BP Pipelines, Inc., /Southwest Arterial Project Utility Relocation Reimbursement Agreement Copyrighted
July 17, 2017
City of Dubuque Consent Items # 20.
ITEM TITLE: BP Pipelines, Inc., /Southwest Arterial Project Utility
Relocation Reimbursement Agreement
SUMMARY: City Manager recommending approval and authorization for
the City Manager to execute a Phase I I — Construction
Utility Relocation Reimbursement Agreement with BP
Pipelines (North America) Inc. for the relocation of a
petroleum distribution pipeline impacted by the Southwest
Arterial and the future East Grading Phase I I Project.
RESOLUTION Approving a Phase I I Construction Utility
Relocation Reimbursement Agreement with BP Pipelines
(North America) Inc. for the relocation of a petroleum
distribution pipeline associated with the East Grading
Project and the continued development and advancement
of the Southwest Arterial Project
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s)
ATTACHMENTS:
Description Type
BP Pipeline Utility Relocation Reimbursement City Manager Memo
Agreement-MVM Memo
Staff Memo Staff Memo
Resolution Resolutions
BP Reimbursement Agreement Supporting Documentation
Area Map Supporting Documentation
THE COF Dubuque
DtUB
E All-America
City
Masterpiece on the Mississippi 1 1 1 1"
2009•2012•2013•2019
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Southwest Arterial Project
BP Pipeline Utility Relocation Reimbursement Agreement – Phase 2 Construct
Iowa DOT Project No. HDP-2100 (667)-71-31
DATE: July 11, 2017
Assistant City Engineer Bob Schiesl recommends City Council approval and
authorization for the City Manager to execute a Phase II – Construction Utility
Relocation Reimbursement Agreement with BP Pipelines (North America) Inc. for the
relocation of a petroleum distribution pipeline impacted by the Southwest Arterial and
the future East Grading Phase II Project.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
IVZSIA-�,
Mic ael C. Van Milligen
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Teri Goodmann, Assistant City Manager
Robert Schiesl, Assistant City Engineer
Gus Psihoyos, City Engineer
THE CITY OF Dubuque
ik
UBE All-America City
1 1.I
Masterpiece on the Mississippi III
2007•2012•2013•2017
TO: Michael C. Van Milligen, City Manager
Gus Psihoyos, City Engineer
FROM: Robert Schiesl, Assistant City Engineer
SUBJECT: Southwest Arterial Project
BP Pipeline Utility Relocation Reimbursement Agreement - Phase 2 Construct
Iowa DOT Project No. HDP-2100 (667)--71-31
DATE: July 11, 2017
INTRODUCTION
The purpose of this memorandum is to seek City Council approval and authorize the
City Manager to execute a Phase II - Construction Utility Relocation Reimbursement
Agreement with BP Pipelines (North America) Inc. (BP) for the relocation of a petroleum
distribution pipeline impacted by the Southwest Arterial and the future East Grading
Phase II project.
BACKGROUND
Through the continued collaborative partnership between the Iowa DOT staff and the
City, the Memorandum of Understanding (MOU), was signed on August 9, 2013, and
the Transfer of Roadway Jurisdiction (TOJ), was signed on November 7, 2016.
Following the execution of the MOU and TOJ, the City is continuing as the lead agency
for the multiple project development phases for completing the Southwest Arterial and is
responsible for completing the following improvement projects:
Project Description Status
Final Engineering Design Underway
Right-of-Way Property Acquisition Completed
BHE Gas Pipeline Utility Relocation Completed
BP Gas Pipeline Utility Relocation Summer/ Fall 2017
North Cascade Road Reconstruction Completed
English Mill Road Reconstruction Punch List Items
Military Road Reconstruction Underway
As outlined in the MOU and TOJ, the City is responsible for the relocation of impacted
utilities. Prior to beginning the East Grading Phase II project, the City needs to relocate
an existing in-service 10-inch petroleum distribution pipeline which is owned and
Service People Integrity Responsibility Innovation Teamwork
operated by BP. The BP pipeline is located on its own private easements upon land
acquired by the City for the Project.
Utility Relocation Reimbursement Agreement
Upon reviewing the Iowa Department of Transportation (Iowa DOT) Federal-aid
Participation in Utility Relocations, it has been determining the BP utility relocation is
eligible. However, due to the federal regulatory requirements, it was determined that a
more efficient way of completing the associated relocation work would be to separate
the work into two (2) phases.
On February 6, 2017, City Council authorized (Resolution No. 41-17) and entered into a
Phase I - Design Utility Relocation Reimbursement Agreement with BP. The Phase I -
Engineering Design is not eligible for federal-aid funding.
The Phase I - Engineering Design phase is nearing completion and the City is now able
to proceed with executing an agreement with BP for the Phase II - Utility Construction
Relocation. The Phase II construction relocation will be federal-aid eligible.
The development of the Utility Relocation Reimbursement Agreement has been a very
long collaborative effort between BP, the City and Iowa DOT staff, Bryan Bradley, State
Utility Engineer. The City utilized a State of Oklahoma standard federal aid agreement
template and made minor revisions and additions so that the agreement was applicable
to the City's specific project.
ELIGIBLE COSTS
Upon reviewing I.M. No. 3.650, Federal-aid Participation in Utility Relocations, and after
determining the utility relocation is eligible, the City believes that all associated activity
costs (e.g., materials, labor, equipment, and overhead, etc.) are eligible.
Engineering
BP will be using in-house staff resources to complete the following eligible work and
operational services:
a. Engineering and Administration Services for soliciting competitive bid proposals
for the procurement of materials required.
b. Purchase of eligible materials required to complete the relocation work.
c. Engineering and Administration Services for soliciting competitive bid proposals
from contractors to complete the relocation work.
d. Contract with the lowest responsible, responsive bidder for construction contract
labor to complete the relocation work.
e. Engineering, Administration and Inspection Services for the work performed at
the construction stages.
f. Engineering and Administration for the work performed at the final completion
and project close out stages.
The above eligible costs are summarized in the scope of work and estimate of probable
cost, shown as Exhibits B and C of the Relocation Reimbursement Agreement.
Service People Integrity Responsibility Innovation Teamwork
Right-of-Way
BP owns and operates the impacted 10-inch petroleum distribution pipeline located on
its own private easement through and upon property acquired by the City for the project,
Parcels 151a, 152, and 161 . As part of relocation agreement, the City will provide a
Grant of Permanent Easement for BP to operate, access, repair and maintain the
pipeline utility within the established future highway right-of-way. In return, BP has
agreed to relinquish all rights granted to BP for those portions of existing pipeline
easements to be vacated after relocation and to subordinate certain specified rights of
its easements within the land acquired by the City for said future highway right-of-way.
The associated costs for securing the replacement relocation easements are not
included as part of this agreement since the acquisition costs have already been
incurred.
Construction
Per the terms and conditions of the Utility Relocation Reimbursement Agreement, BP
will solicit competitive bids from BP's pre-approved Master Service Agreement for
outsource construction contractors to complete the relocation or adjustment work. BP
will contract with the lowest responsible, responsive bidder for construction contract
labor and equipment to complete the relocation or adjustment work.
FUNDING SUMMARY
The estimate of probable cost for the utility relocation work is as follows:
Description Estimated Cost
Material & Equipment Cost $ 279,000
Construction Contract Labor Cost 764,180
Consultant Services Cost 196,000
BP Staff Direct Costs 97,900
SUBTOTAL - UTILITY RELOCATION COST: $ 1,337,080
BP Indirect and Overhead Cost (15%) 185,877
TOTAL - UTILITY RELOCATION COST: $ 1,522,957
* BP Overhead Cost = 15% x (Material Costs + Contract Labor + Consultant Costs)
The anticipated project funding is summarized as follows:
Fund Description Fund Amount
Federal SAFETEA-LU Funding (80%) $ 358,366
DMATS STP Funding (80%) 860,000
Local Funding - City (10%) 152,296
Local Funding - County (10%) 152,295
Total Project Funding $ 1,522,957
Service People Integrity Responsibility Innovation Teamwork
RECOMMENDATION
I recommend that the City Council authorize the City Manager to execute a Phase II —
Construction Utility Relocation Reimbursement Agreement with BP Pipelines (North
America) Inc. (BP) for the relocation of a petroleum distribution pipeline impacted by the
Southwest Arterial and the future East Grading Phase 11 project.
ACTION TO BE TAKEN
The City Council is requested to authorize the City Manager to execute a Phase 11 —
Construction Utility Relocation Reimbursement Agreement with BP Pipelines (North
America) Inc. (BP) for the relocation of a petroleum distribution pipeline impacted by the
Southwest Arterial and the future East Grading Phase 11 project through adoption of the
attached resolution.
