TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 911 High Bluff Retaining Wall Repair Project
DATE: February 10, 2009
City Engineer Gus Psihoyos is recommending acceptance of the construction contract
for the 911 High Bluff Retaining Wall Repair Project, as completed by Arensdorf
Trucking & Excavating, Inc., in the final contract amount of $112,371.04. This cost was
$8,952.12 higher than anticipated due to the fact that an additional 10 feet of wall
needed repair to securely fasten it to either end of the existing retaining wall.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
,. ~ L~
Mic ael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
THE CITY OF Dubuque
DT T~ ~ AA-Ameri~aCny
LJ
Masterpiece on the Mississippi
2007
TO: Michael C. Van Milligen, City Man
FROM: Gus Psihoyos, City Engineer .
~.-
SUBJECT: 911 High Bluff Retaining Wall Repair Project
CIP 3502089
DATE: February 9, 2009
INTRODUCTION
The enclosed resolution provides for the acceptance of the construction contract for the 911
High Bluff Retaining Wall Repair Project.
BACKGROUND
On October 13, 2008, the City Council authorized (Resolution 359-08) emergency repairs to a
retaining wall on private property behind 911 High Bluff and street pavement of Thomas Place.
This project was necessitated due to the impending collapse of the private retaining wall
endangering the private residence and also the nearby street pavement. The property owner
of 911 High Bluff was notified by the City that it was proceeding with the repair due to the
property owner's failure to complete the work in a timely manner.
Based on Iowa Code § 384.103 and § 364.12(3)(c), and through the competitive quotation
process for public improvements, this project was awarded on October 20, 2008 to Arensdorf
Trucking & Excavating, Inc. of Anamosa, Iowa, in the amount of $103,418.92.
DISCUSSION
The 911 High Bluff Retaining Wall Repair Project was completed by Arensdorf Trucking &
Excavating, Inc. of Anamosa, Iowa, in the final contract amount of $112,371.04.
Award Final
Construction Contract
Contingency
Construction Engineering & Inspection
Total Project Cost
$103,418.92 $112,371.04
10,341.89
0
17.064.12 27,368.19
$130,824.93 $139,739.23
The increased construction cost is based on the need to remove and repair an additional 10
feet of wall so that the wall repair is securely fastened to either end of the existing retaining
wall.
At a later Council meeting, the Engineering Department will request a public hearing to
approve an assessment for the property owner of 911 High Bluff Street.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment of the
contract in the amount of $112,371.04 to Arensdorf Trucking & Excavating, Inc. for the 911
High Bluff Retaining Wall Repair Project.
BUDGET IMPACT
The project funding summary is as follows:
CIP No. Fund Description
3502089 High Bluff/Thomas Wall
Total Project Funding
Fund Amount
$139,739.23
$139,739.23
Due to the project cost, the associated street repair of Thomas Place will be handled as a
separate project. It is the intent of the Engineering Department to initiate this project in spring,
2009, as part of the City's annual street program.
ACTION TO BE TAKEN
I respectfully request that the City Council adopt the attached resolution accepting the
improvements and authorizing payment of the contract in the amount of $112,371.04 to
Arensdorf Trucking & Excavating, Inc. for the 911 High Bluff Retaining Wall Repair Project.
Prepared by Jon Dienst, PE
cc: Barry Lindahl, City Attorney
Jenny Larson, Budget Director
Bob Schiesl, Assistant City Engineer
RESOLUTION NO. 51-09
ACCEPTING THE 911 HIGH SLUFF RETAINING WALL REPAIR PROJECT AND
AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE
CONTRACTOR
Whereas, the Public Improvement Contract for the 911 High Bluff Retaining Wall
Repair .Project (the Project) has been completed and the City Engineer has examined
the work and filed a certificate stating that the Project has been completed according to
the terms of the Public Improvement Contract and that the City Engineer recommends
that the Project be accepted; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the High Bluff/Thomas Wall Capital Improvement Program appropriation (GIP#3502089)
for the contract amount of $112,371.04 less any retained percentage provided for
therein as provided in Iowa Code chapter 573, and to pay such retainage only in
accordance with the provisions of Iowa Code chapter 573.
