NW Art JFK - 52 IDOT AgreementMEMORANDUM
May 14, 2002
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen. City Manager
SUBJECT: IDOT Pre-Construction Agreement - Northwest Arterial Extension. John F.
Kennedy to US 52
The Iowa Department of Transportation (IDOT) has submitted a Pre-Construction
Agreement for the City of Dubuque relating to the construction of Iowa 32 (Northwest
Arterial) from John F. Kennedy Road to US 52. The agreement provides for the City's
reconstruction of John F. Kennedy Road from Spring Valley Road to the northerly City
limits to be incorporated into the IDOT construction project for the Northwest Arterial. A
public hearing on these plans and specifications and the levy of special assessments
has already been held and approved by the City Council.
The additional work, although it will be incorporated into the IDOT contract, will be paid
for at 100% City cost. The IDOT estimate for this work is $1,038,927.
The City's public hearings were based on the City's estimated cost of $1,027,780, which
is slightly different than IDOT's estimate. At the end of the project, the actual
construction costs will be computed; and both the City's contribution to IDOT and the
special assessments will be recalculated based upon actual construction costs.
Public Works Director Mike Koch recommends approval of the of the Pre-Construction
Agreement with IDOT relating to the construction of John F. Kennedy Road from Spring
Valley Road to the northerly City limits, in conjunction with the Northwest Arterial from
John F. Kennedy to US 52.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, Corporation Counsel
Cindy Steinhauser. Assistant City Manager
Michael A. Koch, Public Works Director
CITY OF DUBUQUE, IOWA
MEMORANDUM
May 14, 2002
TO: Michael C. Van Milligen, City Manager
FROM: Michael A. Koch, Public Works Director
SUBJECT: IDOT Pre-Construction Agreement- Northwest Arterial Extension, John F.
Kennedy to US 52
INTRODUCTION
Enclosed is a proposed agreement between the City of Dubuque and the Iowa
Department of Transportation relating to the construction of Iowa 32 (Northwest Arterial)
from John F. Kennedy Road to US 52.
DISCUSSION
The IDOT agreement provides for the City's reconstruction of John F. Kennedy Road
from Spring Valley Road to the northerly City limits to be incorporated into the IDOT
construction project for the Northwest Arterial. A public hearing on these plans and
specifications and the levy of special assessments has already been held and approved
by the City Council.
The additional work, although it will be incorporated into the IDOT contract, will be paid
for at 100 percent (100%) City cost. The IDOT estimate for this work is $1,038,927.
The City's public hearings were based on the City's estimated cost of $1,027,780, which
is slightly different than IDOT's estimate. At the end of the project, the actual
construction costs will be computed; and both the City's contribution to IDOT and the
special assessments will be recalculated based upon actual construction costs.
RECOMMENDATION
I recommend approval of the proposed agreement and further recommend that the
Mayor be authorized and directed to sign the attached pre-construction agreement
through the adoption of the enclosed resolution.
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolution relating to the
construction of John F. Kennedy Road from Spring Valley Road to the northerly City
limits, in conjunction with the Northwest Arterial from John F. Kennedy to US 52.
MAK/vjd
RESOLUTION NO.258-02
RESOLUTION APPROVING PRE-CONSTRUCTION AGREEMENT NO.
99-4-095C WITH THE IOWA DEPARTMENT OF TRANSPORTATION
RELATING TO THE CONSTRUCTION OF IOWA 32 (NORTHWEST
ARTERIAL) AND JOHN F. KENNEDY ROAD TO US 52
Whereas, the Iowa Department of Transportation is proposing to construct
Iowa 32 from John F. Kennedy Road to US 52; and,
Whereas, the Iowa Department of Transportation has prepared a pre-
construction agreement outlining the terms and conditions under which the City's
reconstruction project on John F. Kennedy Road from Spring Valley Road to the
northerly City limits can be included in the State's construction project; and,
Whereas, the City Council of the City of Dubuque approves the terms and
conditions of said pre-construction agreement.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
Section 1. That the Iowa Department of Transportation Agreement No.
99-4-095C consisting of an agreement providing for the City's reconstruction
project on John F. Kennedy Road from Spring Valley Road to the northerly City
limits be included in the Iowa Department of Transportation's contract for the
construction of the Northwest Arterial from John F. Kennedy Road to US 52.
Section 2. That the Mayor be authorized and directed to execute two
copies of said pre-construction agreement.
2002.
Karen M. Chesterman, Deputy City Clerk
Passed, adopted and approved this 20th day of May, 2002.
Terrance M. Duggan, .'Mayor
Iowa Department of Transportation
District 6 Office
430 Sixteenth Avenue SW
P.O. Box 3150, Cedar Rapids, IA 52406-3150
319-364-0235
FAX: 319-364-9614
April 30, 2002
Ref: STP-32-t(2)--2C-31
Dubuque County
City of Dubuque
Addendum 99-4-095C
Michael A. Kock P.E.