Prepared by Robert Schiesl, Assistant City Engineer
cc: Jenny Larson, Budget Director
Ken Yanna, Kent Ellis, Roget Walton, Iowa DOT
Chandra Ravada, ECIA
F:\Projects\Southwest Arterial\Utility Coordination - Relocation\BP Pipeline\Council and Staff Documents
Service People Integrity Responsibility Innovation Teamwork
gyp•
BP PIPELINE RELOCATION
:.3...... .....,•..........
Access
Road 'C' 11 # ayµ- Access
Knapp Jahn L : Road 'B'
••�..........•. lfil
t v .� : • d
" �� �•� � Reebr,El:zabelh
1508 p e_.� •
. 1; Valentine,Ronald L& Modene N \ \ • `t Bike
151 �� �/'�•• � .� _��
A �
r 1 008 152 \
/ plentlne,Ronald L& Modene - Kmv,VAlliam J. _
,, � • -
EPq
SBP PIPELINERW� �em
15 a01 161 O! 176 Ronoaay,
& Ja eM.
Valentine,Gary L. Tm
V i 175 Dennieni.C.
O& Susan D.
'?0
combed,
1 +• / p�
174 David L.
& Shirley A. � O
Y.; Lambed,
173 Michael D.
& Chds A. ,y a
tea. >>O
�o - Bike Trail --
Q
_ • � _ t � � t ;. fin
RESOLUTION NO. 259-17
RESOLUTION APPROVING A PHASE II CONSTRUCTION UTILITY RELOCATION
REIMBURSEMENT AGREEMENT WITH BP PIPELINES (NORTH AMERICA) INC. FOR THE
RELOCATION OF A PETROLEUM DISTRIBUTION PIPELINE ASSOCIATED WITH THE EAST
GRADING PROJECT AND THE CONTINUED DEVELOPMENT AND ADVANCEMENT OF THE
SOUTHWEST ARTERIAL PROJECT
Whereas, the City is proceeding with the proposed East Grading Project (hereafter Project) in
accordance with its plans and specifications, which the City has designed as part of the Southwest
Arterial Project; and
Whereas, prior to the City commencing work on the Project, the City needs to have an existing
in-service 10 -inch petroleum distribution pipeline relocated; and
Whereas, the 10 -inch petroleum distribution pipeline is owned and operated by the BP Pipelines
(North America) Inc. (hereafter BP) and located on its own easements upon land acquired by the
City for the Project shall be relocated in accordance with a Phase II — Construction Utility Relocation
Reimbursement Agreement (hereafter Agreement); and
Whereas, it has been determined that the utility relocation to be completed by BP shall be
separated into a Phase I - Engineering Design and a Phase II - Utility Construction Relocation; and
Whereas, on February 6, 2017, City Council authorized (Resolution No. 41-17) and entered into
a Phase I - Design Utility Relocation Reimbursement Agreement with BP; and
Whereas, the Phase I - Engineering Design phase is nearing completion and the City is now able
to proceed with executing an agreement with BP for the Phase II - Utility Construction Relocation;
and
Whereas, BP shall initially pay all costs to relocate and adjust its facilities as covered by the
Agreement; and
Whereas, upon reasonable satisfactory completion the City will pay BP for said eligible
reimbursement costs as covered by the Agreement.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE,
IOWA, THAT:
Section 1. That said Phase II - Construction Utility Relocation Reimbursement Agreement
between the City of Dubuque and BP Pipelines (North America) Inc. is hereby approved.
Section 2. That the City Manager be authorized and directed to execute three copies of said
Agreement between the City of Dubuque and BP Pipelines (North America) Inc. for the relocation of
the petroleum distribution pipeline associated with the Project and the continued development and
advancement of the Southwest Arterial Project.
Passed, approved and adopted this 17th day of July 2017.
Attest:
Kevin . i-irnstahl, ity Clerk
(°1/4"
Roy D. Buol, Mayor
Page 1 of 7
CITY OF DUBUQUE
AGENCY UTILITY RELOCATION AGREEMENT
PHASE 2 - EXECUTE CONSTRUCTION RELOCATION
Agreement No.: U-BP-PP05-2017-667-71-31
Project: Southwest Arterial (U.S. 52)
Project No.: HDP‐2100 (667)‐‐71‐31
County: Dubuque County, Iowa
Location: Sec. 03, 10, & 11 -88N-2E
Knepper Lane Relocation - SW Arterial PP05
BP Reference: 4000 - 766, 765, 764, 763, & 762 TPR: 6486
Work Description: Phase 2 – Execute construction relocation; including materials, labor, and
equipment to relocate or adjust existing in-service 10” pipeline facilities.
THIS AGREEMENT, made and entered into this 8th day of, August 2017 (“Effective
Date”), by and between BP Pipelines (North America) Inc., a Maine corporation, whose address
is 30 South Wacker, 10S-322, Chicago, Illinois 60606 (hereinafter referred to as "Company”)
and City of Dubuque, whose address is 50 W. 13th Street, Dubuque, Iowa 52001 (hereinafter
referred to as "CITY”).
WITNESS TO THAT
WHEREAS, the City proposed to proceed with the East Grading Project (NHSX-032-1 (50)--3H-
31) in accordance with its plans and specifications, which the City has designed as part of the
Southwest Arterial (U.S. 52) Project (hereafter Project), and;
WHEREAS, prior to the City commencing work on the Project, the City needs to have the existing
in-service 10” Whiting-Dubuque distribution pipeline relocated and adjusted as generally shown
and depicted on the attached Exhibit “A”), and;
WHEREAS, the 10” Whiting-Dubuque distribution pipeline is owned and operated by the
Company and located on its own easements upon land that has been acquired by the City for
constructing the proposed Project, and;
WHEREAS, the proposed Project and such improvements will necessitate the relocation and
adjustment of the Whiting-Dubuque facilities by Company (scope of work is further described in
the attached Exhibit “B”), and;
WHEREAS, the total estimate of probable eligible cost ($1,522,957) required by the Project for
the relocation and adjustment of Company facilities and estimated City share of such costs are
shown on the itemized estimate of probable cost included in Exhibit "C", and;
WHEREAS, it is understood that said Project is to be financed in part from funds appropriated
by the United States and expended under its regulations, that acceptance of work and procedure
in general are subject to Federal Laws, Rules, Regulations, Orders, and Approvals applying to
it as a Federal Project, and that costs for items entering into the improvement are reimbursable
to the City in such amounts and forms as are proper and eligible for payment from Federal
Funds. Reference is made to U.S. Department of Transportation, Code of Federal Regulations,
Title 23, Parts 645A, 645B and 635.410, and the Iowa Department of Transportation Utility
Accommodation Policy, and;
Southwest Arterial Project
Agency Utility Relocation Agreement
Page 2 of 7
WHEREAS, the City reserves the right to cancel this Agreement at any time prior to the
beginning of the relocation or adjustment of the facilities of this Company, and;
WHEREAS, the City agrees to pay the Company for the proportionate share of the actual cost
incurred related to the Phase 2 - execute construction relocation scope of work, if for any reason
the City cancels this Agreement.
NOW, THEREFORE, in consideration of the mutual covenants herein contained, the Company
agrees:
1. To prepare a detailed estimate of the cost of work to be performed in accordance with the
Iowa Department of Transportation Utility Accommodation Policy, and such estimate of cost
must be attached and be a part of this Agreement. The estimate will include: (1) The
accounting system to be used in computing the relocation costs; (2) Credit for Expired
Service Life setting forth therein the conditions on which such credit was determined or
complete justification if the credit is not applicable; and; (3) Whether equipment costs are
developed from experience records.
2. To include the costs for backfill and compaction of any trenches or holes within the right-of-
way limits in the estimate of costs. The backfill will be placed and compacted to a density as
directed by the City Engineer, but will not be compacted to less than that of the adjacent soil.
3. Any and all existing fencing that may require alteration during the utility relocation process
shall be restored to its original condition during and after the time of the utility relocation or
adjustment. It is the responsibility of the Company to ensure that the integrity of the fencing
is not compromised at any time to an extent in which it prevents the fencing from performing
its intended purpose.
4. To prepare drawings showing the present, temporary and proposed location of its facilities
with reference to the centerline of survey and/or the new or existing right-of-way lines using
highway stationing in both plan and profile. Delineate details, including date of installation,
class, and type of present facility. To comply with all applicable laws and regulations
necessary to meet the City’s requirements for pollution prevention, including discharges from
storm water runoff from the utility relocation or adjustment. Company further agrees to secure
a National Pollutant Discharge Elimination System (NPDES) Permit from the City, when
required. It is agreed that the project plans and specifications, required schedules for
accomplishing the temporary and permanent erosion control work, the storm water pollution
prevention plans and the appropriate location map contained in the plans constitute the
Storm Water Management Plan for the project previously described in the document.
Company agrees to have daily operational control of those activities, at the site, necessary
to ensure compliance with plan requirements and permit conditions. Company agrees to file
the Notice of Intent (NOI), when required, for a general construction NPDES Permit from the
City, which authorizes discharges of storm water associated with construction activity from
the project site identified in this document. Such drawings will be attached to and become a
part of this agreement.
