ ~ ~ T I: T.o.co C ~ ~ i I ~6 r ~ li I _I _ ~~, I ~ - ~ -_.-_ I___ ~-_ ~ ~ '.y Y ~~ ~~~' 701.1 ~ ( -~i7oD ~ ~ i ~-~ ~ i f ! STONE FACING ~ I _ I ~ ~~ i 700- ~ i_- ~ J ~ r-_ .- , I I CONC BA KFlI1 t ~ ~ .I; ~ ~ ~ ~L ~ I I . i ii ~ i I i _ 7~ ~~ _- ~ ~ ~ ~ i I I_I ~I ~ I ~ ~ ~~~ -- -~! L~-_. _I ~ ~~_ _., ~_~ I ~ ~I _ ~ ~ .ai-_~~I C.4 I ~ ~_~ ~ I~~~I ~ I g i ~ ~ ~', I ~j ~ - j ~ yam( ~/,I ~ j-i I'.O69 NC I ~ _ ~ _L..~L I ... 1__ Z ~ ~ ' ~ ' ~~ I f ~ fi I ~I _~_ I I~_~ I '__ i _I~ ~ ~ ~, ~ ~ I~-- j ~-~ 'I ~ I l i 1 I I I T '` ~ ~ I ~ I, I I ~~ w~ -.. - _ ~ i _.-_I I ~ '~ ~ - .. _ ~_-_ ~ _ I ~ ~ !. ~ ~ 1_,_.. T _ ~I _1 ~ ~_._ __-~ 690 P' 69D - -... I ._~ ~-- ~ --~- i ~ _ -= - ~ W -50 -40 -30 -20 -10 D 10 20 30 40 50 p.;, ~ ~ .] H ~ O a ..~ U' u ~ W Z QF~~~ ~~jxc TYPICAL SECTION ~ ~ STA: 0+80.00 a~ H a a SEE SHEET 52.1 FOR LOCATION r, `~ 3 h ~vF ~S~ ~a, ~ ~ vi .~.,Oa ~~~;' 6 w a„:. zw~ s~3 h, W~~ a~9 ~~ dyw u Project Mgr: 9dM Project Number: 06146-04 EXTEND RISERS TO TDP OF GRANULAR FILL 71 Y I ~ #5 x 5 -6° GEOFCAM CONCRETE ® 24° OC - RDUGHE~ - - SURFACE ' a rc 0 v CDMPACTED GEOFOAM CONCRETE '' N BASE. CDURSE BACKFlLL " o 5 x 4,_6„ I ® 24" OC n ROUGHEN SURFACE ~ ~ x 3'-4" GEOFOAM ~ DOWELS ® n a ~ CONCRETE ~ 24" OC 10" J ~ . ~~ I ~ 7G~ `,~ ~ CONCRETE ', 4" PERF CPE ~ ®24" OC DRAINTILE HOR1Z, TYP ~ ' W/ FILTER MATERIAL #5 x 4'-6" ® 24" OC N-SITE LEDGE '-` ROCK CONNECT ALL DRAINIILE TO RISERS 4° PERF CPE DRAINIILE W/ FILTER MATERIAL LEGEND CONCRETE BACKFlLL f-1 GEOFOAM L=J BACKFlLL COMPACTED BASE COURSE BACKFlLL SALVAGED ST~JE FACE 1~ CONCRETE n v z .f SEE ~ ELEV V 1,_C,r , L .-``7 111 CONCRETE WWW f a EX STONE- ~ jE5 ®24" OC EV! -J o I Q5 DOWELS ®24° --'~~ r7 OC DRILL & EPOXY INTO EX STONE, TYP ' 4" PERF CPE -~ _ ,. DRAIN TILE, TYP 6" GRANULAR ENVELOPE OF FILTER MATERIAL, TYP NOTE: EXTEND DRAINIILE TYPICAL DETAIL TO FACE OF WALL AT 1 ELEV 693.4 TO 713.5 win°enR cuA oRMINATE sz.01 am's~4's a'sie : i~-~v jr'S ®12" OC EW. TERM FACE OF STONE W/ STD HOOK SALVAGED LIMESTONE FACING, TYP 4" DRAINTILE RISER BAR GUARD ON 4° DRAINIILE LEVELING BED CONC ABUTMENT SEE PLAN ON SHEET 51.0 1 /2" STEEL SOLID ROUND--~ 1 1/2" SCH 40 STEEL PIPE POST w/cAP 1 1/2" STD STEEL CHANNEL 3" CORE HOLE AND GROUTED 6x6 STONE FLLER. GROUT TO MATCH STONE. CORE DRILL AROUND BOLT HEAD AS REO'D. DO NOT ~ PLACE ADJACENT TO POST, iv i'r I Z ~ ~~ s it ~ w w Ili 3° SLOPE ~ > ;III n m ~ ° iI 6,i E TRANSITION AS ~ REOb ~ DOWELS ®24" O.C. STRUCTURAL CONCRETE (BARRIER p5 ®18° O.C. E.W. ~'"'- STEP BOTTOM Of CONC AS -- NECESSARY -SEE DETAIL 6/51.1 FOR REINF ®STEPS ii I ~ U TL-2 BARRIER RAIL s SECTION 92.01 11:17 6D1IB:9/B' - !'-0" east ecu>s:s/4° - r-v dE R 4x4xYi W/ NUT. SCORE THREADS FOLLOWING INSTALLATION ALL~IHREADIPER STONEL 0 LIMESTONE FACING BLOCK N I I~ DOVrELS x 1'-6" m a ~R 4x4xY4 W/ NUT AT END ~5 ~ 12" O.C. E.W. A L9 m d Q [4 m ~ o a ~ ~ co m a o a; w x m a V w vF n q W y O A z ~ ~ W ~ P. H ~ L/j .a dl H ~O a °-1 CO ~ W Z ~ a ~~ZCB i ~rFa,G ~' 3 z °a'U~ ~s~ ~Qi .t a~h o a~ W~ ~~`o O~ ~ ~~~ ~~> zWW s" W~~ 5~• ~ _~~ F-i a u r+(Az Q~0> Project Mgr: BJM Project Number: 06148-04 © 1 11TH STREET WALL NOTES: 1. SALVAGED LIMESTONE SHALL BE USED WHERE POSSIBLE. REFER TO SHEET G1.3. 2. CONTRACTOR SHALL PROVIDE ADEQUATE MEANS TO PREVENT CONCRETE FROM FLOWING THROUGH WALL JOINTS. ENG FABRIC ON THE BACK FACE OF THE WALL IS AN ACCEPTABLE METHOD. 3. CONCRETE BACKFlLL SHALL INCLUDE THE COST OF STEEL REINFORCEMENT AND AND DOWELS INTO EX STONE. 4. STRUCTURAL CONCRETE (BARRIER RAIL) SHALL INCLUDE THE COST OF STEEL REINFORCEMENT AND DOWELS INTO LIMESTONE. 5. 4° PERF CPE DRAINTILE SHALL INCLUDE COST OF FILTER MATERIAL AND FITTINGS. 6. TL-2 BARRIER RAIL CONNECTION HARDWARE SHALL INCLUDE COST OF STAINLESS STEEL RODS, STEEL PLATES AND HARDWARE, ANO 6°x6" LIMESTONE BLOCKOUT WTH FILLER. z SECTION 92.D! 11:L7 BDIIB:9/6 . 1'-D' / ~ ~ 1 I / ! / _. -..~ ~ ._. __. ~ __ - - _ . - _-_ .- - - / \ _ - ~ qh~~ _ ~` -- -'- - - --_. -- ---._720 -- ~ ~ - -- - -- _ ,i~~__ __715-__ ~,i~\ ~, ~ j ~~ _J-_---775--._-----'~~_- '_715 -- ~._------ ,, ,~. ~ ~, t ~ _ _ - ~ /, / 71o- _ ~~~. _ - ~,7/ ~ ~ ,~~~ _ _ _ _--_-_-710--__=_-- -~-_-_ ~ - "I I ~ ~~ _ ~~ I ~ n h ~~ I~ ~ 11 ~ o ~ ~ ~ ~ ~ ;~ ~ _ ~~ _ " - ,~ Q _' I n N O O ~~ O O\ e~ ~- -~ O ~ I ~ ~~ r~ I ~ I I I ~ r 1 ~ I ' ~ ~ ~ o° ~ ~ / PROPOSED GUTTER LINE ~ , t ,~ I ~ ~ i I ~ '~ I i n ~ / 701.67 707 64, ~~?051 703.58 703.51 ~ _~ -- ----- ~ r I I ~ / 7 / ~ 71:AZ--------------------- -- 1 --- --- ---X95-"-. ., - __--- ~ I ~ I~ 1 ~ i ~ ~, _ _ .~ _ - ~,:59~ ~ ~ 00 0~` _ - ~ 7 1 I ~ )~ ~~ ~ ~ r ~ ~ ~~- ~ 7 ~ ~~`~~ ~~~~ ~%~ i ~ 00 ~ \~ 0145 ~ 701.4201.3 70137- n~ 3.68 nob no~~ ~ .