Public Works Director/City Engineer
50 West 13th Street
Dubuque, IA 52001~4845
SUBJECT: Extension of Iowa 32 (Northwest Arterial)
Dear Mike:
Attached are two (2) copies of an addendum to Agreement 99-4-095 between the City of Dubuque
and the Iowa Department of Transportation for the above referenced project. The project involves
the construction of an extension to Iowa 32 (Northwest Arterial). The addendum reflects the current
concept of this project.
Please secure the necessary approvals and signatures of the appropriate city officials and return both
signed copies of the addendum to this office for further processing. An original of the fully executed
addendmn will be forwarded to the city after final signature by our department.
If you have any questions concerning this addendum, please contact me at the above listed phone
number.
Very truly yours,
Richard E. Kautz, P.E.
District Engineer
REK/jh
Attachment
Staff Action No:
ADDENDUM TO
PRECONSTRUCTION AGREEMENT
No: 99-4-095
County Dubuque
City Dubuque
Project No. STP-32-1 (2)- -2C-3 !
Iowa DOT
Addendum No. 99-4-095C
This Addendum, is entered into by and between the Iow~i Department of Transportation,
hereinafter designated the "DOT", the City of Dubuque, hereafter designated the "CITY" in
accordance with 761 Iowa Administrative Code Chapter 150 and Iowa Code sections 28E.12 and
306A.7;
WITNESSETH; that
WHEREAS, the DOT proposes to establish or improve an extension of the Northwest
Arterial within Dubuque County, Iowa; and
WHEREAS, the DOT and CITY are willing to jointly participate in said project, in the
manner hereinafter provided; and
WHEREAS, this Addendum reflects the current concept of this project which is subject to
modification by the DOT; and
NOW, THEREFORE, IT IS AGREED as follows:
l. The DOT will design, let and inspect construction of the following described project in
accordance with the project plans and DOT standard specifications:
A new extension of Iowa 32, also known as the Northwest Arterial, will be
constructed beguming at the junction of existing Iowa 32/J.F.Kermedy Road (J.F.K.
Road) and extending northeasterly to the CITY's north corporation line. The new
paved roadway will be a four-lane divided facility with a raised median. Each pair of
lanes will be approximately 7.2 meters in width with a 1.8~meter wide paved inside
shoulder and a 3.0-meter wide ~anular outside shoulder.
2
Special Provisions
The CITY and DOT have previously entered into the following Agreements for the above
referenced project:
Agreement 98-1-178 for right of way acquisition was signed by the CITY and DOT
on March 1 & 8, 1999 respectively.
Agreement 99-4-095 for construction of the above referenced project was signed by
He CITY and DOT on July 5 and 17, 2000 respectively.
Addendum 99--4-095A for transfer 9f jurisdiction of Iowa 32 was signed by the CITY
and DOT on July 20 and 26, 200t respectively.
Addendum 99-4-095B for recreational trail construction was signed by the CITY and
DOT on January 2 and 9, 2001 respectively.
Additional miscellaneous improvements will be made to JFK Road within the CITY, at its
west junction with the Northwest Arterial. This additional work will be accomplished at
100% CITY cost. The estimate for said work is approximately $1,038,927 (see the estimated
quantities on Exhibit "A" attached).
Miscellaneous Provisions
Previously executed Agreements 98-1-178, 99-4-095 and Addendums 99-4-095A and 99-
4-095B (see section 2 herein) will remain in full force and effect except as revised herein.
If any section, provision, or part of this Addendum shall be found to be .invalid or
unconstitutional, such judgment shall not affect the validity of th? Addendum as a whole or
any section, provision, or part thereof not found to be invalid or unconstitutional, except to
the extent that the original intent of the Addendum cannot be fulfilled.
6. It is the intent of all parties that no third party beneficiaries be created by this Addendum.
Tiffs Addendum may be executed in two counterparts, each of which so executed will be
deemed to be an original.
Any subsequent change or modification to the terms of this Addendum will be in the form of
a duly executed amendment to this document.
3
IN WITNESS WHEREOF, each o£the parties hereto has executed Addendum No. 99-4-095C as of
the date shown opposite its signature below.
CITY OF DUBUQUE, IOWA:
By: Terrance M. Duggan, Mayor Date May 20 ,2002
Title:
Karen M. Chesterman
Deputy
, certify that I am thc. Clerk of the CITY, and that
Terrance M. Duggan, Mayor , who signed said Agreement for and on behalf of the CITY was
duly authorized to execute the same on thel-20 day of l~ay
,200 2
Signed
Karen M. Chesterman
Deputy City Clerk of Dubuque, Iowa.
IOWA DEPARTMENT OF TRANSPORTATION:
By:
Richard E. Kautz
District Engineer
District 6.
