Wartburg Place ReconstructionMEMORANDUM July 30, 2002 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Wartburg Place Reconstruction Sealed bids were received for the Wartburg Place Reconstruction Project. Public Works Director Mike Koch recommends award of the contract to the Iow bidder, Portzen Construction, Inc., in the amount of $464,434.43, which is 16.7% under the engineer's estimate. At the last public hearing on this project, there was much discussion about whether to include or delete the proposed new sidewalks on the east side of Wartburg Place. The contract amount includes the cost of the sidewalk, since sidewalks were included in the original scope of the project. If the Council chooses to eliminate the sidewalks, there would be a savings of $13,104.59 on the project cost, all of which is assessable. The amount would be deducted from the contract by a change order following the execution of the contract at the bid amount. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Michael A. Koch, Public Works Director CITY OF DUBUQUE, IOWA MEMORANDUM July 30, 2002 TO: Michael C, Van Milligen, City Manager FROM: Michael A. Koch, Public Works Director SUBJECT: Wartburg Place Reconstruction INTRODUCTION The enclosed resolution provides for the award of the construction contract for the Wartburg Reconstruction Project. DISCUSSION The project will consist of the complete reconstruction of the existing base and pavement surface for Wartburg Place and a hammerhead turnaround constructed at the end of Wartburg Place at the entrance to Sunset Ridge. The street width is 31 feet in front of Wartburg Seminary with parking on one side. To the east of Wartburg Seminary, there is a 24-foot wide section with parking prohibited on both sides of the street. Since there is a parking prohibition on both sides of the 24-foot wide section of street to allow for two lanes of travel; and therefore; the existing width will be retained. The 6- inch wide curb will widen the street width to 25 foot. Storm sewer improvements are being proposed at the end of Wartburg Place to limit the stormwater going down Sunset Ridge. Sealed bids were received on the project on July 25, 2002. Portzen Construction, Inc. of Dubuque, Iowa, submitted the Iow bid in the amount of $464,434.42. This amount is 16.7% under the engineer's estimate. A summary of the bids received is as follows: Portzen Construction, Inc. $464,434.42 Horsfield Construction, Inc. $483,130.30 Tschiggfde Excavating Co. $594,123.39 RECOMMENDATION At the last public hearing on this project, there was much discussion about whether to include or delete the proposed new sidewalks on the east side of Wartburg Place. The contract amount above includes the cost of the sidewalk since sidewalks were included in the original scope of the project. If the Council chooses to eliminate the sidewalks, there would be a savings of $13,104.59 on the project cost, all of which is assessable. The amount would be deducted from the contract by a change order following the execution of the contract at the bid amount. I recommend that the contract be awarded to Portzen Construction, Inc. in the amount of $464,434.42. BUDGET IMPACT The summary of the project costs is as follows: Estimate Bid Construction Contract $557,840.00 $464,434.42 Contingency 55,784.00 55,784.00 Engineering 92,043.60 92,043.60 Total Project Cost $705,667.60 $612,262.02 The project will be funded as follows: Estimate Bid Road Use Tax $454,262.74 $385,554.58 Special Assessment to Private Properties $108,682.51 90,937.09 Special Assessment for Sidewalk $ 17,316.59 13,104.59 Special Assessment - Water Services $ 15,895.99 13,360.27 Sanitary Sewer Construction Fund $ 48,682.24 51,687.26 Watermain Construction Fund $ 60,827.53 57,618.23 Total $705,667.60 $612,262.02 The project will be funded through the Fiscal Year 2002 CIP appropriation of $2,515,000 for the annual street program. The project, as outlined, will require $437,241.84 in City funds. Low- to moderate-income property owners subject to street assessments will be eligible for financial assistance ranging from 20 to 100 percent of the street assessments for owner-occupied residential property, depending on family size and income level. This financial assistance program is made available through the One Percent Local Option Sales Tax Fund. ACTION TO BE TAKEN The City Council is requested to adopt the attached resolution awarding the construction contract to Portzen Construction, Inc., and to give staff direction on whether to include or delete the proposed sidewalks on the east side of the project. Prepared by Michael Felderman cc: Bob Green, Water Plant Manager Gus Psihoyos, Assistant City Engineer CITY OF DUBUQUE ENGINEERING DEP~ DUBU(~UE, IOWA Warlburg Street Project RESOLUTION NO. 394-02 RESOLUTION WITH RESPECT TO THE ADOPTION OF THE RESOLUTION OF NECESSITY PROPOSED FOR THE WARTBURG RECONSTRUCTION PROJECT Whereas, the City Council has proposed a Resolution of Necessity for the Wartburg Reconstruction Project has given notice of the public hearing thereon as required by law; and Whereas, the public hearing has been held, all persons offering objections have been heard and consideration given to all objections and is pending before this Council; and Whereas, this is the time and place set as provided for the taking of action on the proposed Resolution of Necessity. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the proposed Resolution of Necessity described above is hereby: Adopted, without amendment, and all objections filed or made having been duly considered are overruled. X Adopted as amended by the Schedule of Assessments attached hereto as Exhibit A, and made a part hereof by reference. All objections filed or made having been duly considered are overruled. Deferred for later consideration to a City Council meeting to be held on the __ day of ,2002, next at 6:30 p.m. in the Public Library Auditorium, with jurisdiction retained for further consideration and action at the adjourned meeting. Abandoned. Passed, adopted and approved this 5th day of August ,2002. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, City Clerk Attest: RESOLUTION NO. 392-02 RESOLUTION ADOPTING PLANS AND SPECIFICATIONS Whereas, on the 26~h day of June, 2002, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for the Wartburg Place Reconstruction Project. Whereas, notice of hearing on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. Passed, adopted and approved this 5th day of AugUst, 2002. Te~a~,~rr~ Attest: , ~J~'anne F. Schneider OMC, City Clerk RESOLUTION NO. 393-02 AWARDING CONTRACT Whereas, sealed proposals have been submitted by contractors for the Wartburg Place Reconstruction Project pursuant to Resolution No..~£$-m,2and notice to bidders published in a newspaper published in the City of Dubuque, iowa on the 5th day of July, 2002. Whereas, said sealed proposals were opened and read on the 25th day of July, 2002, and it has been determined that the bid of Portzen Construction, Inc. of Dubuque, Iowa, in the amount of $464,434.42 was the lowest bid for the furnishings of all labor and materials and performing the work as provided for in the plans and specifications. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the contract for the above improvement be awarded to Portzen Construction, Inc. and the Manager be and is hereby directed to execute a contract on behalf of the City of Dubuque for the complete performance of the work. BElT FURTHER RESOLVED: That upon the signing of said contract and the approval of the contractor's bond, the City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful bidders. Passed, approved and adopted this 5th Attest: day of August ,2002. (_//Jeanne F. Schneider, CMC, City Clerk CODE ITEM 1101.013 Cleating & Grabbing 30" to 36" 1103.02 Excavation, Unc[assified UNIT QUANTITY UNIT COST TOTAL COST Each 8 $2,000.00 $16,00000 LrNIT 190L01 Installing 11~5" PVC duct containing 4 ~ I" PVC innor LF QUANTITY UNITCOST TOTALCOST 750 $10.00 $7,500.00 3 $100.00 $300.00 I $15,00000 $15,00000 200 10 $2,00000 200 $2.00 $400.00 4 $1,000,00 $4,000.00 4 $1,200.00 $4,800.00 334 $1500 $5,010.00 Construction $557,840.00 - $557,840.00 3.85 770.00 1.35 270.00 t,057.00 4~228.00 400.00 1~600.00 23.16 7,735.44 Total Estimate 449,830,98 Total ~t[mat~ w/ 464,434.42 % Over / Under (-) ~19.36% -61.50% 600 1,200.00 7,90 1,580.00 -32.$0% I 00 200.00 0.90 180.00 5.70% 1,125.00 4,500.00 1,125.00 4,500.00 468,824.30 577,815.45 483,130.30 594,123.39 MEMORANDUM June 22.2002 TO: FROM: SUBJECT: The Honorable Mayor and City Council Members Michael C. Van Milligen, City Manager Wartburg Place Reconstruction Public Works Director Mike Koch recommends initiation of the bidding process for the Wartburg Place Reconstruction Project. ana further recommends that a public hearing be set for August 5, 2002. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser Assistant City Manager Michael A. Koch, Public Works Director MEMORANDUM June 24,2002 TO: FROM: SUBJECT: Michael C. Van Milligen, City Manager Michael A. Koch, Public Works Director ~.:.