~~-~ / I ~ ~ ~ ~ - l I ~ ~ r r- j 7 ~ 701.4J 3 ~ - ~~ ~ 703 fi 703.7D 703.49 ~ ~ ~ ~~ r ~ o ~ ~ ~~.~. 701,37 ~~~ 701.28 _ - 701.23 ;, ~ o r ~ ~ . r !~ ~ l ~ ~ ~ 7 r ~ _ ~ ~ ~ .\ - - ~ o n~ _703.56 b n ~, __ "' ' V. ' ~ r' ~ 1 ~ ,-P''-~ ;- - '\ ~ ,~ ~ ~ o ;~~ 701.33 - ~ n 69 .29 700.15 `, _ , ~% n I , ~ ~ ( ~• ~ ~ ~ ~_ , ~ ~. ~, ~ ~A „ram ~ 701.28 00-~ ~I1 ~-/ I ~ (~I i I a '~.i ~., m ~ q~N n~ n°m~o°' 701T2°' no r 1 I i -~, ~ h;^ ~ ~. 897 44 0' m' ~ o / ~ -' /_~--"'~_7,.--T~l ~~,1 j ~ i ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 89496 ~ ~,~ \ ~ ~u ~ ~ ~ ~I ~~ n• 698.33,q• 0,`0~ o~. ~ n - ._ {{ 89419 ~ ~ ~ ~ n I ~ I I ~ ~ I ~ ( ~ ~ r ~ 894.96 - v ~ n°~ ' (~ g _ ~' - ~ ~ ~ j rn ~ o ~ o r 694.49 °~ o I: ~ ~ 694.47 ~ ro o" 0 1 ~I ~ I 4~ P~ SER ~ o ~ ~ ~ 89`~ (;, ~ 1.19 69,61 ~ n , n E) ~ ~ ~ ~ (" 4' PERF CPE ~ ~ ' ~~ 697.5 ~ ~ o° %~~ ~ RE I ~ SSE DE'T L A/S2.U1 ~ 1 ~~. 4.D8 h 6 8.01 ~ ~ , DRAIN TILE ro 701.27 °~ ~, n , J I f ~ ~ ~ ~ ` 1 v~ ~ i 897.56 ~ ~, ~ _ _ ,-0, n ro 7D,.29 ~ 698.34 ~o ' LEGEND - ~ ~ ~' ~ i I ~~ ~, -- - ~ - ~. ~,~ ~J ~ ~~~ ~~~1 ~ oy' fT ~ ~~o~ ~m~ ~ i _ o/r ~ n q, o i , 1 ~, ` ~~ ~ CONC BACKFlLL y~:~~,~> u EX LIMESTONE CPE OUTLET W/ o I ~~I ~ 11 ~ ~ ~ IINESTONE FACING RETAINI ~A OVE) BAR GUARD ~~ ~ ~ ~ ~ i, EX CONC PAD ~~~ ii~~- ~~is~i i INFILL 0! FACE Of EX LEDGE ~I ROCK AND GROUT SOLID STAGE 1 PLAN 693,4 -TOP 691.2 - BTM 719.51 718.61 W ~z ~O d z '~ ~ W ~wz Nay O ~+' U' ~a F ~ a ~ a E a x ~o F ~ r-I W H ~ ~z~ ~EZA ~' 3 °~UH ~s ~~~ a w '~ ~ ~~~ ]~ ~~a ~~ ~ as W~~ g.~h ~~~ a~~ ~rnz oN°> RETAINING WALL ELEVATION Project Ner: BIN Project NumEer: 08116-04 .1 HORQONTAL SCALE IN FEET 0 5 10 DRAWING NAY HAVE BEEN REDUCED )NTAL SCALE IN FEET 5 10 SAY HAVE BEEN REDUCED ,- ; ,--~ . . / ~' ' . ~. - _ ~ ~~ / ~ ~ ~ - - - - - - - - -- - -_- - 720 _ ... - _ _- _ - - _ _ ._ / i ~ / -_. - - - - ------715----~~_,._----- ~~', ' ~. 715 ~ _ `~ /~ v /~ ~ _ 111 / - ~~~ _ -- -_-_ - _~ ---710-- ~ _- _ -~/ n"may-_- ~ ~~- _ ~ _ _m--p ~ ~ ~ ~% 1 ~ ~ ~ ~ ~ ~ I ti ~ ~ ~' ~ A ~ . ~ A i , ~~l~o; 1, -. ~ -,, ~~I _ __ ~ ~ ~ I I ~ ~ ~ ~ ~ ~ ~ ~ ~o ~ 1 ~ ~ PROPOSED GUTTER LINE ~ ~ ~ ~ ~ ~~ i ~I ~"~ o _ ~ ~ ~ i n° A 701.67 701.94. 7' 1 703.68 703.57 / ~ ~ ~ ~ '~ i I 1 ___ 05.E I ~ ~ , ~' ~ ~ - - ---- ---- ---~ ~ ---~ ~ ~ ~ ~~ 1~ ~~ ~ ~ t I~ i ~~iil~ ~ ~ ~~ 707-01:59 701.37 _~I~. ~~ ~~.r'_~^ A°" _.1~-~-=- ~ ~~ j~~,~~~ ~~ ~ ~ ~ i ~ ~ , :~ . _ /~ ~~~ ~ ~,~ 701.46 V - 7D3,88 A 703.68 n ~ - -: ~ ~- ~ I I ~ ~ ~~0o 701.3 i' ~ ~ 1 ~ ~ r f ~ ~ / ~ ~ ~ i ~ I ~ - ' ~~~ .i do~j `~p0 '~A 701.43 701.42 ~~ ~ ~ 703JD 703.49 A /~ h ~ A\ ~ ~ t ~ I I I ~ ~ / ~ / ~A ~~ 701.37 '~~ 7D1.28 = - - 701.23 a~ ': ~' ~ ~ 6 I / ,~ / ~ ~ ~ l ~ ~ n I l ~ ~ 1 ~ ~ ~ //'' ~A ~ ~- ~ ° A 700.15 7D3.56 "~ 8 A _ ~ - i ~ ~ ~ ~ ~ ~ ~~ ~ i ~ vim-- ~~ ~ ~ i' h % ~~ F b.. 701.33 ' ~ 7D1.28 69 29 ~ `-` '- - -' / A I ~ ~ ~i ~ i _ - ~ ~. 0 ~ ~ J ~ ~~ ~ ~ ~"T ~ ~~ ~~~. A> i/ ~ °~ 5O~' a° ~~`~~ _ .:- '- - _ ~~ 1 ~a. ^'~ o o m 7 1.13 0 ~ ~ ~ LI-~ =- _ / ~ ~ { ~ I f I ~ ~ J ~ ~ .~- 69744 ~ ~ M ~~ n n m ~ 0 701.12 ~ ~~ ~ ~ ~ 1 ! ~ ~ ~ I I ~ 894.98 ~ ~ :, ~ (A' A• 698.33 ~~' o°., °~ A ° - - ~ ~ ~ I ~ ~ ~ ~ r 1 ~ f I ~ - 69419 ~ >'a:y ~ ~ ^r ~~ ~ ~i "~ °j o `~` A~ '- "7 ~ I~ i ~ ~ ~~ 1 ,., ~.;8`~C~u4 4` PERF CPE o ~ ~_ ~: a o _.. ~ I I ~ ~ ~ 694_46 - DRAIN TILE a ~ n I ~ ~ ( -, ~ m o ~ ~ ~ i ~ 1 ; 694.49 .,, ,94:~7t~r,~F sy m°j r , , -- - I - " o• ~ EX LIMESTONE I ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ o `.\ ~ t .,- °` " ~i ,~^±'l. <~;~~,~~s~~}~ ~ ~ ~_ .~ 697.5 697.6 ~ ~I,i ~ A ~/ n~ %Slso ~ RETA(NINO WALL r I ~ '' J I I ~ I I ~ ~ ~ ~ t \ ~ a~ t'~ .:t _ ~" ~ 701.27 687.68 698.01 i ; ~ I ~ , ~' ~ ~~ , ~ ~ _ . :"~, ~ m 7o1,2B ~ ss6.a4 U1 ~ ~EGE~D -- ' / ~ ' ~ I "~- - v I- ~ i r o ~~„~. tvr . k - ~ a ~ ~ ~, ~° L .~ I \ ~ ~, 'I I CbNC BACKFlLL ~yt,~~+'':*'~~ O EX LIMESTONE - - - - - _~ /a A s 1 ~ ® ~~ RETAINING WALL ~ "~' m ~ I ~ iI LIMESTONE FACING (AAOVE) I ~ I ~ I EX CONC PAD EX STONE 1 I I GEOFOAM BACKFlLL ~~q I~~~i~~~~ ~%irI FACING ~ ~ ~ ~ a a n n HORIZONTAL SCALE IN FEET zsea O 5 10 4' CPE RISER STAGE 2 PLAN COMPACTED 0 0 0 0 _: - ~E DETAIL 1/52.01 694.8 -TOP BASE COURSE BACKFlLL DRAH1NG MAY HAYc BEEN REDUCED 693.4 - BTM `~~ ~°°~"`°°` nL' 1H11y11V1x rrLiLL LiLP~YH11U1V 719.5f ~18.6t INTAL SCALE IN FEET 5 10 IAY HA1c BEEN REDUCED A 0 I 0 N I O w a a W 0 ra P. ~ O F ~~ „za Fzw ~wz ~x~ W O ~+ C7 A E ~ W ~ W P. ~ ~ E a C ~ E" ~ o a .-{ U' .m ~ Wz~ a HdH~ w P F PW'i A `~ 3 h ~U~ ~s V~pi~ ua„ ~ o tae W~; ~~~o ~Da °~m ~e3 C7~~ ate; ZWW s~3 W~,; s~ ~~ a~~ Project Mgr: BIM U8146-04 1 i - i i --\ ~'~~ ,~ ~ _ -. _ ~. ~ "_ ~ "--_----------'~---.--720-- - - -- -- - .