5. To begin the process of relocation or adjustment of the facilities as shown on the plans and
covered by this Agreement within a reasonable time, depending on the availability of material
and work forces, but the actual time must not exceed thirty (30) days after receipt of notice
from the City to do so, and in no event, proceed with any relocation or adjustment work until
Southwest Arterial Project
Agency Utility Relocation Agreement
Page 3 of 7
such notice is received. To inform the City Engineer of: (1) The proposed starting date, prior
to commencing work, and continually maintaining liaison with his/her office for the duration
of the physical relocation; (2) The materials to be disposed of by scrapping, or sale, and to
inform him/her of a time and place for his/her inspection thereof; (3) The date work is
completed.
6. Compliance with the Buy America Requirements:
A. In accordance with the BUY AMERICA requirements of the Federal Regulations (23
U.S.C. 313 and 23 CFR 635.410) all manufacturing processes, including the application
of coating, for predominantly steel and iron products furnished for permanent
incorporation into the work on this project shall occur in the United States.
A product is considered to be manufactured "predominantly of steel and iron" if the
product is at least 90% steel or iron content (measured by weight) when it is delivered to
the job site for installation. For clarification, a job site includes the sites where precast
concrete projects are manufactured.
"All manufacturing processes" are defined as any process required to change the raw
ore or scrap metal into the finished steel or iron project (smelting, rolling, extruding,
bending, etc.).
"Coating" is defined as any process which protects or enhances the value of the steel or
iron produce to which the coating is applied (epoxy, galvanizing, painting, etc.).
Products of steel include, but are not limited to, such products as steel pipe, steel
encasement, reinforced concrete pipe, steel electrical poles, conductor wire, etc.
Products of iron include, but are not limited to, such products as ductile iron pipe. The
coating material is not limited to this clause, only the application process.
The following materials are exempt, unless processed or refined to include substantial
amounts of steel or iron material, and may be used regardless of source in the domestic
manufacturing process for steel or iron material:
Raw Materials (iron ore or alloys)
Scrap
Pig Iron
Processed, pelletized, and reduced iron ore material
Aluminum
Brass
Copper
For recycled steel, only the manufacturing processes to produce steel products must
occur domestically beginning at the point where the recycled steel is melted.
B. Minimal Use Request - The federal regulations do not prevent the use of miscellaneous
steel or iron components, subcomponents and hardware necessary to encase, assemble
and construct certain highway products and manufactured products that are not
predominately steel or iron if the cost of such materials used does not exceed one tenth
of one percent (0.1%) of the total contract price or $2,500.00, whichever is greater. The
value of any foreign material to be used includes the cost of the material as well as any
shipping and taxes.
Southwest Arterial Project
Agency Utility Relocation Agreement
Page 4 of 7
The Company must submit a written request to the City Engineer which includes the
origin and value of any foreign material to be used. This request must be submitted prior
to the work being performed.
C. Compliance with Buy American Requirements - The Company's responsibility for
meeting the Buy America requirements are as follows:
a) Before any work begins that incorporates steel or iron products into the project, the
Company shall submit a project specific certification letter stating that all
manufacturing processes involved with the production of these projects will occur in
the United States, along with project specific certification letters from each
subcontractor and supplier of steel or iron products for the project.
b) For each steel or iron product, the Company will be responsible for providing to the
City all documentation required to verify that each product complies with Buy
America. The Company must also provide a completed "Certificate of Materials
Origin" form for each steel or iron product incorporated into the project.
c) The "Certificate of Materials Origin" form is attached to this agreement as Exhibit
“D”. Records shall be maintained by the Company and the City. The certification shall
include a signed mill test report and/or a signed certification by EACH supplier,
distributor, fabricator, or manufacturer that has handled the steel or iron product
affirming that every process, including the application of the coating, performed on
the steel or iron project has been carried out in the United States in accordance with
the requirements of the corresponding category listed below. In most instances,
determination of compliance with Buy America requirements should be achieved prior
to incorporating the project into the work. If not, the City Engineer will be responsible
for withholding payment for this work until compliance has been determined.
d) The City shall retain records of the Buy America certifications provided by the
Company as part of its Federal-aid project file.
e) The lack of these certifications will be justification for rejection of the steel and/or iron
product or nonpayment of the work.
7. That no contract with any individual will be entered into without meeting the requirements of
the Iowa Department of Transportation Utility Accommodation Policy.
That contract work for technical services, professional services or other labor classifications
involved in the rearrangement of the facility proposed under this Agreement will be supported
by a statement to the effect that, “The Company is not adequately staffed or equipped to
perform such work with its own forces”. Proper approval must be obtained in accordance
with the Iowa Department of Transportation Utility Accommodation Policy prior to
executing a contract with any outside firm or continuing contractor.
8. The City desires to construct a new highway Project on part of the land subject to the
easement of the Company and further desires the Company to subordinate its easement
rights to the City and the Company agrees execute and deliver to the City, on forms supplied
by the City, a Partial Disclaimer of Interest in Realty as shown on the attached Exhibits “E,
E1, E2, and E3”, for the vacating and relinquishment of all easement rights for those
segments located within rights-of-way acquired by the City for this Project.
Southwest Arterial Project
Agency Utility Relocation Agreement
Page 5 of 7
9. The City shall deliver to the Company, an executed Grant of Permanent Easement
agreement as shown on the attached Exhibits “F and F1”, to allow for the Company’s
perpetual use of public highway right-of-way to occupy, rights to operate, access, repair and
maintain facilities within the established public highway right-of-way.
10. The City shall deliver to the Company, an executed Subordinate of Easement Agreement as
shown on the attached Exhibits “G, G1, and G2”, to allow for the Company’s perpetual use
of public highway right-of-way to occupy, rights to operate, access, repair and maintain
facilities within the established public highway right-of-way.
11. Billing and Final Payment
A. The Company may elect to provide the City with a progress invoice at various stages of
the utility relocation and adjustment effort (progress payments) for materials or contract
labor expenses incurred prior to the date of the invoice.
B. If more than one progress payment is requested, upon substantial completion, the total
of all progress payments will not exceed 95 % of the actual costs of work completed.
C. Upon satisfactory completion of the work, City and Company hereby agree to a 5 %
retainage until an audit of actual expenditure costs incurred is completed, a Certificate of
Final Completion is issued, and a Final Payment Invoice is received.
D. Company shall submit to the City, within six (6) months after satisfactory completion of
relocation or adjustment of their facilities under this Agreement, a Final Payment Invoice,
with a certified statement of final costs with supporting documentation as reasonably
requested by City in accordance with the provisions of this Agreement.
E. Upon receipt of a Certification of Final Completion and all requested supporting final cost
documentation, the City will request that an external audit of final costs be performed by
the Iowa Department of Transportation. The audit will be completed within sixty (60)
calendar days and the City shall issue payment to the Company for the authorized Final
Invoice.
F. Company’s accounts, and the accounts and records of any contractor or sub-contractor
involved in carrying out the work, shall be kept in such manner that they may be readily
audited and actual costs determined, and such accounts shall be available for audit by
auditors of or by the City for a period of eighteen (18) months from date final payment has
been received by Company.
In consideration of the faithful performance by the Company of the foregoing, the City agrees:
To reimburse the Company for the actual costs of work completed, prorated on the basis of
the following percentage or for the lump sum as proposed:
Upon Substantial Completion
Company shall be reimbursed 95 % of Actual Expenditure Costs Incurred
Upon Certificate of Final Completion
Company shall be reimbursed the 5 % retainage amount as Final Payment
It is understood this Agreement does not change the rights or obligations of the Company as
they exist in accordance with present State Law.
12. Signatures
Southwest Arterial Project
Agency Utility Relocation Agreement
IN WITNESS WHEREOF the Parties hereto have caused the agreement to be executed by their duly authorized
officers on the dates below indicated.
INC. 5P1P'
Executed by the Company this _Lf_._=fl_f"l __ day of Aqgu @t '2017.
State of fl\ 1 0016
County of [W K
I
ss.
(Print Name)
(Print Title)
Executed by the City of Dubuque this ~ day of ~~ , 2017.
ss .
Page 6 of 7
CITY OF DUBUQUE
By __ ~,t~~==~~====---
(Signature)
Michael C. Van Milligen
(Print Name)
City Manager
(Print Title)
Southwest Arterial Project
Agency Utility Relocation Agreement
Executed by the Iowa Department of Transportation this ~~ day of A V) (IS f-. 2017 .
IOWA DEPARTMENT OF TRANSPORTATION
Accepted for FHWA Authorization **
By ___,.~=+-.=....:...__c! -=--=Yt;=-----7 (Signature)
Yev.rL. EIJ~:s
(Print Name)
(Print Title)
**The Iowa DOT is not a party to this agreement. However, by signing this agreement, the Iowa DOT is indicating
the work proposed under this Agreement is acceptable for FHWA authorization of Federal funds .
