Loading...
Westside Water System Improvements - Construction Inspection Contract Award Copyrighted May 15, 2017 City of Dubuque Action Items # 6. ITEM TITLE: Westside Water System Improvements - Construction Inspection Contract Award SUMMARY: City Manager recommending authorization to enter into an agreement with IIW, P.C. to perform construction administration and inspection services associated with the water main extension to the former Central Iowa Water Association's (CIWA)Vernon Water and Barrington Lakes water systems. SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Approve ATTACHMENTS: Description Type Westside Water System Improw:ments Construction City Manager Memo Inspection of Water Main Extension-MVM Memo Staff Memo Staff Memo Cost Breakdown Supporting Documentation THE CITY OF Dubuque DUB TENWinrkaCky 1111. Masterpiece on the Mississippi 2007.2012.2013 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Westside Water System Improvements English Mill Pumping Station and Water Main Extension to Vernon and Barrington Lakes SRF Project 2017 — Construction Inspection of Water Main Extension DATE: May 11, 2017 Water Department Manager Denise Ihrig recommends City Council authorization to enter into an agreement with IIW, P.C. to perform construction administration and inspection services associated with the water main extension to the former Central Iowa Water Association's (CIWA) Vernon Water and Barrington Lakes water systems for a contract amount of$103,400. IIW, P.C. is the design engineering firm assisting the City with planning, design, and permitting of the West Side Water System Improvements. I concur with the recommendation and respectfully request Mayor and City Council approval. Mic ael C. Van Milligen MCVM:jh Attachment cc: Crenna Brumwell, City Attorney Cindy Steinhauser, Assistant City Manager Teri Goodmann, Assistant City Manager THE CITY OF Dubuque AII11-America CiI.ty UB E1 Masterpiece on the Mississippi 2007.2012.2013 TO: Michael C. Van Milligen, City Manager FROM: Denise Ihrig, Water Department Manager SUBJECT: Westside Water System Improvements English Mill Pumping Station and Water Main Extension to Vernon and Barrington Lakes SRF Project 2017 - Construction Inspection of Water Main Extension DATE: May 10, 2017 INTRODUCTION The purpose of this memorandum is to request your review and authorization to enter into an agreement with IIW, P.0 of Dubuque, Iowa to perform construction administration and inspection services. The services are associated with Water Main Extension to the former Central Iowa Water Association's (CIWA) Vernon Water and Barrington Lakes water systems. IIW, P.0 is the design engineering firm assisting the City with planning, design, and permitting of the West Side Water System Improvements. BACKGROUND In 2016, following successful negotiations between CIWA and the City of Dubuque, the City retained IIW to perform engineering services in preparation for obtaining favorable State Revolving Fund (SRF) loan monies for the purchase of the Vernon and Barrington Lakes water systems. In addition to the system purchases, the loan includes, planning, design, and construction of water system improvements to connect these areas to the City of Dubuque's water supply. In October 2016, the City entered in a professional services contract with IIW in the amount of$25,000 to complete a preliminary engineering report, an Iowa SRF Intended Use Plan application, and contracted services for environmental assessment services thereby greatly increasing the City's ability to obtain funds to complete design and construction of the improvements in 2017. In January 2017, the City approved a contract for design services and partial construction engineering inspection services with IIW in an amount of $226,700. Of which, $186,700 was for design services associated with three contracts; Contract A: English Mill Road and North Cascade Road Water Main Extension to Highway 20, Contract B: English Mill Pumping Station and Contract C: Highway 20 Water Main Extension to Barrington Lakes, commonly referred to as the Westside Water System Improvements Project; and $40,000 was for construction engineering services associated with the English Mill Road Pumping Station. Under the current contract, IIW has completed, bid and assisted the City with award of the English Mill Pumping Station and English Mill Road and North Cascade Road Water Main Extension to Vernon and Barrington Lakes (Contracts A and B), with a third and final Contract C ready for bid within the upcoming month following easement procurement. IIW is cognizant of the City's firm deadline with the Department of Natural Resources (DNR) to connect Barrington Lakes and the Vernon Water systems to the City's water supply and has successfully worked with the City and the DNR to keep the projects moving forward toward the target deadline date of December 31�`. DISCUSSION When design service approval was presented to the Council in January, construction engineering services were to be shared between IIW, P.C. and City Engineering. Due