~ ---_ --_'--_~_ - ~~, ~~ry~~ .. _ -_ -- -- - _- - ~ ,~ -' ---- _ ._ -`~ -- _715-•-._~ ~~~'`, i ~ / ~ •~ i i - __ ___. -- / - -- -- --"'~_ --715 ~_-~_--- --- ~.~ _, / ~ / ~ ~ / '_ - "J _715- ~ _ - - - - -_ . - _ ._.~- -- _. ~ - - - - - - .. ~, %,'`, ^ ,~• r ~, ~ ~ ~ l _ ,.. ~/~ /~ ~ ~ ~% ~ __-___._. --. ~~~~-.'~-----710__ _~ _ ~~ ~---^-'~~ n° ~__ ~~ ~~ ~ ~V ~ ~~ ~. ~ rr a I [ / ~ ~ / ._ _710- --- -- -. _~ rv ~ ~/ ~ / ~ ~ ~. ~ ~ ~ ~ -- ~ n n° 4~ ~. A~ r 1 1 I ~ j ~ I~O i O ~ ~ - _ PROPOSED GUTTER LJN~~ ~~ ~ ~ ~~ ~ ~ ~~ ~ ~ ~ ~ 1 ~ r i soh ~ ~ o~• _~~~ ~ _ -7G5~ _ _ ~-_ ~ ~~ ~, ~ ~ ' ; % J h' n ~ ~ 1 1 ~ ~ ~ ~O`01 n° ~ --- 703_51 ~~~~ _ 78~.r~` _ --~-' ~ / I ~ ~ I ~ 7D ~-------------- ~ ~ ~ ~ ~ ~I ~ ~ ~/ ~ ~~~ .~= _- .~~ 701.57 70 61 7D~1:39 4"PERFCPE ------701.370$~I~ 703.56 ~~_ ~ ~~~ _=~ r ~ / ! p ~ l I II / I;~~I ~ ~ f ~ ~~~~- ~ ,~ ~ DRAIN 11LE M' / 1 i ~ ll \\ ~ ~~ ~ q. 701.45 ~• r`~ 703,86 n~ o ~~-~ ~ I 1 ,~ '1 701 J ~. 7DJ.66 n ~;~ I / I ~ ~ ~ ~ ~ ~ ~ ~- ~ /~ > ~' V 701.43 ~ A _ 703.70 703.49 /b' h ,A I 7 i ~ ~ I /' ~,. .,:. .3 ,~ ~__,_ 1,2 703.56 ~ ~ o"• n° ~ 1 ~ ~ I 7 ~ ~~ ~~\. 01.37 701.42 /io• 701.28 -, 70 ~ ~ I ~ ~ ~ 1 ~ '~ ~ ~ / ~~~ ~ ~:a~~~ 'V ~' ~ ~ to M~ \ ,/ n 700,15 =- - rv 1 j ~ ~ ~/ ~ l ~~ ~ ~_•~ ~ i .,~ - ~ ~~ •~ i. ,~ r • a~a'.. ". ~~\. 701.33 701.28 69 29 p'~ - " ° ~I ~ ~ i I ~ ~ 0 _; ~ _ _ L I /~ I 1 ~~,~ ~ ~ ~i ~ ! ~ 4t x ~ ~a ~ ik~`q+ ~ ~ OVA ,_ _ ..- _ _~~ ~ N~ ~ n~~ ~ o~ 701.171.13 no' ~ ~ LI ~~ -=-7 % I ~ ~ ~ i I I I ~ , ~.,a''r.r.. ~ ~: s t u ^.~„i`,:• ~ ~ ~~. 69744 ;. ~' ro o. n~ o. ., ~ ~ :::.. i I ~ ~ ' ..._....: ~'1'`~sp .+~;;°-..r,', ` Aq!~~~;i;yF,ry 33q~ ~~• _ - -~nFx :.6'a . \ 698• ~ ~ ~ o ~ I~ .'M~"r cyan ;1~':?:~t s•~ d'i~~Y;~~t• ':';~ltij`;': ~? ~`R::~t'~, oP `~nr n~ i I I ~ t~ ~ ~~ ' I r Kuly I~:W'/.^ X~ x•5'-0> •~~~f•~'fi.^ ': ~ ~ k + '-; b O I I I I ~ ~ 1 ': 6 ~p y.BJJO.•:; t'~`~i .`~:. ^~:r•y~~:.,~ n _ ~' ~ i `` ' ~ i ~ '~~~'~,:;,~~`'+ r } &9>i5'~ 1 ~~ ~ ~ =- - I ~°' r~ a• ~0 1 i EX LIMESTONE I I ~ ~ i ~ I° u~,b0~r 3 ~ ` L. .19 697.61 I~ I n n I RETAINING WALL J ~ I ~ n° ~ ~' ~ w...... I ° ~ %5160 t, .,. { I / I I I I ~ I ~ 1 \ s~ t . t•~•4 i+:•;. W 701.27 697.50 696.01 i n° l ~ ; I ~ ` ~ '~~'~'' '~ ~• _ ~ - _ - - m~'• m 701.29 ~ 697.66 i ss6.J4 ( ~ I' LEGEND _ ' l ~ l M~ i 0 ~ m L ~ 4~ 6PE RISER ~ `~ ~ ay~t~,~. +'}`~f:rr• ~,y`: °r J~ m ~ I SEE DETAIUI/52.01 ' I I ~ CONC OACKFlLL '+^„•`vx,'i';f'c•?}' I ~ = Jrv I I n e o41 \ :YF T^~; a1. ~ F.W f, .p __ ~~ l °," A^ ~ 1 1 ~ EA LIMESTDNE `_- - ~~`O ~ 0 ~°j j o CPE~IOUTLET W/. RETAINING wAU `° ~ OAR GUARD ~ ~ CONC LEVELING ~ LIMESTONE FACING (ABDVE) I 1 ~ ~ PAD I 1 _~ ~ ~ '' I INFILL ®FACE OF EX LEDGE STAGE 3 PLAN RocK AND cRDUT soup 697.8 -TOP 694.8 - BTM 719.51 '18.6f A b p w z a G11 E ~~ ~za ~~w w D'i C, 0 p•' C7 A E ~ W a ~ ~ F a ¢' ",~ ~ o '-I W Z ] ~,~zc~ ~Fxa 2 3~.. ~U° ~s~ ~a3 ~~~ o aN W~ ~~~ 70~-• pw ~q~FF~~ F w V~°~ ¢ ~ zW w~~ ~~e ~ a~w z~~ rtiC7~ ow> ~~ --/~- RETAINING WALL ELEVATION Project ESgr: BSM Project Number: 08146-04 HORIZONTAL SCALE IN FEET 0 5 10 DRANING MAY HAVE BEEN REDUCED 41TAL SCALE IN FEET 5 10 AY HAVE BEEN REDUCED : ~ ~ ~. ~. ~ ~ - _ _ _ ~ _ ,. _ _ __ _ _ ,% /~ ~^ryp `/ `r _ __ ~ ~` _ _ - _. _ ... _ -.--715-----~ ~.._. ----- ~`' ~/-^ .- `_'715-^ _ _ -= ~~ ~~\. i - ~ ~ / ~ ~ ~ ~ / -/ _ - -715- -._. - _ _ _- ~ _ ~ -- - . `.' h, •. f '// ~/ ~ _ _ - _-- - -_- -- -- -- - - ~-' ~ M• q ~~/f /,/ ~ `~ //~ -__- - - -=- -=---710-- _ -.- -- / ~' ~ -- 1~~ , ~Ii ~ /~ _- ~ ---- _--~_ -- - -~ ._--- ~_L ~ ~ ~,'~, ~ i %„/ __'- --710-- -- "_-_- m ~` a~ ~-Xp ~, 1 ~ ~ ~~/~ ,,° ~_ , ~ - i ,~~ --~, I ~ - I ~ ~ .~ ~ ~/1~ ~ _ ~~ II, , ~ p' f / o ~ ~ 1 ~ ~ n ~ p ~~ ~ ~ ~ ~ PRDP0.5ED GUTTER LINE ~ ~ ~ ~ ~ i ~ ~ ~~ ~~ ~ f I i I ~ ! ~ I~f ~ p~. ~~---'D5~ ___ _--,_ _ ~ ~~~., III , I ~~ ~ 1.67 7 703 58 - ~ ~__ r 1 ,i r ~ ~ ~~~! ,~ _--_ DRAIN TILE ~ 70 ~ 701.84. 7:59, ~ - -~-~--DS ~...~ - 70351 - - q ~~ I ~ 0 1 ; I ~ - ) ~ T ~ ~ ~ ~ ... ~_ ~ ~ 701.37,- M ~ ~p 1~- _ ,~ ~~I,~ ~~ ~ ~ /~ ~ 1 ~~ ~ 01 5 no M' ~ - Ir' i ~ ~ 1 ~ ~; ,~T p 7 ~. 01.33 _ - ~, 703.68 7D3.68 ~o ~~'~-•~ ~ y 1 4 ~ ~ / ~~ _ 703.70 703.4 M^ h `, 1 j ~ ~ T ~: ~~ 701.43 7 _ / A ~_ ~ 1~~~~( / ., ~ / ._ ° , ~ ; ; t ~~ r~~ s i h s ~ .,~ 01.37 701.42 /~ ~ 701.28 '- - , 70123 0' ~ ~ ~ i / % l 1 ^ l i ~ ~~ ~ o,. e., r,. b.r .v - ~° n 700.15 703.56 • ~o n _ 1 ~ ~ T / ~_ i ~ ~~ •~' ~5~.. v .,, n rk+ ~ ?.. ! ~ .. 701.33 ' ~ 7D128 69 29 °p~ - - ~ ~ I ~ / ~~ K H ti W':: .. '~ v ~'1~~~•.~ ~ / '~ / j~ Y~. ,L .~ .~~!`~:xA `~ f. tines>~\a:i ~:4'y'.`.,4:~.~':•:'..~1..'~ k - L ~_ I .=7 i ~ f ~ ~ i + sr f>f _ .7't,k. .}•~x",C;.r i .'f' 7p ~ ~'\ - / I I ~ ~ I ~ ' ° ~ ~ ', V • ~~ •'3'`•:''.