Eagle Point Water Plant Clear Well Phase II Dubuque THE CITY OF D't T~ ~ ~ J Ap-AmericaCi~p ,,, ~ asterpiece on the Mississippi ,; 1 ~, 2007 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Eagle Point Water Plant West Clear Well Phase II Pipe Coating Project - CIP 7401828 - 62712 DATE: July 15, 2009 Sealed bids were received for the Eagle Point Water Plant West Clear Well Phase II Pipe Coating Project on April 8, 2009. K&W Coating, LLC submitted the low bid in the amount of $35,000. This amount is approximately 32.5% under the estimate of probable cost. Since then it was discovered that K&W Coating could not comply with the City of Dubuque's insurance requirements. The City is now proceeding with the recommendation in awarding the project to the second low bidder, Superior Painting & Epoxy Coating, LLC in the amount of $36,256, which is approximately 30% under the estimate of probable cost. I concur with the recommendation and respectfully request Mayor and City Council approval. ., Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Bob Green, Water Department Manager THE CITY OF Dubuque ._ ~' DUB E "'"~'~~~~ 1 1 Masterpiece on the Mississippi 2007 TO: Michael C. Van Milligen, City Manager FROM: Bob Green, Water Department Manager SUBJECT: Eagle Point Water Plant West Clear Well Phase II Pipe Coating Project - C I P 7401828 - 62712 DATE: July 7, 2009 INTRODUCTION: Through City Council Action, on May 4, 2009, authorization was approved to proceed with K & W Coating, LLC of Elkader, Iowa, to complete this phase of the project in the amount of $35,000. DISCUSSION: Since the awarding of this project to K & W Coating, LLC, staff and I have been working with them in an effort for them to comply with the contract specifications for this project. Through several discussions and requests, it was discovered that K & W Coating, LLC could not comply with the City of Dubuque's insurance requirements for this project. As a result of this we are recommending through the attached Resolutions that the offer to K & W Coating, LLC of Elkader be rescinded and that the project be awarded to the second low bidder, Superior Painting & Epoxy Coating, LLC of Urbandale, Iowa in the amount of $36,256. Representatives from Superior Painting have advised us that they have no issues in meeting the City's insurance requirements. They have agreed to honor their original bid price and a new proposed construction schedule should they be awarded the project. It is our recommendation to hold K & W Coating of Elkader, Iowa accountable for the bid price difference of the two in the amount of $1,256 through their bond. SUMMARY: Sealed bids were received for the project on April 8, 2009. K & W Coating, LLC of Elkader, Iowa submitted the low bid in the amount of $35,000. This amount is approximately 32.5% under the estimate of probable cost. Since then it was discovered that K & W Coating could not comply with the City of Dubuque's insurance requirements. We are now proceeding with the recommendation in awarding the project to the second low bidder, Superior Painting & Epoxy Coating, LLC of Urbandale, Iowa in the amount of $36,256 which is approximately 30% under the estimate of probable cost. A summary of the bid proposals received are as follows: COMPANY LOCATION BID AMOUNT 1. K & W Coating, LLC Elkader, IA $35,000 2. Superior Painting Urbandale, IA $36,256 3. Klauer Construction Dubuque, IA $38,000 4. TMI Coating St. Paul, MN $48,400 5. Pospisil Painting Cedar Rapids, IA $60,620 RECOMMENDATION: The bid proposals for this project have been reviewed by the Water Department's Consultant Firm, V & K Engineering of West Des Moines. It is their recommendation to proceed with the second low bidder, Superior Painting & Epoxy, LLC of Urbandale, Iowa. This project phase has been reviewed and approved by the Iowa Department of Natural Resources SRF