Page 7 of 7
REVISION DESCRIPTIONNO.
REV.DATE
US Pipelines & Logistics
PREPARED BY:
x
x
EXHIBIT A
NOT FOR
CONSTRUCTION
EXHIBIT B
AGENCY UTILITY RELOCATION AGREEMENT
PHASE 2 - EXECUTE CONSTRUCTION RELOCATION
SCOPE OF WORK
The scope of work to be performed by the Company shall include all phases of administration and
construction for the relocation or adjustment of facilities impacted by the Project and shall be completed in
accordance with generally accepted standards of practice. The Company is not limited or constrained to the
scope of work as outlined and the final scope of work may be adjusted to remove items not required or to
include items not listed, if it is determined that additional task items are needed to complete the relocation
and adjustment of said facilities.
The contemplated scope of work and operations to be completed by the Company may consist of the
following:
1. Company services for soliciting competitive bid proposals from the Company’s pre-approved Master
Service Agreement vendors for the procurement of materials required.
2. Purchase of materials from the Company’s pre-approved Master Service Agreement vendor(s) to
complete the relocation or adjustment work.
3. Company services for soliciting competitive bid proposals from the Company’s pre-approved Master
Service Agreement for outsource construction contractors to complete the relocation or adjustment
work.
4. Contract with the lowest responsible, responsive bidder for construction contract labor and equipment
to complete the relocation or adjustment work.
5. Consultant engineering, construction management and inspection services for the work performed at
the construction stages.
6. Company services for the work performed at the final completion and project close out stages.
7. Upon execution of the Phase 2 - Execute Construction Relocation Agreement, the Company will
proceed with reasonable promptness to solicit competitive bids for the procurement of materials and
construction contract labor covered by this agreement. The Company shall provide the City with
documentation of the bid procurement process and an itemized tabulation of the bids to the City for
review. After receiving bids, the Company will provide the City a contract award proposal for the
procurement of materials and contract labor. After review and concurrence of the contract award
proposal, the City will provide written authorization to proceed with work.
8. Upon receipt of written notice to proceed from the City, the Company shall relocate and adjust its
facilities in a reasonably satisfactory manner that will not interfere with the Project. The Company shall
notify the City Engineer of the date on which Company work begins in the project area and of the
anticipated completion date. The Company will also inform the City when each phase of the work is
completed. If a change in schedule is warranted, it shall be approved by the City Engineer.
9. The Company shall initially pay all costs to relocate and adjust its facilities as covered by this
agreement. Upon reasonable satisfactory progress as the work is underway, the Company may elect
to provide an itemized monthly progress payment for expenditures incurred.
10. If there are changes to the scope of work approved by the agreement (e.g., extra work, significant
changes to the plans, specifications, or estimates), an amendment to the agreement, written change,
or extra work order must be approved by the City. Absent such documentation, Federal funds may
not participate in the additional costs associated with such changes.
11. If there are unforeseen site conditions encountered during the utility relocation and adjustment work
(e.g., rock, high ground water conditions, unsuitable soils, pipe wrap or coating materials) which may
cause changes to the cost of the awarded contract, the Company shall promptly notify the City of such
conditions and a written change order or extra work order must be approved by the City. Absent such
documentation, Federal funds may not participate in the additional costs associated with such
changes.
12. The City shall allow the Company and its contractor(s) to be a co-permitee under the City’s National
Pollutant Discharge Elimination System (NPDES) Permit for the project.
13. The Company shall be responsible for providing construction staking for both horizontal and vertical
alignment for the utility relocation and adjustment work.
14. The Company shall be responsible for providing as-built construction drawing for both horizontal and
vertical alignment for the utility relocation and adjustment work.
15. The Company shall be responsible for the removal and disposal of the vacated and retired segments
of 10" pipe located within the limits of the right-of-way corridor. Company shall comply with all federal,
state, and local environmental laws and regulations concerning the removal and disposal of the
vacated and retired segments of pipe. Company will hold harmless City for any damages caused by
Company's negligence or willful misconduct in the removal or disposal of the vacated and retired
segments of pipe.
Southwest Arterial Project
Construction Project No. HDP‐2100(667)‐‐71‐31
Relocation of 10" Whiting-Dubuque Distribution Pipeline
200 Materials Equipment Materials
Construction
Labor
Consultant
Services BP Staff Amount
210-220 Civil / Concrete 93,180$ 93,180$
230 Structural Steel
260 Piping 82,000$ 421,000$ 503,000$
270 Electrical
280 Instrumentation
290 Protective Coatings, Insulation 4,000$ 3,000$ 7,000$
240 Buildings & Architectural
299 Other Bulk Materials
400 Field Indirect & Overheads Equipment Materials Construction Consultant BP Amount
410 Const Mgmt: BP CM, 3rd Party Oversight 70,000$ 49,000$ 119,000$
420 Construction Equipment
430-470 Mob‐Demob/Const Super/Temp Facs/Services 142,000$ 24,000$ 166,000$
490 Other Indirects 14,000$ 14,000$
500 Contractor Engineering Services Equipment Materials Construction Consultant BP Amount
510‐520 Engineering, D&D 67,000$ 67,000$
530 Misc Engineering Services 6,000$ 4,000$ 10,000$
570 Inspection Services: QA / QC 6,000$ 6,000$
599 Other Engineering Services
600 Other Project Costs Equipment Materials Construction Consultant BP Amount
610 Permits 4,000$ 4,000$
620 Demoltion / Abandonment 219,000$ 219,000$
630 Environmental
680 Special Costs (Tax&Freight) 17,000$ 17,000$
699 Other Project Costs 20,000$ 20,000$
700 BP Costs Equipment Materials Construction Consultant BP Amount
710-750 Project Team, Controls, Procurmnt 67,000$ 67,000$
760 ROW Costs (Access, Restore, Buy)
770 Project Assurance/Benchmarking 3,900$ 3,900$
799 Other BP Costs
800 Start-up & Commissioning Equipment Materials Construction Consultant BP Amount
810-890 All Start‐Up & Commissioning 21,000$ 21,000$
Material & Equipment Cost 279,000$ *
Construction Contract Labor Cost 764,180$ *
Consultant Services Cost 196,000$ *
BP Staff Direct Costs 97,900$
SUBTOTAL ‐ UTILITY RELOCATION COST: 1,337,080$ 1,337,080$
BP Indirect and Overhead Cost (15%) 185,877$ *
TOTAL ‐ UTILITY RELOCATION COST: 1,522,957$
Line Item Description
210-220 Construction contract labor and equipment
260 Pipeline material costs and construction contract labor and equipment to install
290 Pipeline material costs and construction contract labor and equipment to install
410
430-470
490 Insurance costs for material
510‐520 Consultant services for engineering design support during construction, provide as‐built record drawings
530 Consultant services for construction surveying and as‐built survey costscosts. Material cost is for Hydrotest
570 Costs associated with weld testing and hydrotest verification by BP personnel and/or a 3rd party depending on availability
610 Permits required for pipeline relocation
620 Construction contract labor and equipment for the demoltion, removal, and abandonment of retired pipeline
680 Tax and freight costs for the procurement and delivery of materials
699 Equipment required at the 2‐tie in locations
710-750 BP internal project team direct costs associated with procurement, controls, and contracts
770
810-890 BP internal project team costs during the switch over and restart of the pipeline
Estimate of Probable Cost Summary
Consultant services for construction management and field observation / inspection services. Material cost for x‐ray and mag particle testing required
for all the welds. All welds will have to be 100% tested and inspected.
BP internal project team costs associated with benchmarking the project to ensure material, construction, surveying, and inspection costs are within
industry standards
EXHIBIT C
Mobilization: Contractor preconstruction expenses and the cost of preparatory work and operations setup (Equipment, staging, temporary facilities,
temporary power, security measures for staging area, construction office and equipment). Demobilization: Removing and transporting
equipment/material/personnel; site cleanup and restoration.