+y •;r14s,`t ~i;^;:'~;i:'e~ }. y I, p `R` ~ _ I n i .. ? '~M~~ b 'L.:'<J 'vl;;';v ~f.i F' q ~ l I l~ it I ~~ t>,~.".;cie'.'1k ~ x.,.,*~..fs:;: <,,:,`-':.~~~~;i~y::..., _i% ~ o ~ p I ~ ~.;i. , i~'vmi~.. ~'= t~~r:~ ~m• fi~.~~ - p m ~0 0 1 EX LIMESTONE ~ ~ ~ ~ ~ ~ ~ ~ ,~"r~^.F'%~~',k' .%~-C'~~ r~`: :9;i ~' ~~~, X1.1 69.61 it ii ° ~ 1CSI50 I j ~ I ~ ~ %~~ ~ w h ~ ~ 70127 ~ 697.5 68.01 0 ~ ~ RETAINING WALL ~ ~ _ ~ ~ ~ ~ ~ I I ~ ~ i r 1„ 1 u' ~ _ p ~ G97.5G ~ ~: i C = ~. ~ ~~ q' ~ 7m.zs ' sssa4 ~~, I ~ LEGEND ~. ~ ~ J'~`i x'"{~ 1:p, ~ 0~ ~ pp_ ~ o~ ~~~a rF ~'~'Mt s' jr•' ~~ ~~ m ~ i CD~JC BACKFlLL ,..~ `'af.<<.•m".: : ~ ~ ~ , ~, ~ ~ .~ ~,.s .>>~.,..•.' Y ~ ice; ~ ~ I ' EX LIMESTONE =-~~-- =- ~ ---"`~-~0~ ~~~ ~ ~°~ c I r ~ ~ I I IMESTONE FACING RETAINING WALL m (ABOVE) - - - - - I~ °~ I 4" CPE RISER ' ~1 I SEE DETAILII/5201 ~, I ~ I h~~i ~i N, J~i~ i~/i/ HORIZONTAL SCALE IN FEET EX BTDNE 1 I GEOFOAM BACKFILL ~,//f~f~~/~/~~y ~,f/ D 5 10 FACING >~ STAGE 4 PLAN ~ 4" CPE RISER 701.1 -TOP BASEACOURSE 0 0 0 0 O DRANING MAY HAVE BEEN REDUCED SEE DETAIL i/S2.D1 697.8 - BTM BACKFlLL `~~ .~~,. "V ~~ RETAINING WALL ELEVATION a 7 ti a P. ~ O d .. ,z., W ~zW F vwNz N W A m a i a N I e a W O x •~ E~ a W ~ W a x a ~" a m a F ~o a ..1 C7 ~~Wz~ A ~x¢~ a ~FaG m 3~ `~U~ ~~ Pia o~'h ° ~~ Wow ~o~o 7 N ~ C7~w ~N> zw~ ~3 ° m u rnz ONo Project Mgr: BSM Project Number: 08146-04 Y 719.5f ~18.6t )NTAL SCALE IN FEET 5 10 IAY HAVE BEEN REDUCED L ~~ - - ,. ; : ~ _'_-_ i _ - _ " - _ -. - 72D - _ - _ - - - . ' r __ '-- ~ - -- --- - ---- - - o - -- -- - --- - - - ~ -- / _ _ _ _ ~ i / _ -_._- --._ ~--~ __-'-__-_--_-715-__ _~`~_------ '~..-.~ ^.___'-- ---.-_._,-~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ . J _715_ - _- - - _ . - __- _- _ _ _- _ ~-- -' - _ - , ~~" ~~ r1 ; --.~ _--- -~ ~---710-- _ - _- -i' ~ ~ - - ~ V ~, ~ 1 ,i l' , / - , ~ - -- --- - - _ - _~ _ r / / , / ~ ~; / / -- -- - '-" - -7100- - _ - ~" _ - - _ _ _ ' _ - m ~ ~ - ~~ ~ ~ \ ~ ~, / , , ~1/, p o ~ - - - ~• I I I (~' f I' r~ ~ / O O 0 0 O 0 O\ O 0 PROPOSED CUTTER LINE \~ ~- ~ ~- ~- I j ~ ~ ~ ~ l O O O p O O 4" PERF GPE I I I III ~ 0 ~O 0 O p - O ~ O O O DRAIN 11LE SEE SHEET 52.7 -~ ~ ~, ~ 1 ~ ~ ~~ ~ I I I 1 ~ ~ ~ ~ , 0 0 O O p 0 _O O O ! ,~ ~ FOR CONTINUA110N / ~ ~. ~ ~ ' ~ / I l I 0 O 0 0 ~~ I I ~ ' ~ I I I I I 0 0 0 0 _ 0 0 O O ~ i I / 0 0 0 0 O 0 ~ r,l:':3';';~'! ~'r~'`.".. •~ i~ o '1 1 1 / h I 14' PERF CPE / 0 0 0 p 01. O p O O r q /~ :a :i,';,i0`f;.:.,:_,..1•~•'.?;, f r I I ~ I DRAIN TIDE ~; 0 0 0 0 0 O 0 0 I, h 7 h her, r, l,/, , r I y I /~ 8 !S`a?T^;• '-- -' '+9:v.;L+' / 0' 0 ~ , h h N h ry Q~rlr/~ ry 7 4r,i ri~i,~ ~,Ar~ ry \+a{:^.i'r. ~ .: X;: u..4-xytirc:~..°... •.. 7.. ~• 1. I '~ I I I O .0 r I/ g y r ry y g I rl 14 H I ry/ .x•;til;•:.'.y~f~~°j',:~~''t{:`')l o:; ~,:J .~ .,'•id'`.r'„~:'k:i»a::aFay,.i.:%~'•.'. ~'E`•i ~ I S 4 I/ I I I ,, / / / I I I , / t:a,a:. r1;'1 .'a {.~.<,::. ^,y°.l+V ~ t'`~ { 1 F III "i I I I ~ ' ~ / 1~ , IO O 0 O r~/,rr ih~y9/ IhppNh r r, I I / r ? .;a. Y.:. y,: ,/aj •". ..;`.','1i r ~l•4 Is ~'• ? O 0 / •,,0 _ r / Ir/ ii i i, p ,r ri ,i ri irri, ~rr~ li r,/, , ,y,,,.. ~:?,: t••i{`•`" 9 ~i,,,' . ;'P'~"_;"•;q!~LL~C,;,,r, •~.~;;:5~~ ~ ~ ~ ) ; ; (~ l r I l - ~ O I , , r i I' ,/ p q ~ r t I i '3P'ri~,( h°S.i ',Q},Ty$ •';~^.'; n4 r.\ .5.~. I I ~ : / I J I ' O O- - O qq r r I r r ; J '/ / 0 O 0 0 ,li ii ,, iyrr ii,~//4r/ prygq i/ir4 rq~l, r, it r~ .;:: eY%~1~i ?';;:,~.::~ ~:_ 4•~, ~~}~~ ?r+k7• "' ~~ ~:.Y'a ^'qt, :k;e~3~5, ~.4:~:<':it;_Q.'- JI I I "~ / ) i~ I) ~ / ^ ~ ' . 0; O; O , I r y/i~ b9 4 Ir,4/i~ r r gll l , y q r ri ,_ • ~ g;•~/ :".~~F,"~° : ., 6,1s" ,y, .. J~~V. '; I , ' \~ ~ , , I I / I, / ~/I II // r, I / 'ir4 :5~,'-:~.' U~'f •yS ~.=t:`^<n `:.: `.r~F13r` ~' iH ~' f.., ti.p "l.<"::4~ :rJ„~. ~. 1 I II _. - , 4 n~rir ,~ lir, 4 ~r / r r I ="~`'~''k'l ,}'t' .:f:7'?~ • _ _ ~! •' z' I j l~ J ~ / ~ l - .0 , 4 4 I ~i~l,~ p / ,, i p / , "" °;C: v;j_ T~E ,,., :;;~;~. '1} V °ppd>p~~.2pp M ~•1 ,-, r- / '_~ O O , r ri,~,i, h~,~l r~r,~,? i~ihr Y~~,,h" ` {i a Irt} ~ ~; ~ L ( " ~ 0 ,~ ,, /, // 1, ~/,~ , l,~/, I r ,^, yc ~~~ ,._ ~.'^4~~ J I ,1 ( r / I ~ .O C) ~ O , 0 , ,r it iii, ri4 ,~/ti h ,rl r/ir r q ~...,;'+,.:.ir +~@• .n o• p ^ _ ~ ~- - I I I r r • / ~ i i 0 O r rr ~r~~~/i i rrr ~,li r/i I/r ~ r'.:'j~i,''~ y 1d u,~~;?.:{'.r~ 0. pro p,, 0 © O _ _ _ ~ I r Irl /~ q~,~i h~i err r 1 ~r....: ~;F7i'r:'~('. b.R ~r ;i:.4an.y, i, ~ 0 a ^7 ~\ c ~ I t /j /j I ~Ir~r ~ ~ /j Ij I% I/ {., •, I,t:~ ~ \ y ,,.r. y I ~ I O rAl ~% ,, ii,,((~iri ~i ri 4r ,° .'.. ~' ' ~ ta4d4~. `' ro ~ ~ N°j b p' 1 X LIMESTONE ~~ RETAINING WALL I ii I I /0 ryr, /iii r+ri~iilr~ ..,." .,. ", };t`., a f.., '~ 1.19 697. ~ I ~ E '.