to time sensitive project workload and staff availability within the engineering department, I am requesting the City look to IIW for assistance with construction inspection and administration for the water main extension projects. IIW's cost proposal for design of the Westside Water System Improvements Contracts A, B, and C included a cost proposal for Construction Engineering Services in the amount of$143,400.00. Of which, $40,000 was awarded for pumping station inspection services. The fees associated with construction inspection and administration of the water main improvements under contracts B and C is $103,400.00. A summary of the construction inspection services that IIW will provide are as follows: • Provide deliverables including but not limited to, construction meeting minutes, submittals, contract documentation, payment requests, project certification, and construction record drawings. • Conduct preconstruction meetings • Provide water main staking layout for the contractor to use • Ensure adherence to the City's standards for water main installation by providing onsite inspection services • Review all submittals, brochures, samples, and test results provided by the contractor for compliance with the contract documents • Assist the City with preparation and negotiation of change orders • Provide the City with contract progress reports and attend meetings as necessary IIW has worked closely with the City and the Iowa DNR to ensure all deadlines were met. This is due in part not only to their commitment to working for and in the community as a local professional engineering firm, but also to their commitment to the project since 2013. BUDGET AND SCHEDULE The Westside Water System Improvements: English Mill Pump Station and associated water main improvements identified in the Intended Use Plan as submitted to the Iowa DNR SRF program in December 2016 included reimbursement of engineering planning and design fees. The Intended Use Plan reflects planning and design engineering fees of$355,100. Should the City be in agreement to enter into a contract with IIW to fulfill the remainder of the proposal and provide construction engineering (staking, inspection, and administration) services, the contract amount will increase to $355,100.00 as presented herein and is eligible for reimbursement. The budget summary of the work currently being performed by IIW on the Westside Water System Improvements is as follows: Date Authorized Contract Services Authorized Contract Amount October 2016 Iowa SRF and City coordination and submittal of the $25,000.00 Preliminary Engineering Report and Intended Use Plan Subtotal $25,000.00 January 2017 Design of Westside Water Improvements, Contracts $186,700.00 A, B, and C January 2017 Construction Engineering Services: English Mill $40,000.00 Pumping Station Only Subtotal $226,700.00 Total Authorized Contract Services $251,700.00 The requested increase to the contract for water main construction engineering services as described above will add $103,400.00 to the Total Authorized Contract Services of$251,700.00 totaling $355,100.00, as presented below. Requested Contract Requested Contract Services Amount May 2017 Construction Engineering Services: Contract A: $103,400.00 English Mill Road and North Cascade Road Water Main Extension to Highway 20, and Contract C: Highway 20 Water Main Extension to Barrington Lakes Subtotal $103,400.00 Total Authorized Contract Services $251,700.00 Total Authorized & Requested Contract Services $355,100.00 The attached cost breakdown proposal from IIW reflects these total design fees including construction engineering services. REQUESTED ACTION I respectfully request your authorization to enter into an agreement with IIW, P.0 of Dubuque, Iowa to complete construction engineering inspection services associated with the Westside Water System Improvements to Vernon and Barrington Lakes water systems for a contract amount of $103,400.00. cc: Jenny Larson, Budget Director Alexis Steger, Budget Analyst Jean Nachtman, Finance Director Gus Psihoyos, City Engineer Section A - SRF PER, Coordination with IDNR and City Section B - Preliminary Design Section C - Final Design Total for Design English Mill English Mill Road North Cascade Pump Station Water Main Road Water Main $ 11,800.00 $ 17,700.00 $ 29,500.00 Section D - Bidding and Contract Award $ 1 Section E - Construction Basic 1 $ 14,900.00 Section F - Construction Observation 1 $ 25,500.00 Total for Construction 1 $ 40,400.00 $ 8,500.00 $ $ 7,500.00 $ $ 16,000.00 $ $ 14,400.00 $ 18,900.00 $ 33,300.00 Subtotals 25,000.00 $ 25,000.00 43,500.00 $ 63,800.00 16,300.00 $ 41,500.00 59,800.00 $105,300.00 10,500.00 $ 10,500.00 $ 12,100.00 $ 41,400.00 $ 18,800.00 $ 63,200.00 $ 30,900.00 $104,600.00 Subtotal $245,400.00 Highway 20 Water Main $ 47,200.00 $ 17,700.00 $ 64,900.00 $ 6,000.00 1 1 $ 13,500.00 1 1 $ 25,300.00 1 1 $ 38,800.00 1 Highway $109,700.00 20 Total ' Totals $ 25,000.00 1 $ 111,000.00 1 $ 59,200.001 $ 170,200.00 1 $ 16,500.00 $ 54,900.00 $ 88,500.00 $ 143,400.00 Project $ 355,100.00 Total 1