&(57,),&$7(2) 0$7(5,$/625,*,1
352-(&7180%(5 &2175$&7,'
,7(0'(6&5,37,21 %,',7(0180%(5
,192,&(180%(5 48$1,7<
'$7(5(&(,9(' %,//2)/$',1*180%(5
0$7(5,$/66285&(1$0($1'$''5(6672,1&/8'(($&+6833/,(5)$%5,$&$725$1'0$18)$&785(5,1&/8',1*
+($7%$7&+180%(5,)$9$,$/%/(
0$7(5,$/6'(6&5,37,21
'(6&5,37,212)0$7(5,$/62)81.12:125,*,125)25(,*10$7(5,$/6'(/,9(5('727+(352-(&7
7KLVFHUWLILFDWLRQLVPDGHIRUWKHSXUSRVHRIHVWDEOLVKLQJWKHPDWHULDOVDFFHSWDQFHXQGHUWKH%X\$PHULFD&HUWLILFDWLRQ&)5DQGWKH
&RQWUDFW6SHFLDO 3URYLVLRQV $OO LURQ DQG VWHHO PDQXIDFWXULQJ SURFHVVHV LQFOXGLQJ SURWHFWLYH FRDWLQJ IRU WKH GRPHVWLF PDWHULDOV GHVFULEHG
DERYHRFFXUUHGLQWKH8QLWHG6WDWHRI$PHULFD
0DQXIDFWXUHU
VFHUWLILFDWHVYHULI\WKHRULJLQDERYHGHVFULEHGLQWKHGRPHVWLFPDWHULDOVZLOOEHNHSWRQILOHIRUWKUHH\HDUVE\WKHVXSSOLHUIROORZLQJ
WKHILQDOSD\PHQW&RSLHVZLOOEHSURYLGHGWRWKH&LW\RI'XEXTXHXSRQWKHLUUHTXHVW,GHFODUHXQGHUWKHSHQDOW\RISHUMXU\XQGHUWKH6WDWH
RI,RZDDQG)HGHUDO/DZVWKDWWKHIRUHJRLQJLVWUXHDQGFRUUHFW
&RPSDQ\1DPHDQG$GGUHVV$XWKRUL]HG5HSUHVHQWDWLYH
1DPH
7LWOH
6LJQDWXUH
'DWH
EXHIBIT D
REVISION DESCRIPTIONNO.
REV.DATE
US Pipelines & Logistics
PREPARED BY:
x
x
EXHIBIT E
BP VACATE
EASEMENT INTEREST
E1
E3
E2
REPLACEMENT
EASEMENT
EXISTING EASEMENT
EXISTING EASEMENT
BP REPLACEMENT EASEMENT
BP EXISTING EASEMENT TO REMAIN
E1 VACATE EASEMENT - KRESS
E2 VACATE EASEMENT - KNEPPER
E3 VACATE EASEMENT - REUTER
Prepared by: Robert D. Schiesl, Assistant City Engineer, City of Dubuque, City Hall, 50 W 13
th Street, Dubuque, Iowa 52001
Return to: Robert D. Schiesl, Assistant City Engineer, City of Dubuque, City Hall, 50 W 13th Street, Dubuque, Iowa 52001
Partial Disclaimer of Interest in Realty
Parcel 152 - Kress
Project No. HDP䇲㻞㻝㻜㻜㻌㻔㻢㻢㻣㻕䇲 䇲 㻣㻝䇲 㻟㻝
CITY OF DUBUQUE
PARTIAL DISCLAIMER OF INTEREST IN REALTY
County Dubuque
Project No.HDP-2100 (667)--71-31
Agreement No.U-BP-PP05-2017-667-71-31
BP Pipelines (North America) Inc., a Maine corporation, with principle office located at 30 South
Wacker, 10S-322, Chicago, Illinois 60606, has certain interests and rights to an easement granted to
Standard Oil Company on May 27, 1946, and recorded July 26, 1946, in Book L36, Page 72, in the
office of the Dubuque County Recorder and shown on Exhibit "E1" attached does hereby relinquish all
rights granted to said corporation to the portions of existing easement to be vacated as shown on
attached Exhibit "E1."
Executed by the Company this __________ day of ________________, 2017.
BP PIPELINES (NORTH AMERICA) INC.
By ____________________________________
(Signature)
______________________________
(Print Name)
______________________________
State of __________________(Print Title)
County of ________________: ss.
On this day of , 2017, before me, the undersigned, a
Notary Public in and for said State, personally appeared and
to me personally known, who, being duly sworn, did say that
they are the and ,
respectively, of said corporation; that (no seal has been procured by the said) (the seal affixed thereto
is the seal of said) corporation; that said instrument was signed (and sealed) on behalf of said
corporation by authority of its Board of Directors; and that they, as such officers, acknowledged the
execution of said instrument to be the voluntary act and deed of said corporation, by it and by them
voluntarily executed.
(SEAL)(Sign in Ink)
(Type/Print Name)
Notary Public for said State
EXHIBIT E1
K
N
E
P
P
E
R
L
A
N
E
0
SCALE
EXHIBIT E1
150 300
SEC 11-88-2E
NW1/4 NW1/4
FD SCM
NW COR SEC 11-88-2E
FD SCM
N1/4 COR SEC 11-88-2E
N87°20'18"E 2638.87'
FD I.P. W/YELLOW CAP NO. 14417
SW COR NW1/4 NW1/4 SEC 11-88-2E
SEC 11-88-2E
W LINE NW1/4 NW1/4
N02°04'49"W 1323.70'
SEC 11-88-2E
N LINE NW1/4 NW1/4
PLAT SHOWING PORTION OF EXISTING BP PIPELINES (NORTH AMERICA) INC.
(GRANTED TO STANDARD OIL COMPANY ON MAY 27, 1946) EASEMENT TO BE VACATED
SOUTHWEST ARTERIAL
CITY OF DUBUQUE, DUBUQUE COUNTY, IOWA
SEC 11-88-2E
E LINE NW1/4 NW1/4
PAGE 1 OF 1
N87°20'18"E 1319.44'
50.02'
S01°49'50"E
219.10'
S86°38'25"W
177.83''
N86°38'25"E
BE VACATED
EASEMENT TO
PORTION OF
P.O.B. OF THELINE SW ARTERIAL
EXISTING R-O-W
0
SCALE
150 300
S01°49'50"E 388.33'
65.69'
N37°04'24"E
Prepared by: Robert D. Schiesl, Assistant City Engineer, City of Dubuque, City Hall, 50 W 13
th Street, Dubuque, Iowa 52001
Return to: Robert D. Schiesl, Assistant City Engineer, City of Dubuque, City Hall, 50 W 13th Street, Dubuque, Iowa 52001
Partial Disclaimer of Interest in Realty
Parcel 151 - Knepper
Project No. HDP䇲㻞㻝㻜㻜㻌㻔㻢㻢㻣㻕䇲 䇲 㻣㻝䇲 㻟㻝
CITY OF DUBUQUE
PARTIAL DISCLAIMER OF INTEREST IN REALTY
County Dubuque
Project No.HDP-2100 (667)--71-31
Agreement No.U-BP-PP05-2017-667-71-31
BP Pipelines (North America) Inc., a Maine corporation, with principle office located at 30 South
Wacker, 10S-322, Chicago, Illinois 60606, has certain interests and rights to an easement granted to
Standard Oil Company on May 30, 1946, and recorded July 26, 1946, in Book L36, Page 97, in the
office of the Dubuque County Recorder and shown on Exhibit "E2" attached does hereby relinquish all
rights granted to said corporation to the portions of existing easement to be vacated as shown on
attached Exhibit "E2."
Executed by the Company this __________ day of ________________, 2017.
BP PIPELINES (NORTH AMERICA) INC.
By ____________________________________
(Signature)
______________________________
(Print Name)
______________________________
State of __________________(Print Title)
County of ________________: ss.
On this day of , 2017, before me, the undersigned, a
Notary Public in and for said State, personally appeared and
to me personally known, who, being duly sworn, did say that
they are the and ,
respectively, of said corporation; that (no seal has been procured by the said) (the seal affixed thereto
is the seal of said) corporation; that said instrument was signed (and sealed) on behalf of said
corporation by authority of its Board of Directors; and that they, as such officers, acknowledged the
execution of said instrument to be the voluntary act and deed of said corporation, by it and by them
voluntarily executed.
(SEAL)(Sign in Ink)
(Type/Print Name)
Notary Public for said State
EXHIBIT E2
K
N
E
P
P
E
R
L
A
N
E
0
SCALE
150 300
SEC 11-88-2E
NW1/4 NW1/4
N87°20'18"E 2638.87'
PAGE 1 OF 1
PLAT SHOWING PORTION OF EXISTING BP PIPELINES (NORTH AMERICA) INC.