~;. ~,r, ~ ~ 1 ' ~ 697.50 8,01 0° ~ ~~ J i I I riq i`rirr.r:;p~? ~$>.i . ~e h 7DL27 ~ ~ 0 ~l~lr }y,~au jt,„.+, ~ i ;..m ' ~~_ _. -- ~~ ~ v ~ 701.29 I fi97.56 I fi98.34 ~ me i I , - ~ ~ ~ sll ~ f ,:'<, ~ I ~'~ ~ ~ 1 ~~~ ~~• I ~ ~ I LEGEND ;, r, - m ~ CONC BACNFlLL ~+~ ; ~'V•t;iy;y!,, +}' EX LIMESTONE °~ -=-- _ _ `~~ ~ ~' ~rn ~ ~ ~ RETAINING WALL ~ ~ I (ABDUE) i, ~ ll ~ ~~ LIMESTONE FACING ~~%~%~~~j%%~I~ -J '(U4.5 t7'1'M N A m 0 0 N I m a m A 7 a a ~ O d' r~ ~ w a zw wz Q'~ O C7 Q z E ~ W a ~ ~ E a rn H ~o .-I W Z ~ ~,~z~ W~rE~A z 3~.. ~~o ws~ H Pia ~~~ o a„ Wow ~Q~o ~rY~~ 1~, N w m VV'W ?°3 Zw~ a„~ w~~s~~e ~w ~~ m~ Ntnz Qw>° RETAINING WALL ELEVATION 719.51 '18.61 HTAL SCALE IN FEET 5 10 Project Mgr: BJ6S ~I, Project Number. AY HAVE BffN REDUCED 08146-04 © 1 HORIZONTAL SCALE IN FEET 0 5 10 DRAWING MAY HAVE BEEN REDUCED L V V 'v 0 v n ~, 3 710.5 -TOP 707.5 - BTM RETAINING WALL ELEVATION HORIZONTAL SCALE IN FEET 0 5 10 DRAWING MAY HAVE BEEN REDUCED 719.St /18.61 INTAL SCALE IN FEET 5 10 IAY HAVE BEEN REDUCED bl u .a P. az ~o H L~ ~ zw a F ~ W rF/ Q N W A m 0 0 N I a a W N~ W C7 Q z E~ ~ w ~ a ~ a ~' a o x ~° b r o "'! W~,-~~ A F ~ hHr ~' W ~ H~i (~ ~ 3h. ~U= ~s ~P~a u~~ w W~a ~Q~o ~w a ~I~ 1~, N wW V Y'W >'i vY' ¢rv:a zw~ sus w~ s~~? ~a aNW ~,~ HrAz o~> Project Mgr: DSM Project Number: 08148-04 / ~" I i ~ _ , ~ - - - _--- _- // ~/~,~/ ~ -~-J-_"- -------'"- ___'---715----~~ _-----_~ ~ --_~ I ~ I _ '-715 _ ,_ ~ - _ _ - - _, _. ',w, M. _ _ _ _ _ _ - - _ I ~ ~ _ - _ ~~ / / ~ i '- -- __-._ __ - - - - _ `- - _ - - -\ - -- - - -;'; b, ~ PROPOSED GU~R UNE ~ ~ % _ _ _ ' _ -_ - _ ~~~- j~ ~ ~/~ _ _--__---_-_ ___--- - - --- -- --- ~~ _,~ ~~-~~ - - _ l ,~. ~ ~ ~ r ' i / ~ / - ~ ~ - - - - - - _ - ~ O ~ - - ~ SEE SHEET S26 ~~' I i j ~ I~/ ~ ~ 0 0 O _~ ~ O 0 O O_ O - O 0 O O O O FOR CONTINUA110N ~'- ~` I ~. ~ I 0 O- O O O O 0 0 - - °'~ ~,• ~ Ii,'If~II ~ ~ '~~~ DD~ 0-,0.0 00 ~p0 00 DD O OO Op O00 DO 00 00' O OO ~ - -- . _--- ~ r; i I l,i~ ,O O p O O p O O O !/ i O. O O I. ~I ~- r~ I a: O O O 0 0 _O D O O O O 0 0 0 p 0 O O O o 0 0 O O 0 0 O D O O O 0 0 0 O O 0 0 '0 O 0~ a ~ _ ~ i I I'~II,~~~~ i~ ~~ ~~0.0 O'~ DO ~ O ~ O 00 p0 p O p 00 00 D p 0 O D O O 0 I lI, I ~ 1 ~ / 0~ 0,' 'O 0 0 p O O O O O O O O O O p DO O O O O I ,I~~III~ i Q D. Do D° DD D D~, o D° DD D o DD DD ° Do o Do Do 0 0 0 ~ ~II I'I ~ I t o DD Do o D D o 0 0 0 0° D ° D' ~ D~ o I I I~ I i I ! I 0 O ° O O ° ,_ O O O 0 O I I I III ~, I ~ ~Q O 00 O. O -0 O ~~__ O. ,l,/i/ilq hl/ /q44~//ry I I I I ~ 0 O D 0 0 O D / // // / //I/ / h r / // / i~/pl //i q/i/ ~/ / 4/ lei////i ~/i~l/I / // ! 4r I I~ I I O O 0 O O O O 0 O 0 //, n,ll n/ //// p~// / h~41 oh,l / / / // 9 / / // rll/ / i/// O // //. ////, I/ /// 1, O I III (I i I j ' O ~ O 0 O O O O 0 //// // q // I~ / / y / q/ ~ 1I! III I 1 I ~ I ~ 0 ' 0 D O ©~ - _ 0 p O D //lO/~~/4 ~i ~i~~~ ~;~~~r~i~~~i41j ~~/~/ii/~i/i//~~// I /- Ir //~l~riri /rih~~i~i i/ ~/ q i/ ~~~i//i/' ~~//iii!/ /J~//iii ,0 ~. I III; I; I ' O D 0.0 ~ / i / Ir/iii? 4 iii /~ Ii i li 11 /~/~ y it it/q rl // l~ ry /Ji / ~ ... / / .+v-••.::,~. 1 I: I i i D D D D D D / / I it 4 ///rp / 4 4 i~/~r/4 ~ /, / ry ///i i / :§8 f/ i°` `~7ri ~s,~~.i,,,v~• / `L^,.~N}Y:i;t `a.tijj":~~;:;..;y~ ~ ~ !I / I ~ / _ I j O D D D O // / I / ~ih// /r, /iii 4/ / i //~/iii 0/ I/ 11 / Frr~;Y.;r':.'v';S•::;i.'r / ~;, u,4 ~ ~.;1!~:':lY ~ y ! 4X '~ ~ I / I I ! ~ 0• O / iIi r4 /l~~/y/I 9/IDI 9~/II / ,•".'^::,7J w tr, k _ _ .yl ,,,., .,,, ~":a s1C' ..;,~'Y„ {` I . ~ Il l I D rt/t~~~ D D D q / ~ / / q y q /I l I / p Il ~:•5:,...r; .:^x. tt ;v7~S.,ly .~A? r:jklt'~,1 ~ '' !. l: I ~V II/ r~/r// / III ~(5._'/ri '~: r''1~!. ~4.~ "'li :'4~.'l.'Q ~I.A~'..:1` -%. ~r:4~r,,''~H I ~ / ~ I ! o, // ,, / // ' .I / I / D ~ b - ~ / 11/ lr ill/ //I !I I~ I Ir/ // / I / / ii4i3 YNS. •~'Yr ~1 ~j~~e. ~ ~~A 4^j;',' .v .. ~~ ~~ j I /I I) I ~ I ~~ ~ ~ e ~ D 0 D ~ I ry/b ~ry ry41~iiI /~~/i/i ilr'l//I~ II rill /i ~, ~~ ~S~i_{5.v. n r'Y'A 1~~~'~ , ~ / !„(V> , / / ~. / ~ ~ \ r l r / ~- -~ ~ ~ _ _ _ -_ _ _ -_ - _ ~ _ / / ~ i .~~__ __- __- - -__ ___---720----~-__ _ _ -_ _- __.-_ _ _ _ ~ - - -- -- - - - _ -_ - -PROPOSED GUTTER-{1NE- _ - ~ _ 'r,~~~~, _ _ _ -----_--_~---~__--- - - ___ ~'~---_-775-_- __.~ ~~~~~ ~~~/ ~ ~~, -- -- -_-_ -- - -_ -_- -715---_"--~ ----- -~~~ O O° 0 ~ _ ~~ \•. ~/ ~ ~ /~ ~ i --- -- _ - 0 O O ° A _° ° ° ° ° ~ ~s / i o o ° -o a_ -0 0 0 0 0 (( %lji ~ 0.0,0,00°00. o o° o° o° o° o ° °° °°~°° °° o o ° ° ° ~~~\ l;•~~ / I i °, ~©x,09 0 0 °° o° °° °° °° 0 0 0° o° o° ° ° ° o0 0 0 ~ A ;r~lr' ~~~/ ~ o o ° °° o°o ° o 0 0~ o, o o° o° o° o° o° o°o ° o 0 0° ° o° ono' ~ I I I ~~~--~--' ~D ~ O~ ~o o° °. °o 0 0 °o 00 °0 0 0 0 0 0° o° o° o oo°ooo b' I I I {I~;ill~ / -° o°. oo~o 0 0 0°° ° o~ °° °o °o ° ° °° ° o .