Date ~ 200
4
EXHIBIT"A"
CODE ITEM
t 2101-100100 Clearing & Grubbing
2 2102-100100 Class t0 Excavation, Roadway and Borrow
3 2102-230100 Special Backfill Mater/al
4 2105-103000 Topsoil, Furnish and Spread
5 2110-100200 Granular Material
6 2111-100000 Granular Subbase
7 2121-200100 Granular Shoulder, Type B
8 2123- t 00100 Earth Shoulder Finishing
9 2 t 23-100200 Earth Shoulder, Construction
10 2301-132260 Standard or slip - Form Portland Cement Concrete Pavement,
Class C, Class 2 Durability 260 mm
11 2303-042120 HMA (3M EASL) Intermediate, 12.5 mm
12 2353-043124 HMA (3M EASL) surf, 12.5 mm, Fric L-4
13 2303-246422 Asphalt Binder PG 64-22
14 2303-600000 Adjustment Of Fixture
15 2416-240525 Concrete Pipe Aprons 525 mm, Dia.
16 2416-240750 Concrete Pipe Aprons 750 mm Dia.
17 2416-320750 Pipe Aprons Guard (RF-26) 750 mrn
18 2502-300193 Su drain Outlet, R.F - 19C
19 2502-250100 Longitude Subdraln (Shoulder) t00 mm
20 2503-120525 Concrete 75D Storm Sewer pipe 525mm. Dia.
21 2503-120750 Concrete 75D Storm Sewer pipe 750 mm Dia.
22 2503-140375 Concrete 100D) Storm Sewer pipe 375 mm Dia.
23 2503-140450 Concrete 100D) Storm Sewer pipe 450 mm Dia.
24 2503-140525 Concrete 100D) Storm Sewer p~pe 525mm Dia.
25 2503-400500 Storm Sewer Utility Access RA-50
26 2507-001100 Revetment Class A
27 2510-001000 Removal of Pavement
28 2511-100000 Removal of Sidewalk
29 2511-200100 Portland Cement Concrete Sidewalk 100mm
30 2515-000100 Removal of Paved Driveway
31 2515-100150 Portland Cement Concrete Driveway 150 mm
32 2516-101000 Remove retaining Walls and Steps
33 2527-1010112 Painted Pavement Marking, Waterborne
34 2527-104010 Painted Symbols & Legend, Waterborne
35 2535-200440 Modular Block Retaining Wall
36 2598-190050 Relocate Water Service Stop Boxes
37 2599-999901 Watermain 304.8mrn DIP, Push on Joint w/Polywrap, Class 52
38 2599-999901 Watermaln 203.2mm, Push on Joint w/Polywrap, Class 52
UNIT QUANTITY
Unit 98.9
M3 17686
MG 6670
M3 1178
MG 318
M2 3005
MG 68
M 1918
M 322.22
M2 11992
MG 374
MG 666
MG 34
Each 14
Each 1
Each t
Each 1
Each 38
M 2375
M 7.6
M I4.3
M 677.3
M 271.5
M 75.5
Each 1
M2 60
M2 6334
M2 53
M2 2126
M2 1075
M2 641
M3 6
M 2839
Each 16
M2 30
Each 3
M 118
M' 4
39 2599-999901 Watermain t52.4mm DIP, Push on Joint w/Polywrap, Class 52
40 2599-999915 Fitting 304.8mm x 304.8mm x 304.8mm Anchor Tee
41 2599-999915 Storm Sewer, Intake 101-B
42 2599-999915 Water Valve Box Adjusrment, Repair and Clean
43 2599-999915 Water Valve Box, (Street) Replace Upper Sections and Lids
44 2599-999915 Hydrants MJ
45 2599-999915 Bend 152.4mm (90 Deg.) MJ
46 2599-999915 Fitting 304.8mm x 304.8mm x 203.2mm Anchor Tee
47 2599-999915 Mega Lug 304.8mm
48 2599-999915 Mega Lug 203.2mm
49 2599-999915 Pipe Aprons Guard (RF-26) 525mm
50 2599-999915 Valve, Gate 152.4mm RS "0" Ring MJ
51 2599-999915 Valve, Gate 203-.2rran RS "0" Ring MJ
52 2599-999915 Valve, Gate 304.8rfim RS "0" Ring MJ
53 2599-999915
54 2599-999915
55 2601-101200
56 2601-104200
57 2601-106000
58 2601-109010
59 2602-000020
Sleeve #441,203.2mm MJ
Sleeve g441, 304.8mm MJ
Seeding, Fertilizing (Urban)
Mulching
Sodding
Watering
Silt Fence
M 20
Each t
Each 30
Each 10
Each 10
Each 4
Each 1
Each 1
Each 7
Each 4
Each 1
Each 3
Each 1
Each 7
Each 1
Each 9
Ha 0.3
Ha 0.3
M2 6022
KL 2640
M 420
Estimated Total (100% CITY)