(GRANTED TO STANDARD OIL COMPANY ON MAY 30, 1946) EASEMENT TO BE VACATED
SOUTHWEST ARTERIAL
CITY OF DUBUQUE, DUBUQUE COUNTY, IOWA
BE VACATED
EASEMANT TO
PORTION OF
P.O.B. OF THE
SEC 11-88-2E
N LINE NW1/4 NW1/4
FD SCM
SEC 11-88-2E
NW COR
N87°20'18"E 1319.44'
SEC 11-88-2E
NE1/4 NW1/4
W LINE
EXHIBIT E2
S01°49'50"E 388.33'
FD SCM
SEC 11-88-2E
N1/4 COR
LINE
EXISTING R-O-W
LINE
DUBUQUE
BY THE CITY OF
EASEMENT OWNED
WIDE PERMANENT
EXISTING 30'
BP EASEMENT
EXISTING 50-FOOTN01°49'50"W 50.02'
SEC 11-88-2E
E1/2 NW1/4
W 32' OF THE
SEC 11-88-2E
THE NE1/4 NW1/4
E 39 ACRES OF
32.03'
N85°49'18"E
S01°49'50"E 50.02'
32.03'
S85°49'18"W
Prepared by: Robert D. Schiesl, Assistant City Engineer, City of Dubuque, City Hall, 50 W 13th Street, Dubuque, Iowa 52001
Return to: Robert D. Schiesl, Assistant City Engineer, City of Dubuque, City Hall, 50 W 13th Street, Dubuque, Iowa 52001
Partial Disclaimer of Interest in Realty
Parcel 161 - Reuter
Project No. HDP䇲㻞㻝㻜㻜㻌㻔㻢㻢㻣㻕䇲 䇲 㻣㻝䇲 㻟㻝
CITY OF DUBUQUE
PARTIAL DISCLAIMER OF INTEREST IN REALTY
County Dubuque
Project No.HDP-2100 (667)--71-31
Agreement No.U-BP-PP05-2017-667-71-31
BP Pipelines (North America) Inc., a Maine corporation, with principle office located at 30 South
Wacker, 10S-322, Chicago, Illinois 60606, has certain interests and rights to an easement granted to
Standard Oil Company on May 28, 1946, and recorded July 26, 1946, in Book L36, Page 100, in the
office of the Dubuque County Recorder and shown on Exhibit "E3" attached does hereby relinquish all
rights granted to said corporation to the portions of existing easement to be vacated as shown on
attached Exhibit "E3."
Executed by the Company this __________ day of ________________, 2017.
BP PIPELINES (NORTH AMERICA) INC.
By ____________________________________
(Signature)
______________________________
(Print Name)
______________________________
State of __________________(Print Title)
County of ________________: ss.
On this day of , 2017, before me, the undersigned, a
Notary Public in and for said State, personally appeared and
to me personally known, who, being duly sworn, did say that
they are the and ,
respectively, of said corporation; that (no seal has been procured by the said) (the seal affixed thereto
is the seal of said) corporation; that said instrument was signed (and sealed) on behalf of said
corporation by authority of its Board of Directors; and that they, as such officers, acknowledged the
execution of said instrument to be the voluntary act and deed of said corporation, by it and by them
voluntarily executed.
(SEAL)(Sign in Ink)
(Type/Print Name)
Notary Public for said State
EXHIBIT E3
K
N
E
P
P
E
R
L
A
N
E
0
SCALE
150 300
SEC 11-88-2E
NW1/4 NW1/4
N87°20'18"E 2638.87'
PAGE 1 OF 1
PLAT SHOWING PORTION OF EXISTING BP PIPELINES (NORTH AMERICA) INC.
(GRANTED TO STANDARD OIL COMPANY ON MAY 28, 1946) EASEMENT TO BE VACATED
SOUTHWEST ARTERIAL
CITY OF DUBUQUE, DUBUQUE COUNTY, IOWA
BE VACATED
EASEMANT TO
PORTION OF
P.O.B. OF THE
SEC 11-88-2E
N LINE NW1/4 NW1/4
FD SCM
SEC 11-88-2E
NW COR
N87°20'18"E 1319.44'
SEC 11-88-2E
NE1/4 NW1/4
W LINE
EXHIBIT E3
S01°49'50"E 388.33'
FD SCM
SEC 11-88-2E
N1/4 COR
LINE
DUBUQUE
BY THE CITY OF
EASEMENT OWNED
WIDE PERMANENT
EXISTING 30'
BP EASEMENT
EXISTING 50-FOOT
N01°49'50"W 50.02'
60.10'
S37°55'02"E
495.88'
S85°49'18"W
SEC 11-88-2E
E1/2 NW1/4
W 32' OF THE
SEC 11-88-2E
THE NE1/4 NW1/4
E 39 ACRES OF
EASEMANT TO BE VACATED
P.O.B. OF THE PORTION OF
460.44'
N85°49'18"E
32.03
N85°49'18"E
SW ARTERIAL
R-O-W LINE
PRESENT NE'LY
1
Prepared by: Robert D. Schiesl City Hall 50 W 13th Street Dubuque Iowa 52001 Phone: 563.589.4270
Return to: Robert D. Schiesl City Hall 50 W 13th Street Dubuque Iowa 52001 Phone: 563.589.4270
GRANT OF PERMANENT EASEMENT
For and in consideration of the sum of ONE DOLLAR ($1.00) and other good and
valuable consideration, the receipt whereof is hereby acknowledged, CITY OF
DUBUQUE, IOWA (City), owner of the following described property in Dubuque County,
State of Iowa, does hereby grant, sell and convey to the BP PIPELINES (NORTH
AMERICA) INC. (Company), a Maine corporation, its agents and contractors, from the
date hereof, permanent easement for the purpose, from time to time, of constructing,
operating, inspecting, maintaining, protecting, marking, repairing, replacing, changing
the size of, and removing a pipeline or pipelines, and appurtenances, equipment, and
facilities useful or incidental to or for the operation or protection thereof, for the
transportation of oil, gases, liquids, solids, or any mixtures thereof, upon and along a
route on, under and through the following described land located in Dubuque, Iowa, to
wit:
A PARCEL OF LAND SITUATED IN PART OF LOT A OF LOT 2 OF THE EAST
39 ACRES OF THE NORTHEAST 1/4 OF THE NORTHWEST 1/4 AND OF THE
WEST 1 ACRE OF THE NORTHEAST 1/4 OF THE NORTHWEST 1/4, ALL IN
SECTION 11, T88N, R2E OF THE 5TH P.M., COUNTY OF DUBUQUE, STATE
OF IOWA
AND
A PARCEL OF LAND SITUATED IN PART OF LOT A OF THE NORTHWEST
1/4 OF THE NORTHWEST 1/4 AND LOT B OF THE NORTHWEST 1/4 OF THE
NORTHWEST 1/4, ALL IN SECTION 11, T88N, R2E OF THE 5TH P.M.,
COUNTY OF DUBUQUE, STATE OF IOWA
AND
A PARCEL OF LAND SITUATED IN PART OF LOT A OF LOT 1 OF THE EAST
39 ACRES OF THE NORTHEAST 1/4 OF THE NORTHWEST 1/4, AND OF LOT
1 OF THE EAST 39 ACRES OF THE SOUTHEAST 1/4 OF THE NORTHWEST
1/4, AND OF THE SOUTHWEST 1/4 OF THE NORTHEAST 1/4, AND OF LOT 1
OF 1 OF 1 OF 1 OF 1 OF THE NORTHWEST 1/4 OF THE SOUTHEAST 1/4,
ALL IN SECTION 11, T88N, R2E OF THE 5TH P.M., COUNTY OF DUBUQUE,
STATE OF IOWA
as more particularly shown on the Permanent Easement Exhibit “F1” attached hereto.
EXHIBIT F
2
WHEREAS, the City and the Iowa Department of Transportation (hereafter Iowa DOT),
desires to construct a highway known as US Highway 52 / Southwest Arterial (hereafter
Project) on part of the land subject to the Grant of Permanent Easement of Company
and subject to the terms and conditions of the executed Subordination of Easement
Agreement, and;
WHEREAS, the City and Company have previously entered into a reimbursement and
relocation agreement whereby the City agreed to reimburse and the Company agreed
to relocate certain facilities, and;
WHEREAS, the City has agreed to provide the Company with a replacement utility
easement as more particularly shown on the Permanent Easement Exhibit “F1”
attached hereto, and;
WHEREAS, the City and Iowa DOT shall have the rights to use all that part of the land
above the top of the Company facilities for the purposes of constructing and maintaining
the highway, and for any other lawful purposes, and;
WHEREAS, the Company may, subject to the reasonable requirements of the Iowa
Department of Transportation Utility Accommodation Policy have access to its facilities
for purposes of reasonable operation, maintenance and/or repair, and;
WHEREAS, the City, the Iowa DOT and Company shall respectfully notify the other in
advance of construction, repair and maintenance activities on or adjacent to the land
described in Exhibit “F1”.
To have and to hold in perpetuity, and the undersigned does hereby expressly covenant
that it is the owner in fee of said real estate and has good right to execute this Grant of
Permanent Easement, and that Company, its agents or contractors, subject to the
reasonable requirements of the Iowa Department of Transportation Utility
Accommodation Policy have access to its facilities from and over said real estate for the
purpose of this Grant of Permanent Easement.
Executed by the City of Dubuque this ___________ day of ______________, 2017.
CITY OF DUBUQUE
By ____________________________________
(Signature)
____________________________________
(Print Name)
____________________________________
(Print Title)
NOTARY PUBLIC
STATE OF IOWA,
COUNTY OF DUBUQUE, SS:
On this day of , 2017 before me, the undersigned, a Notary
Public in and for said County, in said State, personally appeared ,
owner, to me known to be the identical person named in and who executed the within
and foregoing instrument, to which this is attached, and acknowledged that she
executed the same as her voluntary act and deed.