° °o °° ° °° ° 0 0 0 0, I I i I 1 I I ° ° o' ',o 0 0 0 0 0 ° °, ° I IjI hill o 00 00, o~ o o° ° o° o ~ ° o o ° o °° o 0 0° o° o° ) I II I 0 O O. ° °° ° ° ° _ ° O / ,/yy,/y/i li'i` ifs/ioy'y///,y /// O~~ / I i i ~ °, ° 0 O 0 O- , y, ,i,i9 y h h y y h h y / y ,,,/I//0 ,,//ri/i/4 I II III u_: 0 I 0 O ° ,O 0 O 0 °'.,,' / "/ / / // ,h`i/`,i9y y/``/i/ti i~ :yi/ y`/,i/~/~ /yir,4 r, yy, ,°. / I II I ' I ~ ^ I O O. ° O ° O. ° ° 0 0 O O O O 0 O O / y / ` l p / a n/ / " ' y ~' ` / ` //y / /~/~~~~/ /~ ~y/ ° I / '. I III ~ ~ I O ° ° ° 0 O O r lrii 'ry/y ,/y,i%,, y/y~i~/~r~, r / y /~`~ ~ // /ihi/i/ y, //,/ ~/~i~ii/~, ~i h/4 h i/~/ih~i/i//r/ ' 0. I I III I O O `;~. O; ~ ° - °-O O ° O O - ° 0 /,4 ~,~~ ii h`y~ l h f///~, p y 4 , / ,//,y,~ /, y / ~/,//4 Vii, ~/~/ ,,/ y/,4~ / / r'/ y 4 y /r/ / / / ,. I I I. III III o. rl,;,,,, ,/l„ ,,,,,,/, y,,, ,/„ ,,,/ ,~ / ~0; O' /l /hgryl/ //qy/ /44 yy/// ,.u 14`x. :k. », ,,, ~ I ~ 0 ° O l` li~/q//i h y y q yil i/l `l ii h//i 4`4 4i/i/ ``" ,.Jf .5:1'~ •~ ~..,+r. ~~u t}l~ry ~`1,y ~N~'."i ~i:~' - ~ I / I I I Ii' .I I ~ ,° . 0 ° ° ° ° ,/ / / /y q y 4,i`/ rr /`y,y,yr/y,i`r , , r ~ iii/ y r r, y ti,:,:"S+ ..'~".' 1~~~_ ,. :3'~ +~1, !~!~l`.4`''` ~o~, b„~r. ~w545fw'S:F, ;Cy~'~«,r,'r' fr,} ~~~ / I cs+ ~ 4 ~~ I I ` i O O ~ 0 ° O ~ ' i / h` y l ` `/ i/ i/ `, / / `/~ / ...!'v ' '~ ~y1?`i:.. ,,: Yv- ~? A a.y , N, rs ~' r / rti /A} ,f , '' / I ,1 ~ I /r - 0 ~ O O~ ° ° °~ ° + y``h/ y, y,, li y / i / y / i , ~,1 fi~!' i~ t 4 r ~ yr~ , ,. ~sl~ r~m r' . . 3. •~y• {,.''~o-,~ f .a,~{ /T / / / / / / N , {n/ ,ti r ~, ,I l . / 1 l O; 'O ° ~- ~,0 ,„o 1;1i y `o `/`r/ r r/iy, '1.::'11 :y','`;~r ~'r:nty~•a';.~X'kN:,~ I , ~ I O / y h y , ! h 4 , 4, r , / .' :7.' ~^+" ~ . {;'w.`: ,. ~~ I I ~ / O O'° a ° ~ ~4 p~/~i/y44 ~~/~/ i/,y~~~ii ~'•~yY':.v 7rol~i.i ^,',1"`r !•• 71.13 1~~~~ =7_^? /I~ ~ / ~ 'O rO /y//4 9y/i //~/~/,y,4/ ,i/,l r~J , ~ '~ +! '.>n4 .1 •• n ~0 C1 po O I/(I I /I; O °: O O /4hy/ihy `riif/i,iy i~~/// ~*•Z .t ';~~~ ~y M IN ~ ~0 ~O 7D1.12. ,~ - _=' 1 I ~ ~ I! I O O ~ ~ y y`i`i n`q /y i`, ~ ryi/ / ,. :I$S?I Y,S;: p r~ r Cr ~ ^. YC 0. a m' o _ ~_ F ~ ( ? y , ° 00 /; / r / fir y / q 4 'r f •e !u+ . I ~• 698.330• ~ ~~"• ~, 4~ .- ~= '~ I L I 1 ~ ° O 0 O I , 4`, 4 yr4`h/4`y 4 ,i h q /, / `.I ~d. :~^~C )~~ .X,!: ~.•,: _ ~ W~ 0 _ o n I III ~ I O / /,/ q ~, `I ~ y / 4 y y /~,y i/ yi; i,'/f4•. i . %~:v{ %"~n, ~ ~ I I [ p ~ ~ I m ( fi n I EX LIMESTONE I I ~I O~ .,.~/~/i/i/,/f y/: `iiryr/Qej irir :i:/y ".4..~~'•d.. ''{R A• N ~ I ~'~-/ I mac' `c 0 o 1 RETAINING WALL HOR20NTAL SCALE IN FEET 0 5 10 DRANING MAY HAVE BEEN REDUCED 7s.5t 115.6f ONTAL SCALE IN FEET 5 10 i MAY HAVE BEEN REDUCED w y a P, ~ O E C7 ~ ••zW ~~w F a,FG ~ ~ ~ N A m 0 I 0 N I 0 a of W O Q z ~ ~ w ~ a ~ x rrF (n a w p x ~o D C~ a ~ c~ ~~W~: ~,~zo~ 0 ~FaA z 3~^ ~U° ws F ~w a a~ ~~~ ~ W~ ~~~o ~~N A w~ ~~~ ~NE w >r z ~~~ w ; s>~' ~~' G~ U V7z o„°> Project Mgr: BJM Project Number: 08148-04 I ___ _. „nnunur IDIMI DAII TAI t! n i n i ~ / i ~ _ ~, _ 0 0 9 `J ~~ ~ - ~~ ~- '~ ~ -~ `,. ~ __ o ~ ~ _ __-- _ __ -_--------- -- _-_ -.._ --- _. .- -- - -- --_---- C ~ `~ _ _ - _ /,~ ~/,/ ~ 90 O 0 0, _ D _0 ©8 O O _OO~ O~ O _ O O O O p -O /';~ ~ ~, 0 O 0, p O - - O- O - O -O 0 O O O 0 O 0 O O PROPOSED '~ ~ I ~( / 6 O O 0 Q.O. 0.0, O O ~ -O O O- -- O O~ O O O ~ Q 0 O O-~ 0.~ . O O, O O O ©. O O 00 O p O C ARCH ,' / Q 0 0 0 0 0 - O - O O _ __ O - p O O 0 O 0 0 FOOTING '+/ r` O 0 O O 0. O O p O p 0 0 0 0 0 0- O OO O p O O 0 0 0 0 +-~~+I 00 00 O, O. Q O 00 O O 000 00 0 O 0 p O 00 Od O__~- O ~ 0 O ,, O o,a ° Oo, o. o o o° ° o o ° p° o o° ° Q ~o _ 1 _ O o Q o o~ d -- I-'~~I~,~~~ ° Qp~ o., 'd o ° Q 0- _ o. O°'Q °p °~ O° op o° p Q° QO o0 OO!pO ppp Op op 0 p p I I' ~ I 10 O O 0` 0 0 0 0 O 0 0 O ~ O 0 0 0 I II II IO !00 pOi 0 O O O O O O O 00 p O O O O p II I O i O 0 O'•O4j O O O 0 00 O O O 00 p0 O O O O O O O ~ O O O O I I II ~ i C) O O CJ ~ O. 0 O O ' O O O O O r 4 4 r 4 h bar rr/ri ri 4+ 4ir4+i ii p rir+, 4i+r+rr r r 4, r r II I O O O O '- r r 4r ryr r,r rr h4r+irir 4rr 4444 h r ,+rh4 r 9rr r r irr ,rr rl, I iII III i I 0 O O. O 0 ~, '0 O O O O O O O O -..Q O ~ i +rr r,rr ri~ir4riirr h4r4 irr irli 4+r+r r+++rr r41r'ir4/~~r~r it ~r it ri +++r Orr+ir rr4 i++++ ~++rr r4r+++irll r~ I I 0 ~ O 0 O O O O r r rrr r ,, r 4 4rr r 4 r rr r p r r ,r ,, r ,r 4rr rrrr, r 4 h rf + rr , r r I I I i O~ 0 O 0 ~ r 4+ 4,r, r, ri 4/, h r rrr/r/ i ry,rr , rry h 4 ry hr + r 4 r rr4 r i r r rrrr h r r r 2 r r G r r r r H r r r r r r r rr rr r r rr r rr r r r r rri r r r r r r r r r r r r r r r r r r r + r. I '. O 0 r r r r r r r r r r r I I III I 0 O O O O O 0 O O 4+rrr 4rr4r+rrrr 4 h 4 4 rrr,rh4ry rrr l r„ irri rrrr r4r,r rrp 444h4+ri9rr r, I i li~ I i 0 ,O O O O'(,D ~ O O O O O 0 r rrr rrr, r !/rry rririri/+ iii i+ri4 iii/iirr ~ irri ~i ~r+4irry i+44 r x4444+ + r ,r+r r, r ,i4+ r y,r+rrr rr4 rir +irhr rr rry r r rrrr rr rr I III III I O O O 0 - - O r r ,rir/// r rrr r, rrrryr i 4,i ri rii 4+i ri~i i4r 4rir rri ii4 4 r~ r+rr it + r r rrr rr ri g i~ r ' i r r / +ry r r r r i4 r i + ri rrr r I I ~ O O rr r r, r rrrr rrg4rr rrr rh4~r rrr , r r ry rrr r,r r,,4 r q4/r4 iri hq /r/i r~iri4fr rri r+r+4 ri4r 4r I I I Il I O 0 O O 0 O ' rrr 4 +r 4r r rr4 ~/ 4r q r r g h 4 r+r+r 4 ~i 4~r r+rrr ~ i rirr+4r it rr rr rrr ri i it r r /r ryr 4rrr rrrr 4 i+ir i i i4 r ri ~4r Orr/i rir+ rri if ri I ! /CiO 'O~ O~O ~ O~ ~O.-'O~ rgrr+ r,r/rlrr ii 4r+i4 r4 4iir4 rrr ,rr rpr r,h r4 ry/i i+ rr ri rr r, rr4ri 4r I ,~ .I !I l O O O ,OTC) O rr +r r 4 r+i, rri i+irri ryr~ r, /4rr r+r yr4+r/rr +r4rgr 4rqrr ri ri ph ,4 rir/rr4 r+~r 4 r r lI ~ r ~ O O ~~ O rr rr4 r444,rI ,r4r h,r~ rr , rrrrrr r'// 4/rrrr+ r 4444 Q O 0 i I Y) O O - 0 i ! r r rri+irr/r r 4 p 4 i!rr rr 4 y i rri + r4 ~r~r r r4irrs +rr O O l i O O I r i ~ rrrr ii4 rr rr/4/~ b r a /i r4rr ri ~r, ri,r rr y y r 4 ,+ r/, r r _ O I';I/~'~I' 00. 00 ~ ~ r,r, ry//,~~ry ~i;~i ~i~;~;;/~r~;,~ x444 q~i r+q+r ;r f%r r/44; ~'r, rr - rririfiiri ri i4 i. r r~ 4 iir r r 0 EX V a a m ° 0 b " N ~p ` PROPOSED GUTTER LINE 6p c I. . O O O Q °` ° ~ 0 o. o o p o p 0 O 0 0 p 0. O O O O O O O O 'r'n ,0 O 0 0 ~ b ~~ifr O [~ u ri O 0 0 ® o rig ~, 0 0 0 0 ry O ~ 0 O,' I r r r .. ~ u a rl + ~ ~ I;' rr irr4 rirr; rih rh4h, f r 44 r rr r r r + , 4 4/r rq ri ri r, 4x4 rrirr r4 i ri !i r i 4/ , ry/r b~ir r/ri ri 4 ',~ q rr r r ~ rr 4 9 4 i r i r r r 4 44 r rrr r h p/r r rr/ry 4 r r r 0 ~.. r ^ 00 0 71.13 ~ ry ^ r\ 4~ ~ O 701.1 ^O _ 1~"`. - 11~ I - _+ ~ ~~. I~ ,// , i rr r , 4 r, ,4 44 ,/ y ,, ry h 4 4 4, r, r ,r 4~ 4 4 ry q r 9/rir/ it it+i~/ rrr i it r~r 4r i+ brr, rir ri rih r + + ri r r r4 O ' ~. ~~ 698.33 I ~ 00. 0.~~ ~ ~q ~ =- _ , -.__ illl I 0 r/r, r r/ri ri4 rO~r rir it ir4 hr ri4!~irirfri 4r/ry ri444,rr r, 4 r r r i r rir r1 ry r r r ir r r '' it r rrr O O _" ~ O ~~ - \ 0 ~ ^ ~ 1 I i { O 9 , r , / r ri ri 4 4 h r/rr r girirp ir,~ r~ ,/ +r rri///r r Vii,///h ry/r 4 4 ri q r, i r r V' ~ ~ ~' 1 ~ ~ _ _ p > O r I I I I I I I O i ' O h,r r 4 x 4 4 ri 4,rrrl 4 9 g 4 ,r fr/ri ry,/,; ri q r+;;;r;r, r; 4~; r; r 4 4;r ; 4rr; ;, 4 r 4 ~ r O ~ _ 0 ,, ~ 19 1 ~ 697 6 I O O O m r0 i I ^o~ S 1 ! EX LIMESTONE I I I I O C) r /r / 4 ry 4rr,r, r,/r/ri 4 r 4r ,~ it ri /i i'r r t 0 rr i ri ri 4 4/r,r fr 4 i 4 9 r ' . I ~ 697 50 '" . I ; ~ I o X5154 I RETAINING WALL I I O r r , / r 4 4/r 4r ,~ ,/ y 4+ /r 4 r 00 . 01.27 698.01 ^ I I O O ,r rr riry r4p4rrr r O _ ~_~ a' 1 697.56 I i I I I I O 4 4 r r_ O ,O ~ _- b- --~ °~ n W 01.29 ~ 698.34 ~ 0 ~~~ -I or- ~o -L O~.O~a ~ '~~ ~ ~ EXFACIN~ "'-RETAINING WALL (ABOVE) GEOFOAM BACKFlLI. _ 723.53 '----I- ------------------------ II I I~ I j j_^ ® II N II 3 II ~ ~_L1_, ~ ~----~ N I EX STONE FACING _~ ~ ,rv y I \~ a~' I m~ 00 ' an ~ I .` 1 ~ m ` 1 4" CPE RISERS I '1 I SIEE DETAIL 1/52.01 V I I ~~ V STAGE 9 PLAN 716.5 -TOP 713.5 - BTM 725.51 TOP OF EX RETAINING 724.03 WALL BEFORE COLLAPSE 704.5 I_ 702.1 _ _ 701.1 699.3- __ _- - ~~ 697.8 696.3______ 694.6_ 693.4_ -_ __ __ - I----'"'~ - - - _ -EX LIMESTONE 691.2 FACING 701.3 I 694.9 ------ I EX ROCK LEDGE ,I ~I I ' LEGEND N ' C BACKFlLL CO r`^n~.{rr,•";.~~i ., l,..,.,.,.r'• ~::~ LIMESTONE FACING GEOFOAM BACKFlLL i 4/r 4,rr~,~ rrq ,?~;~;~1,4,~ ;~ ;;„ COMPACTED BASE COURSE BACKFlLL 72253 WROUGHT IRON RAILING GEOFOAM SEE DETAIL 2/51.1 (SIMILAR) AND 3/St.t BACKFlLL (2' H) PROPOSED GUTTER LINE BEYOND 721.03 ~ EX 717.63 r a ~z O C Ch Z ~ za W ® '~ wz ~ m Q'i C' HORIZONTAL SCALE IN FEET 0 5 10 a, ~ DRAWING MAY HAVE BEEN REDUCED A Q C~ W ~ G4' a (~ a ~ ~, ~ ~ O 719.53 a 0 rl Ch ""'IW~W z A H~ ~ ~ _ o w ~Faq 718.61 z ~U° 3q.. vs o ~~~ ~~~ w ] s~o ; ~~ ~ ~~ ~<3 ~ z w aH> ~°3 w~~ ~ ~>~' w '~V EX LIMESTONE G p m & FACING i-I UI z o 5ai ~ ~- J EX CONC PAD L EX ROCK LEDGE RETAINING WALL ELEVATION HORIZONTAL SCALE IN FEET L./ D 5 10 ~ Project Her: B1M DRAWING MAY HAVE BE~ DUCED ffoject Num6ee 08140-04 © 1 EX HMA ROAD ., _ ,, B s a ~ D t R ~ ~, ~-" ~. / ~ - / / 1 ~ - ~ ~~ ------- ------- / r '/ _ ~' - ~~ ---- ---- -----~---- - ---- --------- __ _ _ -~ ~ m / ~~ - _- ~~ ~ . _- - - - - - - - -_ .- -- -_ - - 720 -__- - - - - - -- -- --- - ...