Clerk-Specialist, Eunice Boyd. This review and approval process is required when State Revolving Funds are to be used. Staff and I concur with the recommendation(s) and request that the original contract offer awarded to K & W Coating, LLC of Elkader, Iowa in the amount of $35,000 be rescinded and the new contract be awarded to the second low bidder, Superior Painting & Epoxy Coating, LLC of Urbandale, Iowa in the amount of $36,256. BUDGET IMPACT: The estimate of probable cost for the Clear Well Rehabilitation Pipe Coating Project is summarized as follows: Estimate: Construction Contract $ 40,000 Contingency 6,000 Construction Engineering & Inspection 6,000 Total Estimated Rehabilitation Coating Cost $ 52,000 The interior coating to the west tank transmission pipes was scheduled to take place under a separate contract immediately following completion of the construction rehabilitation to the structure of this tank. The following fund summary is as follows: Funding for this project has been secured through prior approval of a state revolving loan fund. CIP NO. FUND DESCRIPTION FUND BALANCE AMOUNT 7401828 Clear Well Rehabilitation Project $168,915 ACTION TO BE TAKEN: I respectfully request that the City Council adopt the attached Resolutions, one in rescinding the Eagle Point Water Plant Clear Well Reservoir Rehabilitation Phase II (Pipe Coating) Project from K & W Coating, LLC of Elkader, Iowa in the amount of $35,000 and approving the second Resolution in awarding this project to Superior Painting & Epoxy, LLC of Urbandale, Iowa in the amount of $36,256. Prepared by Bob Green, Water Department Manager ve Attachments cc: Jenny Larson, Budget Director Jackie Vanek, Water Plant Manager File RESOLUTION NO. 239-09 RESCINDING RESOLUTION NO. 142-09 AWARDING THE PUBLIC IMPROVEMENT CONTRACT FOR THE EAGLE POINT WATER PLANT CLEAR WELL RESERVOIR PHASE II REHABILITATION (PIPE COATING) PROJECT TO K&W COATING, LLC Whereas, Resolution No. 142-09 awarded the public improvement contract to K & W Coating, LLC of Elkader, Iowa for the Eagle Point Water Plant Clear Well Reservoir Phase II Rehabilitation (Pipe Coating) Project; and Whereas, K & W Coating, LLC has failed to meet and comply with the contract insurance requirements for this project. Now therefore, be it resolved by the City Council of the City of Dubuque, Iowa: That Resolution No. 142-09 be and is hereby rescinded. Passed, approved and adopted this loth day of ~1uly, 2009. Roy D,l~uol, Mayor Attest: ,f `~ "-'' eanne F. Schneider, CMC, City Clerk RESOLUTION NO. 240-09 AWARIND THE PUBLIC IMPROVEMENT CONTRACT FOR THE EAGLE POINT WATER PLANT CLEAR WELL RESERVOIR PHASE II REHABILITATION (PIPE COATING) PROJECT O SUPERIOR PAINTING & EPOXY COATING, LLC Whereas, sealed proposals were submitted by contractors for the Eagle Point Water Plant Clear Well Reservoir Phase II Rehabilitation (Pipe Coating) Project (the Project) pursuant to Resolution 116-09; and Whereas, Resolution No. 142-09 awarded the public improvement contract to K & W Coating, LLC of Elkader, Iowa for the Project; and Whereas, K & W Coating, LLC failed to meet and comply with the contract insurance requirements for the Project; and Whereas, Resolution No. 142-09 has been rescinded; and Whereas, Superior Painting & Epoxy Coating, LLC of Urbandale, Iowa with a bid in the amount of $36,125 is the next lowest responsive, responsible bidder for the Project. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That a Public Improvement Contract for the Project is hereby awarded to Superior Painting ~ Epoxy Coating, LLC of Urbandale, Iowa and the City Manager is hereby directed to execute a Public Improvement Contract on behalf of the City of Dubuque for the Project. 20th Passed, approved and adopted this day of July , 2009. ~'% t F ~~ ~` p,s ; , ~~,-~ ~„ t ~ Roy DJBuol, Mayor Attest: /~ Jeanne F. Schneider, CMC, City Clerk