______________________________
Notary Public In and For Said State
EXHIBIT F1 BP REPLACEMENT EASEMENT
3UHSDUHGE\5REHUW6FKLHVO&LW\RI'XEXTXH2IILFHRI&LW\(QJLQHHU:WK6WUHHW'XEXTXH,$
5HWXUQWR5REHUW6FKLHVO&LW\RI'XEXTXH2IILFHRI&LW\(QJLQHHU:WK6WUHHW'XEXTXH,$
+LJKZD\'LYLVLRQ
6WDWHZLGH2SHUDWLRQV%XUHDX
68%25',1$7,212)($6(0(17$*5((0(17
&RXQW\ 'XEXTXH
3URMHFW1R +'3ǦǦǦǦ
&RQWUDFW1R8%333
7+,6$*5((0(17PDGHDQGHQWHUHGLQWRWKLVBBBBBGD\RIBBBBBBBBBBBBE\DQGEHWZHHQ
WKH6WDWHRI,RZD,RZD'HSDUWPHQWRI7UDQVSRUWDWLRQ+LJKZD\'LYLVLRQKHUHDIWHU,RZD'27DQG%3
3LSHOLQHV1RUWK$PHULFD,QFD0DLQHFRUSRUDWLRQDFRUSRUDWLRQZLWKRIILFHVLQ&KLFDJR,OOLQRLV
KHUHDIWHU&RPSDQ\
:+(5($6WKH&RPSDQ\LVWKHRZQHURIWKH:KLWLQJ'XEXTXHSLSHOLQHIDFLOLW\E\YLUWXHRIWKRVH
FHUWDLQHDVHPHQWULJKWVH[HFXWHGE\
x &LW\RI'XEXTXH*UDQWRI3HUPDQHQW(DVHPHQWDJUHHPHQWGDWHGBBBBBBBBBBBUHFRUGHG
BBBBBBBBBBBILOHGDV,QVWUXPHQWQXPEHUIRUUHFRUGLQWKH2IILFHRIWKH
'XEXTXH&RXQW\5HFRUGHU&LW\RI'XEXTXH,RZD
:+(5($6WKH&LW\RI'XEXTXHKHUHDIWHU&LW\DQGWKH,RZD'27GHVLUHVWRFRQVWUXFWDKLJKZD\
NQRZQDV86+LJKZD\6RXWKZHVW$UWHULDORQSDUWRIWKHODQGVXEMHFWWRWKHHDVHPHQWRIWKH&RPSDQ\
DQGIXUWKHUGHVLUHVWKH&RPSDQ\WRVXERUGLQDWHFHUWDLQRILWVHDVHPHQWULJKWVWRWKH,RZD'27DQG
:+(5($6WKH&LW\KDVDFTXLUHGULJKWRIZD\IRUVDLGSURMHFWLQFOXGLQJODQGXSRQZKLFKWKH&RPSDQ\
KROGVDQHDVHPHQWLQFOXGLQJ
x 3DUFHO1R$:DUUDQW\'HHGRU(DVHPHQWIRU3XEOLF+LJKZD\JUDQWHGE\-RKQ/.QHSSHU
DVSHUDJUHHPHQWGDWHG-XO\UHFRUGHG-XO\DV,QVWUXPHQWQXPEHU
EHLQJDSDUFHORIODQGLQLot A of Lot 2 of the East 39 Acres of the Northeast 1/4 of the
Northwest 1/4 and of the West 1 Acre of the Northeast 1/4 of the Northwest 1/4DOOLQ6HFWLRQ
715(RIWKHWK30'XEXTXH&RXQW\,RZDDQG
x 3DUFHO1RWKURXJKHPLQHQWGRPDLQSURFHHGLQJVKHOGRQ$XJXVWQGIRU3XEOLF+LJKZD\
DVRUGHUHGE\WKHFRXUWIRU:LOOLDP-.UHVVDVUHFRUGHG2FWREHUDV,QVWUXPHQWQXPEHU
EHLQJDSDUFHORIODQGLQLot A of the Northwest 1/4 of the Northwest 1/4 and Lot
B of the Northwest 1/4 of the Northwest 1/4DOOLQ6HFWLRQ715(RIWKHWK30'XEXTXH
&RXQW\,RZDDQG
x 3DUFHO1RWKURXJKHPLQHQWGRPDLQSURFHHGLQJVKHOGRQ$XJXVWUGIRU3XEOLF+LJKZD\
DVRUGHUHGE\WKHFRXUWIRU(OL]DEHWK5HXWHUDVUHFRUGHG2FWREHUDV,QVWUXPHQWQXPEHU
EHLQJDSDUFHORIODQGLQLot A of Lot 1 of the East 39 Acres of the Northeast 1/4
of the Northwest 1/4, and of Lot 1 of the East 39 Acres of the Southeast 1/4 of the Northwest 1/4,
and of the Southwest 1/4 of the Northeast 1/4DQGRI/RWRIRIRIRIRIWKH1RUWKZHVW
RIWKH6RXWKHDVWDOOLQ6HFWLRQ715(RIWKHWK30'XEXTXH&RXQW\,RZDDQG
:+(5($6WKH&LW\DQGWKH&RPSDQ\KDYHSUHYLRXVO\HQWHUHGLQWRDUHLPEXUVHPHQWDQGUHORFDWLRQ
DJUHHPHQWZKHUHE\WKH&LW\DJUHHGWRUHLPEXUVHDQGWKH&RPSDQ\DJUHHGWRUHORFDWHFHUWDLQSLSHOLQHV
DQG
:+(5($6LWLVWKHLQWHQWRIWKH&LW\WKH,RZD'27DQGWKH&RPSDQ\WKDWWKH&RPSDQ\VXERUGLQDWH
FHUWDLQVSHFLILHGULJKWVRILWVHDVHPHQWVZLWKLQWKHODQGDFTXLUHGE\WKH&LW\IRUVDLGSURMHFWVRWKDWWKH
,RZD'27PD\HQMR\VDLGODQGIRUKLJKZD\SXUSRVHVDQG
EXHIBIT G
2
WHEREAS, it is the intent of the Iowa DOT and the Company that the Company continue to enjoy its
existing easement rights within the subsurface of the land acquired by the City for said project, subject to
the restrictions specified herein.
NOW THEREFORE, in consideration of the mutual covenants and agreements hereinafter set forth, it
is agreed by and between the parties hereto as follows:
1. The Company does hereby subordinate, relinquish and convey to the Iowa DOT all of its rights,
title and interest by virtue of its easements in and to those parcels of land as shown on the plats
attached as Exhibits “G1, G2”, acquired in 2011 and 2016 as right of way for US Highway 52 /
Southwest Arterial, Project No. HDP‐2100 (667)‐‐71‐31 and located at approximate Sta. 263+57
and referenced as the Company's Whiting-Dubuque pipeline, excepting and reserving to the
Company, its successors and assigns, all rights below the top of pipe in 50-foot utility easement
corridor centered on the 10-inch pipeline, including but not limited to the right to construct, operate
and maintain, repair or replace the pipeline.
2. The Iowa DOT shall have the rights to use all that part of the land above the top of the pipeline for
the purpose of constructing and maintaining the highway, and for any other lawful purposes.
3. The Company may, subject to the reasonable requirements of the Iowa Department of
Transportation Utility Accommodation Policy have access to its facilities for purposes of reasonable
operation, maintenance and/or repair.
4. The Iowa DOT and Company shall respectfully notify the other in advance of construction, repair
and maintenance activities on or adjacent to the land described in Exhibit “G2”.
5. A material aspect of the consideration of this agreement is the performance of the parties hereto,
to their respective obligations as specified in that certain "Agency Utility Relocation Agreement",
adopted herein by reference, executed the (insert date reimbursement agreement was executed).
6. This agreement shall inure to and be binding upon the successors and assigns of the parties hereto.
3
IN WITNESS WHEREOF the Parties hereto have caused this agreement to be executed by their duly
authorized officers on the dates below indicated.
Executed by the Company this _______ day of ____________________, 17
BP Pipelines (North America) Inc.
BY:
(Type/Print Name)
(Title)
STATE OF )
)SS:
COUNTY OF )
On this day of , 2017, before me, the undersigned, a
Notary Public in and for said State, personally appeared to
me personally known, who, being duly sworn, did say that he/she is the
of said corporation; that (no seal has been procured by the said) (the seal affixed
thereto is the seal of said) corporation; that said instrument was signed (and sealed) on behalf of said
corporation by authority of its Board of Directors; and that they, as such officers, acknowledged the
execution of said instrument to be the voluntary act and deed of said corporation, by it and by them
voluntarily executed.