~ - -- - - _ ro o _ _- _ _ _ - - _ -- - __ _ _ - -- - - - Q I ~ i ~ / ~ ~ / ~, ~ ~ O O - - - - - - 0 _ O_ ~~ O ~ ~ ~ ~ O O - O PROPOSED GUTTER IJNE ° /i~',/ O O O 0 - O 00 O- -p0 00 p O ~r ;~ ~ ~ O O- - - _ O O -O -- O ~ p O ~ O O. g_ O O PROPOSED /~. ~~ f' 0 O 0. O D. - O O 0 O ARCH ! / r / p O ~ - © - O ' O FOOTING '~ I / ~ 0 O O O 0- - O _O ~ O O O- O ~ O 0 ~~~ ~ ~~ - It l"r' ~ O O O O 0 00 00 0 O 0 00 __ / O ~O O O O p 0 O 0 ~O O O 0, O O O 0 0 O O 0. O _ - ~-~ ! p O O' O 0 0 O 0 0 ,r' rrh h ri O O O I r r , 4` 'r `rr'ry rh/, rrr ryh44 ~ I /I'~~~II ~QQ O OQ ~Q O ..Q Q _ .'qr' 44'rr err /'r'r 'p'i /'r'r O -- I ,O, O hrr //r rlr r r , //p i"i i O II I~ ~ O O r i,4//,~ ,/,p,4r , r, r , r i i' r r r, r4 O O ~ r r hq r r r r 94ryh ,,rrr iQ 0 w W O ~ 4 i r 9 r rr it /'r/ r/h rrr q/rr rl r q 9/ h/r r'/'h h'h'r/r/r O Q Q, o a ,r hr r r rpr , _ I I, I I ~O O. O q r` irr r r'r ,i4r 'r'r'r/' /r r' 4444 ,4 h,r,, ghyr O O O F. I I I O rr h4 hq 4 4 4 4 ~,/,/, ,, hhhr r4,,,' ri ri 4r'rr O O I O b w I I I' i O O O O ,r ,r,4 ,, rfry ,, , pr. 4444/,/r/rry 444 r,r,/r/,i r4r,r'r - O p O p p Q ~ ~ i O O O O r ir4/rri, q 4 h, „ rrrr q h h r r, 9 /r III I ~ I O r,, ,//,~/ 'q hr riG -4r//'yip //r, r,rr q4 , ry , , , r r - r r ~ r4r 0 O O m I I III I I' O 4 O r r i ri /'r '/i'r i'i iiiirii 4 r/i'riii i i~,i/h ii'4 ',i 4/i ~i y ry 4 ri i'r'r r'r ,r,/4 4 r 4 h~'/' O O Q Q ~ D III I O ~O, O ,444,r4i'ir4 ,,/p,/r 4r/4ir, /,/ri/r, r~,4r ,r44 r4r r r4ri4 444/r ii,4ry4, N,,, O O Q li O I I I I Q O r r,'r'~rri4 ii'i/rrr ~'r~r r'~ ririr'/r/' p,q r r ~ ,r,r,r Grp/~,'4 r 44iri i`r/ry 444h44r i~14 4 e ~ Q m V I • .O ~ r , r ry y r r 4 , rry` „ ' , ~ r r r r, r,r , , h'h l4 rr , r ,, 4 4 4 ry41r+,/ , 4 r, __p- O i O Q Y. III, IIi ~ i h4rjry /r4rir,rr,y rr4h/'rr/i i~ri4 r,p, rr ' r' r/ryry pr/r,/grp,44 4/i /`''r p4 h4r it r, 4, , O p _ Q / I: I I p r ~,h~i' 4ri /rrrr .,r''ri/ 4 4`rr ~', ,4 jrri/, hr4 rii iih hr'rir r rir , , i'r r 4/r/r r 4 r h,r, /, q i ,, r,r,rr~ ie//i;i4 4/,/ii ~h ,;a ,r ;, ,; 'r ry p OD , r rr' r r 4 r r s i i r r O r r, , r r r ,, r r r ;I ;I r /i rh' r//''iri ' r/4"i i r 'rr, r /r r' 4 r,r , ~4y 4~ri , rri riy h4 gri4N 44i'irr rr 444 r, O p I ~ I i, , r r 4 „ r 4r h %r / r p r/rryr r p h r r r 4,r p ph ,, 0 O r r,, g h„ r, q r, p r p ,r „ rr , ,, ,, r q rr r r r q r ry p r/ 4 r h rr r ry h r,r,r r r I ; I r ~ l I: rririr//, r r' ~' i 4 r / r hr/' / / 'r///4 ~ 4/~/rri r r/ ~ „ q rr h r ~ rrr, ,~ rr/r /rr p r, r 9/ , i4 ry ~r/r ,r,,, , O 0 O O. 0• rrr +rrr` rrr hryrrr , rr r r i r ; I ;!, ~ .I, 4,hri r//r G',44/r„/h'4j4 r444r 4, r h4r ,rj4h/r44r, ,,i4 r"h ~f/i 4`r `r 44, r r 'ri i'r r _ _ _ I rryh ,r, ri r, rrr 4~igrr rr'q r rrr 4ryh p,i r,r 4/ r,/,/„ h/i h~ r r Q // ~ ' , 4 r r r, r r h h r 4 4 ~ Ii r r r ry r,//, ,r, rrr,/ r,/r/ri 4 0 r/ri', r r r r rr r r h 4 r r r r r r j /I/ ~ h g r r r rryrr , p g ry r r, , r g 4 r , r, rry ,, it r'r'r rr rrrr r'ryh'~ r r'/' ~/~ ~ Il !~'r ~ ~ ,4//i rr 4~4i,ti riri'/ ~i~r Ii iigrr/i' rrrr'rr 'riq'4irri'h riii~'iI rh hrr !'rl rrh i'/~i ~~' / , ~4~4i, p , r / r/ O - _ 13 a __ .I I ,~J q4h/r r//r,, ,ih 4f,rr rrrf r rr, 4/t rrr rr h, , / ~~~ ~' - .. 'N .-^i 00\ ~-...701.17,(11. ,.~ I- rr rr rrr , r r r r 4 r r'h I N, r r ry„ , r p rr,r/rr r r O h n n 0 O [ O LI I ~~- "I'-I r 4 4 ry r,rrrrr ',' rir 4'h h h p p 4 r' 9r rr', ~ r I A' 98.33 ~ 0' P.~ 4,' n p - - ~ Qa r „ rr rrr, rrr qr h,r r ~ Q ___~~ III II ~~ r4hrrrr r rr r /rrr ry4hr , 4 ,- .,. -__ I i I,,'r r, r ,ry /rh,~ ~r i~p/,,r ,r ~r r/~ rri'i/rhb,~/~'4 r r , Q Q i 0m' A ~ m' n\ -- I I 14 r r4h4i r44~{r r r, Gpyry4, ,rrr rr ~'-~ _' O _` I I I ',/ ,y ri ri /ii'r ri rj r7 i/4i~i~ti ~r ~r ~///,i, r,r r„ Oprv.nO~ ~'i ~ -- =~ ~ ~ ~ ~,'. ~~ t 19 r~°j 00 a' ~ ~ ^ I E% LIMESTONE ra I i i I i ri 4~r// ri/ii i~ i f it ri i 1,4',~ ~~ qr 44 /~ /r , ; _- O ~ O /r 44,/ r,/4/, h r 4 h/r p' Q I I 897.61 n I I I I rrrr/4 h h r r n O y '~ ~ 697.50 ~, I f n0 %yy~ I RETAINING WALL ~~ I I i r h b r O p p h -- ~ 701.27 697.56 6BB.D ~:o LEGEND 2 ~~ I I -~_ n w, 701.29 I 698.34 ~ I Z W O a ~~ I L ~ b0 0 ~ ~ m el ~ ~ ® ~ ~ ~ l ~ ' I ~ _ ~ / or i ~ 1 1 ~ ,~ ~0' L ~ ~ ~ ~p ~ ~ ~ CbNC BACKFlLL ~' s ~1?$~~'y;::~i7 ~ u W '7a a 9 ~I Y J 0 0 n n a t t 7 r E% LIMESTONE RETAINING WALL (A60VE) EX STONE FACING ~ ~ ~ ~ ~ I I ~ I STAGE 10 PLAN 719.5 -TOP RETAINING WALL ELEVATION ~ ~ \ I I I~ NTAL SCALE IN FEET project Mgr: BlL[ 5 10 Project Number: DRAWING MAY HAVE BEEN REDUCED aeta6-o4 © .1 . n•.y ..,Aa •. 1 ~ Pi 6' LIMESTONE FACING ® W HORIZONTAL SCALE IN FEET ~ D 5 10 p '///r/rri'/'rir r/r/r ' ' ' r ' ~i r,~4 ,4/~/~/; r GEOFOAM BACKFlLL ,/4 4 r ~ rr rrr DRAWING MAY NAME BEEN REDUCED URSE O D O O AS E C B ~ ~ LL F a W a x a H Tn a ~o q x ., ~, d o .M .-{ V ""I W H 719.5 `~ G F ~ H h~ ~ H Q'1 Q nest y °~U~ 3h. ~s ~a3 ~h ~ o ~ a~ Q~ F GOm E ~ ~~~ zWW Ny ~h3 W~~ s;h ~a aym U rtiV]z ' o~0> 716.5 - BTM