Passed, approved and adopted this 16th day of February, 2009.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE 911 HIGH
SLUFF RETAINING WALL REPAIR PROJECT
The undersigned City Engineer of the Ci#y of Dubuque, Iowa, hereby certifies that
he has inspected the 911 High Bluff Retaining Wall Repair Project, that the Project has
been performed in compliance with the terms of the Public Improvement Contract, and
that the total cost of the completed work is $139,739.23.
Dated this 11th day of February, 2009.
City Engineer
Filed in the office of the City Clerk on the 11th day of February, 2009.
Jeanne F. Schneider, CMC, City Clerk
THE CTTY OF
DUB E
Masterpiece on the Mississippi
'ARTIAL PAYMENT NO:
City of Dubuque -Engineering Division
Council Final Payment Form
COUNCIL FINAL
PROJECT NAME: 911 HIGH BLUFF RETAINING WALL REPAIR
DATE: February 6, 2009
CONTRACTOR: ARENSDORF EXCAVATING & TRUCKING, INC. CONTRACT AMOUNT: 5103,418.92
BID ITEM DESCRIPTION UNIT UNIT COST OUANTITY AMOUNT EARNED
TO DATE TO DATE
DEMOLITION & REMOVAL
1 Structure Removal LS $ 22,684.21 1.00 $ 22,684.21
2 Excavation (Unclassified) CY $ 3.85 340.00 $ 1,309.00
3 Remove Railing & Posts LF $ 5.56 110.00 $ 611.60
STONE & PAVEMENT
4 PC Concrete Pavement, (7") w/Integral Curb, Class "C" SY $ 45.00 $ -
5 Graded Stone Base, 3/4" TONS $ 13.07 73.18 $ 956.46
6 HMA 300k Surface Course, 1/2" (PG 64-22) TONS $ 70.00 $ -
7 PC Concrete Curb & Gutter, 2.5' Construct LF $ 20.00 $ -
8 PC Concrete Sidewalk, 4" Construct SF $ 5.56 $ -
SANITARY SEWER
9 8" DIP w/Bedding LF $ 43.87 $ -
10 8" x 4" DIP Tee EA $ 385.00 $ -
11 4" DIP Lateral w/ Bedding LF $ 16.59 $ -
12 Locate Existing Lateral/Exploration EA $ 497.37 $ -
RETAINING WALL ITEMS
13 Structural Concrete CY $ 652.48 66.25 $ 43,226.80
14 Engineered Fill TONS $ 14.77 139.46 $ 2,059.82
15 Satisfactory Soil CY $ 11.03 $ -
16 Geofoam Fill CY $ 90.00 75.30 $ 6,777.00
17 Geotextile Fabric SY $ 8.33 88.00 $ 733.04
18 4" Perforated CPE Drain Tile
19 Chain Link Fence
LF $ 6.76 67.00 $ 452.92
LF $ 44.69 105.25 $ 4,703.62
MISCELLANEOUS
20 Sawcut Pavement -Regardless of Type LF $ 4.00 $ -
21 Erosion Control Plan -Operating Procedures LS $ 842.11 1.00 $ 842.11
22 Traffic Control and Safety Control LS $ 555.56 1.00 $ 555.56
23 Mobilization & Miscellaneous LS $ 9,911.58 0.95 $ 9,416.00
TOTAL AMOUNT EARNED TO DATE: $ 94,328.15
CHANGE ORDER -EXTRA WORK ITEMS
Macadam under Footing TONS $15.53 42.42 $ 658.78
Structure Removal LS $16,000.00 1.00 $ 16,000.00
Sawcutting of Wall Footing LF $4.00 18.00 $ 72.00
Geofoam CY $62.75 20.91 $ 1,312.10
TOTAL AMOUNT EARNED TO DATE -CHANGE ORDERS: E 18,042.89
TOTAL AMOUNT EARNED TO DATE: E 112,371.04
TOTAL DUE CONTRACTOR: S 112,371.04
ENGINEERING: S 27,368.19
TOTAL CONSTRUCTION COST: S 139,739.23
CERTIFICATE OF THE CITY MANAGER:
I hereby certify that the above statement shows in detail the correct amount of all work required to complete the
above improvement.
APPROVED:
Michael V ' igen, City Man ger
City of D b ,Iowa
APPROVED:
Gus Psihoyos, City Engineer
City of Dubuque, Iowa
CERTIFICATE OF THE CONTRACTOR:
The undersigned, Arensdorf Excavating & Trucking, Inc. contractor for the above improvement, does
hereby accept the above "Total Due Contractor", as full,Gs}e-~ttlement for all claims for said improvement.
CONTRACTOR: ~~~- ~ S i~v~-~ ~~~~' 1
TITLE: ~ ''"`~
DATE: '~ ~~ ~ - ~~
City of Dubuque -Engineering Division
THE CITY OF Council Final Payment Form
DUB E
Masterpiece on the Mississippi
'ARTIAL PAYMENT NO: COUNCIL FINAL DATE: February 6, 2009
PROJECT NAME: 911 HIGH BLUFF RETAINING WALL REPAIR
CONTRACTOR: ARENSDORF EXCAVATING 8 TRUCKING, INC. CONTRACT AMOUNT: $103,418.92
QUANTITY AMOUNT EARNED
BID ITEM DESCRIPTION UNIT UNIT COST TO DATE TO DATE
DEMOLITION & REMOVAL
1 Structure Removal LS $ 22,684.21 1.00 $ 22,684.21
2 Excavation (Unclassified) CY $ 3.85 340.00 $ 1,309.00
3 Remove Railing & Posts LF $ 5.56 110.00 $ 611.60
STONE & PAVEMENT
4 PC Concrete Pavement, (7") w/Integral Curb, Class "C" SY $ 45.00 $ -
5 Graded Stone Base, 3/4" TONS $ 13.07 73.18 $ 956.46
6 HMA 300k Surface Course, 1/2" (PG 64-22) TONS $ 70.00 $ -
7 PC Concrete Curb & Gutter, 2.5' Construct LF $ 20.00 $ -
8 PC Concrete Sidewalk, 4" Construct SF $ 5.56 $ -
SANITARY SEWER
9 8" DIP w/Bedding LF $ 43.87 $ -
10 8" x 4" DIP Tee EA $ 385.00 $ -
11 4" DIP Lateral w/ Bedding LF $ 16.59 $ -
12 Locate Existing Lateral/Exploration EA $ 497.37 $ -
RETAINING WALL ITEMS
13 Structural Concrete CY $ 652.48 66.25 $ 43,226.80
14 Engineered Fill TONS $ 14.77 139.46 $ 2,059.82
15 Satisfactory Soil CY $ 11.03 $ -
16 Geofoam Fill CY $ 90.00 75.30 $ 6,777.00
17 Geotextile Fabric SY $ 8.33 88.00 $ 733.04
18 4" Perforated CPE Drain Tile LF $ 6.76 67.00 $ 452.92
19 Chain Link Fence LF $ 44.69 105.25 $ 4,703.62
MISCELLANEOUS
20 Sawcut Pavement -Regardless of Type LF $ 4.00 $ -
21 Erosion Control Plan -Operating Procedures LS $ 842.11 1.00 $ 842.11
22 Traffic Control and Safety Control LS $ 555.56 1.00 $ 555.56
23 Mobilization & Miscellaneous LS $ 9,911.58 0.95 $ 9,416.00
TOTAL AMOUNT EARNED TO DATE: $ 94 328.15
CHANGE ORDER -EXTRA WORK ITEMS
Macadam under Footing TONS $15.53 42.42 $ 658.78
Structure Removal LS $16,000.00 1.00 $ 16,000.00
Sawcutting of Wall Footing LF $4.00 18.00 $ 72.00
Geofoam CY $62.75 20.91 $ 1,312.10
TOTAL AMOUNT EARNED TO DATE -CHANGE ORDERS: S 18,042.89
TOTAL AMOUNT EARNED TO DATE: S 112,371.04
TOTAL DUE CONTRACTOR: 3 112,371.04
ENGINEERING: 5 27,368.19
TOTAL CONSTRUCTION COST: S 139,739.23
CERTIFICATE OF THE CITY MANAGER:
I hereby certify that the above statement shows in detail the correct amount of all work required to complete the
above improvement.
APPROVED:
Michael Van anager
City of u e, Iowa `~~~
APPROVED:
Gus Psihoyos, City Engineer
City of Dubuque, Iowa
CERTIFICATE OF THE CONTRACTOR:
The undersigned, Arensdorf Excavating 8 Trucking, Inc. contractor for the above improvement, does
hereby accept the above "Total Due Contractor", as full settlement for all claims for said improvement.
CONTRACTOR: !~ ~~~,~~--z~~c.~v.:.L~~,~
T
~ ``
BY: ~- ' ~ ~~-'~.
TITLE: ,~ ~ ~
DATE: `~ ~ ~~~
THE CITY OF
DUB E
Masterpiece on the Mississippi
MARTIAL PAYMENT NO:
City of Dubuque -Engineering Division
Council Final Payment Form
COUNCIL FINAL
PROJECT NAME: 911 HIGH BLUFF RETAINING WALL REPAIR
~FQY:: A " t c'J I~^"L'J t.,,Y?,, k.:.l` 1 :..1; ~.tiX..~/
Y
DATE: February 6, 2009
CONTRACTOR: ARENSDORF EXCAVATING & TRUCKING, INC. CONTRACT AMOUNT: x103,418.92
QUANTITY AMOUNT EARNED
BID ITEM DESCRIPTION UNIT UNIT COST TO DATE TO DATE
DEMOLITION & REMOVAL
1 Structure Removal LS $ 22,684.21 1.00 $ 22,684.21
2 Excavation (Unclassified) CY $ 3.85 340.00 $ 1,309.00
3 Remove Railing & Posts LF $ 5.56 110.00 $ 611.60
STONE 8~ PAVEMENT
4 PC Concrete Pavement, (7") wllntegral Curb, Class "C" SY $ 45.00 $ -
5 Graded Stone Base, 314" TONS $ 13.07 73.18 $ 956.46
6 HMA 300k Surface Course, 1/2" (PG 64-22) TONS $ 70.00 $ -
7 PC Concrete Curb & Gutter, 2.5' Construct LF $ 20.00 $ -
8 PC Concrete Sidewalk, 4" Construct SF $ 5.56 $ -
SANITARY SEWER
9 8" DIP w/Bedding LF $ 43.87 $ -
10 8" x 4" DIP Tee EA $ 385.00 $ -
11 4" DIP Lateral w/ Bedding LF $ 16.59 $ -
12 Locate Existing Lateral/Exploration EA $ 497.37 $ -
RETAINING WALL ITEMS
13 Structural Concrete CY $ 652.48 66.25 $ 43,226.80
14 Engineered Fill TONS $ 14.77 139.46 $ 2,059.82
15 Satisfactory Soil CY $ 11.03 $ -
16 Geofoam Fill CY $ 90.00 75.30 $ 6,777.00
17 Geotextile Fabric SY $ 8.33 88.00 $ 733.04
18 4" Perforated CPE Drain Tile LF $ 6.76 67.00 $ 452.92
19 Chain Link Fence LF $ 44.69 105.25 $ 4,703.62
MISCELLANEOUS
20 Sawcut Pavement -Regardless of Type LF $ 4.00 $ -
21 Erosion Control Plan -Operating Procedures LS $ 842.11 1.00 $ 842.11
22 Traffic Control and Safety Control LS $ 555.56 1.00 $ 555.56
23 Mobilization & Miscellaneous LS $ 9,911.58 0.95 $ 9,416.00
TOTAL AMOUNT EARNED TO DATE: S 94,328.15
CHANGE ORDER -EXTRA WORK ITEMS
_ Macadam under Footing TONS $15.53 42.42 $ 658.78
Structure Removal LS $16,000.00 1.00 $ 16,000.00
Sawcutting of Wall Footing LF $4.00 18.00 $ 72.00
Geofoam CY $62.75 20.91 $ 1,312.10
TOTAL AMOUNT EARNED TO DATE -CHANGE ORDERS: b 18,042.89
TOTAL AMOUNT EARNED TO DATE: x 112,371.04
TOTAL DUE CONTRACTOR: S 112,371.04
ENGINEERING: S 27,368.19
TOTAL CONSTRUCTION COST: ~ 139,739.23
CERTIFICATE OF THE CITY MANAGER:
I hereby certify that the above statement shows in detail a Corr t amount of all work required to complete the
above imp v ent V ~"'
APPROVED:
Michael Van Mi ' n, ity ager
City of D ,Iowa
APPROVED:
Gus Psihoyos, City Engineer
City of Dubuque, Iowa
CERTIFICATE OF THE CONTRACTOR:
The undersigned, ArensdorF Excavating & Trucking, Inc. contractor for the above improvement, does
hereby accept the above "Total Due Contractor", as full settlement for al claims for said improvement.
CONTRACTOR: ~ ~ ~ci~z~,~
- ~..
BY: _ ~_,
TITLE: .P/r-
DATE: ~ C - O j