(SEAL) (Sign in Ink)
(Type/Print Name)
Notary Public for said State
Executed by the Iowa Department of Transportation this _______ day of ___________________, 2017
STATE OF IOWA
IOWA DEPARTMENT OF TRANSPORTATION
By
Bryan Bradley, State Utility Engineer
Office of Traffic and Safety
STATE OF IOWA )
)SS:
COUNTY OF STORY )
This instrument was acknowledged before me on this _______ day of ____________________, 2017,
by Bryan Bradley, as State Utility Engineer, Office of Traffic and Safety of the Iowa Department of
Transportation.
_________________________________________
Notary Public in and for said State
REVISION DESCRIPTIONNO.
REV.DATE
US Pipelines & Logistics
PREPARED BY:
x
x
EXHIBIT G1
BP REPLACEMENT
EASEMENT
E1
E3
E2
REPLACEMENT
EASEMENT
EXISTING EASEMENT
EXISTING EASEMENT
BP REPLACEMENT EASEMENT
BP EXISTING EASEMENT TO REMAIN
E1 VACATE EASEMENT - KRESS
E2 VACATE EASEMENT - KNEPPER
E3 VACATE EASEMENT - REUTER
EXHIBIT G2
BP REPLACEMENT
EASEMENT
iiiiioiiiiiiiiiiiiiii1IIIIIIllI1l111111iosiii111111ii1t11111 11
Doc ID 010351210003 Type GEN
Kind: SUBORDINATION AGREEMENT
Recorded: 09/12/2019 at 01:48:32 PM
Fee Amt: $17.00 Page 1 of 3
Dubuque County Iowa
John Murphy Recorder
File2019-00010853
Prepared by: Robert Schiesl, City of Dubuque, Office of City Engineer, 50 W 13th Street, Dubuque IA 52001 563-589-4270
Return to: Robert Schiesl, City of Dubuque, Office of City Engineer, 50 W 13th Street, Dubuque IA 52001 563-589-4270
Iowa Department of Transportation
Highway Division
Statewide Operations Bureau
SUBORDINATION OF EASEMENT AGREEMENT
County Dubuque
Project No. HDP -2100 (667)--71-31
Contract No. U-BP-PP05-2017-667-71-31
THIS AGREEMENT, made and entered into this 11th day of June , 2019, by and between
the State of Iowa, Iowa Department of Transportation, Highway Division (hereafter Iowa DOT), and BP
Pipelines (North America) Inc., a Maine corporation, a corporation, with offices in Chicago, Illinois
60606, (hereafter Company);
WHEREAS, the Company is the owner of the Whiting -Dubuque pipeline facility by virtue of those
certain easement rights, executed by
• City of Dubuque, Grant of Permanent Easement agreement dated the 2nd day of December ,
2018, recorded the 5th day of December , 2018, filed as Instrument number 2018-00014333
for record in the Office of the Dubuque County Recorder, City of Dubuque, Iowa;
WHEREAS, the City of Dubuque (hereafter City) and the Iowa DOT desires to construct a highway
known as US Highway 52 / Southwest Arterial on part of the land subject to the easement of the Company
and further desires the Company to subordinate certain of its easement rights to the Iowa DOT and;
WHEREAS, the City has acquired right of way for said project including land upon which the Company
holds an easement including
• Parcel No. 151A, Warranty Deed (or) Easement for Public Highway granted by John L. Knepper,
as per agreement dated July 13, 2011, recorded July 14, 2011 as Instrument number 2011-
000099005, being a parcel of land in Lot A of Lot 2 of the East 39 Acres of the Northeast 1/4 of the
Northwest 1/4 and of the West 1 Acre of the Northeast 1/4 of the Northwest 1/4, all in Section 11,
T88N, R2E of the 5th P.M., Dubuque County, Iowa, and
• Parcel No. 152, through eminent domain proceedings held on August 2nd, 2016 for Public Highway
as ordered by the court for William J. Kress, as recorded October 18, 2016 as Instrument number
2016-00013928, being a parcel of land in Lot A of the Northwest 1/4 of the Northwest 1/4 and Lot
B of the Northwest 1/4 of the Northwest 1/4, all in Section 11, T88N, R2E of the 5th P.M., Dubuque
County, Iowa, and
• Parcel No. 161, through eminent domain proceedings held on August 3rd, 2016 for Public Highway
as ordered by the court for Elizabeth Reuter, as recorded October 18, 2016 as Instrument number
2016-00013927, being a parcel of land in Lot A of Lot 1 of the East 39 Acres of the Northeast 1/4
of the Northwest 1/4, and of Lot 1 of the East 39 Acres of the Southeast 1/4 of the Northwest 1/4,
and of the Southwest 1/4 of the Northeast 1/4, and of Lot 1 of 1 of 1 of 1 of 1 of the Northwest 1/4
of the Southeast 1/4, all in Section 11, T88N, R2E of the 5th P.M., Dubuque County, Iowa, and
WHEREAS, the City and the Company have previously entered into a reimbursement and relocation
agreement whereby the City agreed to reimburse and the Company agreed to relocate certain pipelines,
and
WHEREAS, it is the intent of the City, the Iowa DOT and the Company that the Company subordinate
certain specified rights of its easements within the land acquired by the City for said project, so that the
Iowa DOT may enjoy said land for highway purposes, and
1
CA o4 b 0.0o
� nor
WHEREAS, it is the intent of the Iowa DOT and the Company that the Company continue to enjoy its
existing easement rights within the subsurface of the land acquired by the City for said project, subject to
the restrictions specified herein.
NOW THEREFORE, in consideration of the mutual covenants and agreements hereinafter set forth, it
is agreed by and between the parties hereto as follows:
1. The Company does hereby subordinate, relinquish and convey to the Iowa DOT all of its rights,
title and interest by virtue of its easements in and to those parcels of land as shown on the plats
attached as Exhibits "G1, G2", acquired in 2011 and 2016 as right of way for US Highway 52 /
Southwest Arterial, Project No. HDP -2100 (667)--71-31 and located at approximate Sta. 263+57
and referenced as the Company's Whiting -Dubuque pipeline, excepting and reserving to the
Company, its successors and assigns, all rights below the top of pipe in 50 -foot utility easement
corridor centered on the 10 -inch pipeline, including but not limited to the right to construct, operate
and maintain, repair or replace the pipeline.
2. The Iowa DOT shall have the rights to use all that part of the land above the top of the pipeline for
the purpose of constructing and maintaining the highway, and for any other lawful purposes.
3. The Company may, subject to the reasonable requirements of the Iowa Department of
Transportation Utility Accommodation Policy have access to its facilities for purposes of reasonable
operation, maintenance and/or repair.
4. The Iowa DOT and Company shall respectfully notify the other in advance of construction, repair
and maintenance activities on or adjacent to the land described in Exhibit "G2".
5. A material aspect of the consideration of this agreement is the performance of the parties hereto,
to their respective obligations as specified in that certain "Agency Utility Relocation Agreement",
adopted herein by reference, executed the 8th day of August , 2017.
6. This agreement shall inure to and be binding upon the successors and assigns of the parties hereto.
2
IN WITNESS WHEREOF the Parties hereto have caused this agreement to be executed by their duly
authorized officers on the dates below indicated.
Executed by the Company this Q S TN day of April , 2019.
STATE OF Illinois
COUNTY OF Cook : ss.
On this /6 day of April
and for said State, personally appeared
BP PIPELINES (NORTH AMERICA) INC.
By
(Signature)
eeeGLI
(Print Name)
(Print Title)
, 2019, before me the undersigned, a Notary Public in
Cl Matei to me personally
known, who, being duly sworn, did say that they are the Pf i'e/¢,a of
/ Pita- it:AR-S 1 tl14j
, respectively, of said corporation; that (no seal has
been procured by the said) (the seal affixed thereto is the seal of said) corporation; that said instrument
was signed (and sealed) on behalf of said corporation by authority of its Board of Directors; and that
they, as such officers, acknowledged the execution of said instrument to be the voluntary act and deed
of said corporation, by it and by them voluntarily executed.
(SEAL)
OFFICIAL SEAL
BLAKE PATRICK
NOTARY PUBLIC - STATE OF ILLINOIS
MY COMMISSION EXPIRES:10105122
(Sign in Ink)
(Type/Print Name)
Notary Public for said State
State of Iowa
ss
County of Story
Executed by the Department this ( 1 day of
By
tit I<'1 , 2019
STATE OF IOWA
IOWA DEPARTMENT OF TRANSPORTATION
Martin nkey, Director
0 '` e of Right of Way
State of Iowa
This instrument was acknowledged before me on this / / day of -;1 - , 2019, by Martin J.
Sankey, as Director, Office of Right of Way of the Iowa Department of Transportation.
1
1 ��'ANDERSON
;ComE
nission Number 710534
' ' My Commission Expires
o. February 18, 2021
No`fary Public in and for said State