Asphalt Overlay Access Ramp Project Three Acceptance Copyrighted
December 18, 2017
City of Dubuque Consent Items # 22.
ITEM TITLE: Asphalt OverlayAccess Ramp Project Three Acceptance
SUMMARY: City Manager recommending acceptance of the
construction contract for the 2017 Asphalt Overlay Access
Ramp Project Three as completed by Midwest Concrete,
Inc.
RESOLUTION Accepting the 2017 Asphalt Overlay
Access Ramps Project Three and authorizing the payment
of the contract amount to the contractor
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s)
ATTACHMENTS:
Description Type
2017 Asphalt Overlay Access Ramp Project Three-NNM City Manager Memo
Memo
Staff Memo Staff Memo
Engineer's Certificate Executed Supporting Documentation
Resolution Resolutions
THE CITY OF Dubuque
�
AIFA�erlwGh
UB E '�� III►
Masterpiece on the Mississippi Z°°'�w'2
7A13 2017
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 2017 Asphalt Overlay Access Ramp Project Three
(CIP 2501227) (CIP 3001615)
DATE: December 12, 2017
City Engineer Gus Psihoyos is recommending acceptance of the construction contract
for the 2017 Asphalt Overlay Access Ramp Project Three, as completed by Midwest
Concrete, in the final contract amount of$89,047.25, which was 11 .57°k over the
contract amount of$79,815.49. The overage was for extra sidewalk and curb costs
associated with the new traffic signal installations at Windsor Avenue and E 22"d Street
and for two additional ramps installed at Queen Street and 22"d Street. Sufficient funds
have been identified.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�� �� ���
Mic ael C. Van Milligen �� �
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Teri Goodmann, Assistant City Manager
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
THE CITY OF Dubuque
�
D `J � E Aq•A�c�ki Cit�
ll� ��1
Il
Masterpiece on the Mississippi x°°''z°1Z
xoia•zai7
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
. .
SUBJECT: 2017 Asphalt Overlay Access Ramp Project Three
(CIP 2501227) (CIP 3001615)
DATE: December 11, 2017
INTRODUCTION
The enclosed resolutions provide for the acceptance of the construction contract for the
2017 Asphalt Overlay Access Ramp Project Three.
BACKGROUND
The project replaced twenty-four non-compliant access ramps with thirty-four compliant,
directional ramps as per Public Right of Way Accessibilities Guidelines (PROWAG)
specifications in conjunction with the Public Works Asphalt Overlay Program and
involved the intersections of:
• Windsor Avenue and Garfield Avenue, two ramps
• Windsor Avenue and Rhomberg Avenue, two double ramps and two single
ramps
• Windsor Avenue and Lincoln Avenue, two double Ramps and two single ramps
• Windsor Avenue and Providence Street four single ramps
• Windsor Avenue and E 22nd Street, four double ramps
• Windsor Avenue and Regent Street, two single ramps
• Windsor Avenue and E 24th Street, two single ramps
• E 22�d Street and Queen Street, two single ramps
DISCUSSION
The 2017 Asphalt Overlay Access Ramp Project Three was completed by Midwest
Concrete of Peosta, lowa in the final contract amount of$89,047.25, 11.57% over the
contract amaunt of$79,815.15. The overagP was for extra sidewalk and curb costs
�associated with the new traffic signal installations at Windsor Avenue and E 22�d Street.
Also, two additional ramps were installed at Queen Street and 22nd Street. The average
cost per ramp was $2,663.97.
BUDGET IMPACT
The project cost summary for the 2017 Asphalt Overlay Access Ramp Project Three is
as follows:
Award Final
Construction Contract $79,815.15 $89,047.25
Contingency $7,981.52 $9,232.10
Construction Engineering & Inspection $11,972.27 5 532.77
Total Project Cost 99 768.94 $103,812.12
The funding summary for the project is as follows:
CIP Fund Description Fund
- Amount
2501227 Curb Ramp Program $100,011.80
3001615 Signal Intersection Reconstruct 3 800.32
Total Project Funding . $103.812.12
REQUESTED ACTION
The City Council is requested to adopt the attached resolutions accepting the
improvements and establish the final contract amount of$89,047.25 for the 2017
Asphalt Overlay Access Ramp Project Three.
Prepared by Tom Kopp, Engineering Technician
cc: John Klostermann, Public Works Director
Renee Tyler, Asst. Public Works Director
Jenny Larson, Budget Director
Jon Dienst, Civil Engineer II
Paul Davis Public Works Supervisor
2
RESOLUTION NO. 392-17
ACCEPTING THE 2017 ASPHALT OVERLAY ACCESS RAMPS PROJECT THREE
AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE
CONTRACTOR
Whereas, the Public Improvement Contract for the 2017 Asphalt Overlay Access
Ramps Project Three (the Project) has been completed and the City Engineer has
examined the work and filed a certificate stating that the Project has been completed
according to the terms of the Public Improvement Contract and that the City Engineer
recommends that the Project be accepted; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the Curb Ramp Program appropriations and the signal intersection reconstruct
appropriations for the contract amount of $89,047.25, Tess any retained percentage
provided for therein as provided in Iowa Code chapter 573, and to pay such retainage
only in accordance with the provisions of Iowa Code chapter 573.
Attest:
Passed, approved and adopted this 18th day of December ?17.
K in S. Firnstahl, CMC, City Clerk
h
Roy D. Buol, Mayor
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE 2017 ASPHALT
OVERLAY ACCESS RAMPS PROJECT THREE
The �re�er�igned Cit;r Engir���r of#h� Ci#;� of �ubuqu�, lo�,��, h�r�by� c�rtifi�� that
he has inspected the 2017 Asphalt Overlay Access Ramps Project Three, that the
Project has been performed in compliance with the terms of the Public Improvement
Contract, and that the total cost of the completed work is $103,812.12.
-��---- � ��
Dated this��' day of e�-ea�.2017.
Gus Psihoyos, City Engine r
Filed in the office of the City Clerk on the - day o '''r„��,�� ,��"� . ; 2017.
: evin Fir�ista I, CMC, City Clerk