~4 Wartburg Place Reconstruction INTRODUCTION The enclosed resolutions authorize the public bidding procedure for the Wartburg Place Reconstruction Project. DISCUSSION The project will consist of the complete reconstruction of the existing base and pavement surface for Wartburg Place, the installation of sidewalk on both sides, and a hammerhead turnaround constructed at the end of Wartburg Place before Sunset Ridge (a private street). The street width is 31 feet in front of Wartburg Seminary with parking on one side. To the east of Wartburg Seminary, [here is a 24-foot wide section with parking prohibited on both sides of the street. Since there is a parking prohibition on' both sides of the 24-foot wide section of street, the existing width will be retained; however, the 6-inch wide curb will bring the street width to 25 foot from back-of-curb to back-of-curb. To my knowledge, the City has never received a request to widen this street, and widening would have a negative impact on a parallel row of evergreens located just off the right-of-way. These evergreens would need to be pruned back about three (3) feet if the street were to be widened. Sunset Ridge is a private street; however, the City has historically plowed the snow on the street, in exchange for the snowplows being able to turn around in the turnaround at the bottom on Sunset Ridge. This plowing was eliminated last year; and therefore, a new turnaround must be provided for the Operations & Maintenance Department for the aforementioned purpose. The new hammerhead turnaround will be located in existing City right-of-way just prior to Sunset Ridge, as shown on the attached plan. A new storm sewer is needed to drain the [urnaround and Wartburg Place before the water flows down Sunset Ridge. Negotiations are still taking place to acquire the easement. (If'the easement cannot be negotiated, [he City Council will be asked to authorize condemnation at a future Council meeting.) The last 600 feet of watermain is to be replaced along with a] new valves; the existing sanitary sewer will be updated from 6" to 10" ductile iron pipe. The Engineering and the City Forester have met with some of the residents along the project to discuss Ihe necessary removal of eight (8) trees. The trees aCe along Wartburg Seminary's frontage, and they do not have any problem with the removal because of the condition of the trees. The schedule for the project will be as follows: Advertisement for Bids Notice of Hearing on Plans and Specifications Mail Notice to Property Owners Published Notice to Property Owners Receipt of Bids Public Hearing Award of Contract Completion July 5, 2002 July 19, 2002 July 19, 2002 July 19, 2002 July 26, 2002 July 25, 2002 August 5, 2002 August 5, 2002 June 27, 2003 RECOMMENDATION t would recommend that the City Council give preliminary approval to the Resolution of Necessity and establish August 5, 2002 as the date of the Public Hearing. BUDGET IMPACT The estimate for the project is as follows: Construction Contract Coptingency Engineering $557,840.00 '$ 55,784.00 $ 92,043.60 Total $705,667.60 The project will be funded as follows: Road Use Tax Special Assessment to Private Properties Special Assessment Deficiency to be Paid By City Special Assessment for Sidewalk Special Assessment - Water Services Sanitary Sewer Construction Fund Watermain Construction Fund $454,262.74 $108,682.51 0 17,316.59 15,895.99 48,682.24 60,827.53 Total $705,667.60 The project will be funded through a Fiscal Year 2002 CIP appropriation of $2,515,000. The project, as outlined, will require $454,262.74 in City funds. Low- to moderate- income property owners subject to street assessment will be eligible for financial assistance ranging from 20 to 100 percen! of the street assessment for the owner- occupied resident property depending on family size and income level. This financial assistance program ~s made available through the One Percent Local Option Sales Tax. ACTION TO BE TAKEN The City Council's requested to give preliminary approval to the Resolution of Necessity, approve the preliminary assessment schedule, and to establish the date of the Public Hearing. MAK/vjd Prepared by Michael Felderman cc: Bob Green Water Plant Manager Gus Psihoyos, Assistant City Engineer CiTY OF DUBUQUE ENGINEERING DEPARTMENT 2001 Paving Project Wartburc~ Street Fremont Avenue to Surfer Cirde RESOLUTION NO, RESOLUTION APPROVING PRELIMINARY SCHEDULE OF ASSESSMENTS NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the attached sheets, I to 1 inclusive, are hereby determined to be the schedule of proposed assessments for the Wartburg Place Reconstruction Project and the valuations set out herein are hereby approved. Passed, approved and adopted this day of ,2002. Termnce M. Duggan, Mayor Attest: Jeanne F. Schneider. CMC, City Clerk RESOLUTION NO. PRELIMINARY APPROVAL OF PLANS AND SPECIFICATIONS NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE. IOWA: That [he proposed plans, specifications, form of contract and estimated cost for the Wartburg Place Reconstruction Project, in the estimated amount $705,667.60 are hereby approved and ordered filed in the office of the City Clerk for pubtic inspection. Passed, adopted and approved this day of 2002. Attest: Terrance M. Duggan, Mayor Jeanne F. Schneider, CMC. City Clerk RESOLUTION NO. FIXING DATE OF HEARING ON PLANS AND SPECIFICATIONS Whereas, the City Council of the City of Dubuque, Iowa has given its preliminary approval on the proposed plans, specifications, and form of contract and placed sa me on file in the office of the City Clerk for public inspection of the Wartburg Place Reconstruction Project. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That a Public Hearing will be held on the 5th day of August, 2002, at 6:30 p.m. in the Public Library Auditorium at which time interested persons may appear and be heard for or against the proposed plans and specifications, form of contract and cost of said improvement, and the City Clerk be and is hereby directed to cause a notice of time and place of such headng to be published in a newspaper having general circulation in the City of Dubuque, Iowa, which notice shall be not less than four days nor mc re than twenty days prior to the day fixed for its consideration. At the hearing, any interested person may appear and file objections to the proposed plans, specifications, contract, or estimated cost of the improvement. Passed, adopted and approved this day of ,2002. Terrance M. Duggan, Mayor Attest: Jeanne, F. Schneider, CMC, City Clerk NOTICE OF HEARING ON PLANS AND SPECIFICATIONS Notice of public hearing on proposed plans and specifications, proposed form of contract and estimate of cost for the Wartburg Place Reconstruction Project. NOTICE IS HEREBY GIVEN: The City Council of Dubuque, Iowa will hold a public hearing on the proposed plans: specifications, form of contract and estimate of cost for the Wartburg Place Reconstruction Project, in accordance with the provisions of Chapter 384, City Code of Iowa, at 6:30 p.m., on the 5th day of August, 2002, in the Public Library Auditorium, 360 West 11th Street, ,n Dubuque, Iowa. Said proposed plans, specifications, form of contract and estimate of cost are now on file in the office of the City Clerk. At said hearing any interested person may appear and file objections [hereto or to the cost of the improvements. Any visual or hearing-impaired persons needing special assistance or persons with special accessibility needs should contact the City Clerk's office at (563) 589-4120 or TDD at (563) 589~4193 in the ~tuman Rights Department at least 48 hours prior to the meeting. Published by order of the City Council given on the __ ,2002. day of Jeanne F. Schneider, CMC City Clerk RESOLUTION NO. RESOLUTION OF NECESSITY Whereas, proposed plans have been duly prepared and approved by the City Council of the City of Dubuque and are now on file in the office of City Clerk showing among other things the plans, specifications, form of contract, estimated cost and preliminary plat and schedule showing the amount proposed to be assessed against each lot and the valuation of each lot as filed by the City Council, for the War[burg Place Reconstruction Project. NOW THEREFORE, BE IT RESOLVED BY THE CtTY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the City Council deems it advisable and necessary for the public welfare to make the herein mentioned improvements, and unless property owners at the time of the final consideration of this proposed resolution have on file with the City Clerk objections to the resolution of necessity, they shall be deemed to have waived all objections pertaining to the regularity of the proceeding and the legality of using the special assessment procedure. Said improvements shall be constructed and done in accordance with the plans and specifications which have been approved by the City Council and now on file with the City Clerk. That [he cost and expense of making such improvement will be assessed partially or totally against privately owned property lying with the assessment limits, and in an amount not to exceed that provided by law, and 'n proportion to the special benefits conferred. The portion of the cost which shall be borne by the City will be paid from Road Use Tax, Sanitary Sewer Construction Fund, Watermain Construction Fund, and special assessment bonds may be issued in anticipation of deferred payments of assessments when a contract has been performed and accepted, and the proceeds thereof used to pay the contractor. The above resolution was introduced, approved and ordered placed on file with the City Clerk this day of ,2002. Approved and placed on file for fina action. Attest: Terrance M. Duggan, Mayor Jeanne F. Schneider, CMC, City Clerk RECORD OF FINAL ADOPTION The foregoing Resolution was finaJly passed and adopted as proposed by the City Council this day of 2002. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. FIXING DATE OF HEARING ON RESOLUTION OF NECESSITY Whereas, the City Council of the City of Dubuque. Iowa, has g~ven its preliminary approval on the proposed plans, specifications and form of contract and placed same on file in the office of the City Clerk for public inspection for the War[burg Place Reconstruction Project; and Whereas, the proposed Resolution of Necessity for said improvement has been introduced and is now on file in the City Clerk's office for public inspection NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That on the 5TM day of August, 2002. a public hearing will be held at 6:30 p.m in the Public Library Auditorium 'n the City of Dubuque at which time the owners of property subject to assessment for the proposed ~mprovement or any other person having an interest in the matter may appear and be heard for or against the making of the improvement, the boundaries of the district, the cost, [he assessment against any lot, or the final adoption of a resolution of necessity and the City Clerk be and is hereby authorized and directed to cause a notice of time and place of such hearing to be published n a newspaper having general circulation in the City of Dubuque, Iowa, which notice shall be published once each week for two consecutive weeks, the first publication of which shall be not less than [en days prior to the day fixed for its consideration. Unless property owners at the time of the final consideration of this proposed resolution have on file with the City Clerk objections to the Resolution of Necessity they shall be deemed to have waived all objections thereto. Passed, adopted and approved this day of ,2002. Te~ance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk NOTICE TO PROPERTY OWNERS Notice is g~ven that there's now on file for public inspection in the office of the City Clerk of Dubuque. Iowa. a proposed Resolution of Necessity, an estimate of cost, and a plat and schedule showing the amounts proposed to be assessed against each lot and the valuation of each lot within a district approved by the City Council of Dubuque, Iowa. for an improvement of the type(s) and in the location(s) as follows: War[burg Place Reconstruction Project That the proposed district to be benefited and subject to assessment for the cost of such improvements is described as follows: All property included with the areas described so as to include one-half of the privately-owned property between each such street to be improved and the next street, whether such privately-owned property abuts upon [he street to be improved or not. In no case shall property situation more than 300 feet from the street to be improved be assessed. The City Council will meet at 6:30 p.m. on the 5th day of August, 2002, at the Public Library Auditorium, 360 West 11~n Street, at which time [he owners of property subject to assessment for the proposed improvement or any other person having an interest in the matter may appear and be heard for or against the making of the improvement, the boundaries of the district, the cost, the assessment against any lot, or the final adoption of a resolution of necessity. A property owner will be deemed to have waived ail objections unless at the time of hearing he has filed objections with the City Clerk. Any visual- or hearing-impaired persons needing special assistance or persons with special accessibility needs should contact the City Clerk's office at (563) 589-4120 or TDD (563) 589-4193 in the Human Rights Department at least 48 hours pnor to the meeting. Published by order of the City Council g~ven on the ., 2002. day of Jeanne F. Schneider, CMC City Clerk RESOLUTION NO. RESOLUTION APPROVING PRELIMINARY SCHEDULE OF ASSESSMENTS NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, OWA: That the attached sheets, 1 to 1 inclusive, are hereby determined to be the schedule of proposed assessments for the War[burg Place Reconstruction Project and the valuations set out herein are hereby approved. Passed, approved and adopted this day of ,2002. Terrance M Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. RESOLUTION ADOPTING PLANS AND SPECIFICATIONS Whereas, on the 26th day of June. 2002, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for the Wartburg Place Reconstruction Project. Whereas, notice of hearing on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. Passed, adopted and approved this day of ,2002. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. ORDERING BIDS NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the Wartburg Place Reconstruction Project is hereby ordered to be advertised for bids for construction. BE IT FURTHER RESOLVED, that the amount of the secudty to accompany each bid shall be in an amount which shall conform to the provisions of the Notice to Bidders hereby approved as a part of the plans and specifications heretofore adopted. That the City Clerk is hereby directed to advertise for bids for the construction of [he improvements herein provided, to be published in a newspaper having general circulation in the City of Dubuque, Iowa. which notice shall not be [ess than four days nor more than forty-five days prior to the receipt of said bids at 2:00 p.m. on the 25th day of July, 2002. Bids shall be opened and read by the City Clerk at said time and will be submitted to the Council for final action at 6:30 p.m. on the 5th day of August, 2002. Passed, adopted and approved this day of ,2002. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk