Fiscal Year 2017 CIPP Sanitary Sewer Lining Project Acceptance Copyrighted
January 3, 2018
City of Dubuque Consent Items # 10.
ITEM TITLE: Fiscal Year 2017 CIPP Sanitary Sewer Lining Project
Acceptance
SUMMARY: City Manager recommending acceptance of the public
improvement construction contract for the FY2017 Sanitary
Sewer Cured-in-Place Pipe (CI PP) Lining Project, as
completed by Insituform Technologies.
RESOLUTION Accepting the FY17 Sanitary Sewer Cured-
in-Place (CI PP) Lining Project and authorizing the payment
to the contractor
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s)
ATTACHMENTS:
Description Type
CIPP Sanitary Sewer Lining Project-NNM Memo City Manager Memo
Staff Memo Staff Memo
Resolution Resolutions
Engineers Certificate- E�cuted Supporting Documentation
THE CITY OF Dubuque
�
AIFA�erlwGh
UB E '�� III►
Masterpiece on the Mississippi Z°°'�w'2
7A13 2017
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: FY17 (CIPP) Sanitary Sewer Lining Project
CIP 7101637, 7101335
DATE: December 22, 2017
City Engineer Gus Psihoyos is recommending acceptance of the public improvement
construction contract for the FY2017 Sanitary Sewer Cured-in-Place Pipe (CIPP) Lining
Project, as completed by Insituform Technologies, in the final contract amount of
$156,663.10, which is an 18.9°k decrease from the original contract amount of
$193,131 .40. Most of the cost savings was due to reduced sanitary sewer service
inspection costs.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�� �� ���
Mic ael C. Van Milligen �� �
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Teri Goodmann, Assistant City Manager
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
THE CITY OF Dubuque
�
�� AH•A�Erict City
L�U� � '� �
l��l.
Masterpiece on the Mississippi �DOr Z�12
zox�•zox�
TO: Michael C. Van Milligen, City Manager�
,
4_� a � �
FROM: Gus Psihoyos, Cify Engineer .�.� �
SUBJECT: FY17 (CIPP) Sanitary Sewer Lining Project
CIP 7101637, 7101335
DATE: December 20, 2017
INTRODUCTION
The enclosed resolution provides for the acceptance of the public improvement
construction contract for the FY2017 Sanitary Sewer Cured-in-Place Pipe (CIPP) Lining
Project.
BACKGROUND
The City of Dubuque, lowa is under a Consent Decree according to Case
2:11-cv-01001-EJM, United States of America and the State of lowa v. the City of
Dubuque, IA (N.D. lowa), Civil Action Number 2008V00041, DOJ Case Number
90-5-1-1-09339 effective June 27, 2011. The City is required to submit Corrective Action
plans for each of the Sanitary Sewersheds identified in the Consent Decree. The FY16
budget appropriated funds for sanitary sewer rehabilitative improvements in the
Consent Decree Correction Action Plans for Sewershed 5 and 12. Work is also
scheduled in Sewershed 6.
The FY16 (CIPP) Sanitary Sewer Lining Project was determined from flow monitoring
and smoke testing activities completed by engineering staff in Sewersheds 5, 6 and 12;
in addition to those sewers identified during Public Works maintenance activities such
as cleaning, televising, and following up on customer issues. The Project involved the
rehabilitation of 6,239 feet of sanitary sewer main as well as cementitious spray lining of
58 vertical feet of brick manholes.
DISCUSSION
The FY17 (CIPP) Sanitary Sewer Lining Project was completed by Insituform
Technologies of Chesterfield, Missouri, in the final contract amount of $156,663.10
which is a 18.9% decrease from the original contract amount of$193,131.40. Most of
the cost savings was due to reduced sanitary sewer service inspection costs. The
contractor was able to verify the lateral connections were good but unable in most
cases to televise the laterals themselves due to tight bends in the pipe.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment
of the contract amount of$156,663.10 to Insituform Technologies, for the FY17 (CIPP)
Sanitary Sewer Lining Project.
BUDGETIMPACT
The summary of project costs for the FY17 (CIPP) Sanitary Sewer Lining Project is as
follows:
Award Final
Construction Contract $193,131.40 $156,663.10
Contingency 25,768.00 0.00
Construction Engineering & Inspection 42,517.20 15,666.31
Total Project Cost 2 1 416.60 172.329.41
This project funding is as follows:
CIP No. Fund Description Fund Amount
7101637 Sanitary Sewer Lining Program $164,204.26
7101335 Sanitary Sewer Manhole Replacement 8,125.15
Total Project Funding 72.329.41
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolution to accept the
improvements and to authorize the payment of the contract amount of$156,663.10 to
Insituform Technologies, for the FY 17 (CIPP) Sanitary Sewer Lining Project.
Prepared by: Jon Dienst, P.E.
cc: Jenny Larson, Budget Director
Deron Muehring, Civil Engineer II
Denise Ihrig, Water Department Manager
Charlie Gau, Engineering Technician
2
RESOLUTION NO. 3-18
ACCEPTING THE FY17 SANITARY SEWER CURED -IN-PLACE PIPE (CIPP) LINING
PROJECT AND AUTHORIZING THE PAYMENT TO THE CONTRACTOR
WHEREAS, the public improvement contract for the FY17 Sanitary Sewer Cured -in -
Place Pipe (CIPP) Lining Project (the Project) has been completed by the Contractor,
Insituform Technologies (Contractor), the City Engineer has examined the work and
recommends that the Project be accepted; and
WHEREAS, the final contract amount for the Project is $156,663.10;
WHEREAS, the Contractor has previously been paid $148,829.95, leaving a balance
of $7,833.16; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved, and the Project is
hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of $7,833.16 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa
Code chapter 26.13.
Passed, approved and adopted this 3rd day of January 201
.4 0 L
ROY D,uol, Mayor
Attest:
Ke in S. Firnsfahl, CMC City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE FY16
SANITARY SEWER CURED-IN-PLACE PIPE (CIPP) LINING PROJECT
The undersigned City Engineer of the City of Dubuque, lowa, hereby certifies that
he has inspected the FY17 Sanitary Sewer Cured-in-Place Pipe (CIPP) Lining Project
has been performed in compliance with the terms of the Public Improvement Contract,
and that the total cost of the completed work is $172,329.41. �
!k+^r� �. 9 � 8 � �
Dated thisf ��.. day of;:��,�'�"�:1-�R���; 2017. i
` ��r� r� �M,.,��,..�,,� I= j
�
r ,rf.
,� `
, e
�'s � �_�w�`^'�A� (.�'�,'��,��'-`" II
Gus �sihoyos, City Engineer �
Filed in the office of the City Clerk on the�� ay of ��017. '�I
�.'.__... � u
�
vi S. irns h , C C, City Clerk li
� �
i
�
�
�
�
�
�
�
�
�
�
9
�
