TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Heeb Street Retaining Wall Reconstruction Project
CIP 1002086 -Heeb Street Wall
DATE: September 1, 2009
City Engineer Gus Psihoyos recommends initiation of the bidding process for the Heeb
Street Retaining Wall Reconstruction Project, and further recommends that a public
hearing be set for September 21, 2009.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Mic el C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
THECrrY OF Dubuque
DLTB E ~"'~~'
~ r
Masterpiece on the Mississippi
2007
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
DATE: August 31, 2009
SUBJECT: Heeb Street Retaining Wall Reconstruction Project
CIP 1002086 -Heeb Street Wall
INTRODUCTION
The enclosed resolutions authorize the public bidding procedure for the Heeb Street
Retaining Wall Reconstruction Project.
BACKGROUND
The Heeb Street Retaining Wall is located at the intersection of Kaufmann Avenue and
Heeb Street. This is an existing City-owned limestone retaining wall that is showing signs of
distress (existing stones have broken loose from the wall). The wall height varies from 7
feet to 11 feet, with a wall length of 75 feet. The wall supports Heeb Street (a 20-foot wide
street) and has an 8-inch sanitary sewer main and 4-inch watermain in close proximity.
The Engineering Department has worked with IIW Engineers & Surveyors, PC to analyze
the existing wall. Concrete barriers were placed (summer of 2008) in the parking lot behind
Meineke Muffler at the corner of Heeb Street and Kaufmann Avenue to protect pedestrians
and vehicles from possible falling rock.
DISCUSSION
Engineering is proposing that the project base bid include wall reconstruction with native
Dubuque limestone, with geofoam as a backfill material. This reconstruction would be
similar to the retaining walls at Grove Terrace and St. Mary's Street. The existing wall is
limestone which is why Engineering proposes this as the base bid.
An alternate bid would be installation of an integral, limestone-buff colored concrete wall
that would simulate the look of native limestone. This type of installation was done
successfully at the Loras College Alumni Center.
In order to reconstruct the retaining wall, most of the street will need to be removed to
accommodate the backfill. Along with this work, the watermain and sanitary sewer utilities
will need to be partially reconstructed and protected to accommodate the work. The street
pavement would be 7-inch concrete and match the existing width of 20 feet.
PROJECT SCHEDULE
The schedule for the project is as follows:
Initiate Public Bidding Process
Publish Notice to Bidders, Advertise for Bids
Notice of Public Hearing on Plans & Specifications
Pre-Bid Meeting
Public Hearing
Receipt of Bids
Award Construction Contract
Project Completion Date
RECOMMENDATION
September 8, 2009
September 11, 2009
September 11, 2009
September 15, 2009
September 21, 2009
September 24, 2009
October 5, 2009
November 13, 2009
I recommend that the City Council establish a date for the public hearing and authorize the
City Clerk to advertise for proposals.
BUDGET IMPACT
The estimate of probable cost for the Heeb Street Retaining Wall Reconstruction Project is
as follows:
Estimate
Construction Contract $135,251.00
Contingency (15%) 20,287.65
Construction Engineering & Inspection (15%) 23,330.80
Total Project Cost 5178,869.45
The funding for the Heeb Street Retaining Wall Reconstruction Project will be as follows:
CIP No. Fund Description Fund Amount
1002086 Heeb Street Wall $178,869.45
Total Project Funding 5178,869.45
ACTION TO BE TAKEN
The City Council is requested to establish the date of the public hearing and to authorize
the City Clerk to advertise for proposals through adoption of the enclosed resolutions for
the Heeb Street Retaining Wall Reconstruction Project.
Prepared by Jon Dienst, PE
cc: Jenny Larson, Budget Director
Don Vogt, Public Works Director
Bob Green, Water Department Manager
Bob Schiesl, Assistant City Engineer
RESOLUTION NO. 331-09
HEEB STREET RETAINING WALL RECONSTRUCTION PROJECT
PRELIMINARY APPROVAL OF PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST; SETTING DATE OF PUBLIC HEARING
ON PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED COST;
AND ORDERING THE ADVERTISEMENT FOR BIDS
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
the proposed plans, specifications, form of contract and estimated cost for the
Heeb Street Retaining Wall Reconstruction Project, in the estimated amount
$178,869.45, are hereby preliminarily approved and ordered filed in the office of the
City Clerk for public inspection.
a public hearing will be held on the 21St day of September, 2009, at 6:30 p.m.
in the Historic Federal Building Council Chambers at which time interested persons
may appear and be heard for or against the proposed plans and specifications, form
of contract and estimated cost of said Project, and the City Clerk be and is hereby
directed to cause the attached notice of the time and place of such hearing to be
published in a newspaper having general circulation in the City of Dubuque, Iowa,
which notice shall be published not less than four days nor more than twenty days
prior to the date of such hearing. At the hearing, any interested person may appear
and file objections to the proposed plans, specifications, form of contract, or
estimated cost of the Project.
The Heeb Street Retaining Wall Reconstruction Project is hereby ordered to
be advertised for bids for construction.
The amount of the security to accompany each bid shall be in an amount
which shall conform to the provisions of the Notice to Bidders hereby approved.
The City Clerk is hereby directed to advertise for bids for the construction of
the improvements herein provided, by publishing the attached Notice to Bidders to
be published in a newspaper having general circulation in the City of Dubuque, Iowa,
which notice shall be published not less than four but not more than forty-five days
before the date for filing bids before 2:00 p.m. on the 24t" day of September, 2009.
Bids shall be opened and read by the City Clerk at said time and will be submitted to
the City Council for final action at 6:30 p.m. on the 5t" day of October, 2009, in the
Historic Federal Building Council Chambers (second floor), 350 West 6t" Street,
Dubuque, Iowa.
Passed, adopted and approved this gth
Attest:
r7 / ,
Jeanne F. Schneider, CMC, City Clerk
day Of September , 2009.
.~
2 [/.~/
F b ~fi/'z.~~ti
+ Roy D. 13uo1, Mayor
NOTICE OF PUBLIC HEARING ON
CONTRACT, AND ESTIMATED COST
WALL RECONSTRUCTION PROJECT
PLANS, SPECIFICATIONS, FORM OF
FOR THE HEEB STREET RETAINING
NOTICE IS HEREBY GIVEN: The City Council of the City of Dubuque, Iowa
will hold a public hearing on the proposed plans, specifications, form of contract and
estimated cost for the Heeb Street Retaining Wall Reconstruction Project, in
accordance with the provisions of Chapter 26, Code of Iowa, at 6:30 p.m., on the
21St day of September, 2009, in the Historic Federal Building Council Chambers
(second floor), 350 West 6th Street, Dubuque, Iowa. Said proposed plans,
specifications, form of contract and estimated cost are now on file in the office of the
City Clerk. At said hearing any interested person may appear and file objections
thereto.
The scope of the Project is as follows:
Engineering is proposing that the project base bid include wall reconstruction
with native Dubuque limestone, with geofoam as a backfill material. This
reconstruction would be similar to the retaining walls at Grove Terrace and St.
Mary's Street.
An alternate bid would be installation of an integral, limestone-buff colored
concrete wall that would utilize form liners to simulate native limestone. This type of
installation was done successfully at the Loras College Alumni Center.
In order to reconstruct the retaining wall, most of the street will need to be
removed to accommodate the backfill. Along with this work, the watermain and
sanitary sewer utilities will need to be partially reconstructed and protected to
accommodate the work. The street pavement will be replaced with 7-inch concrete in
the area of the wall reconstruction.
Any visual or hearing-impaired persons needing special assistance or
persons with special accessibility needs should contact the City Clerk's office at
(563) 589-4120 or TDD at (563) 690-6678 at least 48 hours prior to the meeting.
2009.
Published by order of the City Council given on the day of ,
Jeanne F. Schneider, CMC, City Clerk
NOTICE TO BIDDERS
CITY OF DUBUQUE PUBLIC IMPROVEMENT PROJECT
HEEB STREET RETAINING WALL RECONSTRUCTION PROJECT
Time and Place for Filing Sealed Proposals. Sealed bids for the work comprising
each improvement as stated below must be filed before 2:00 p.m. on September 24,
2009, in the Office of the City Clerk, City Hall -First Floor, 50 West 13th Street,
Dubuque, Iowa.
Time and Placed Sealed Proposals Will be Opened and Considered. Sealed
proposals will be opened and bids tabulated at 2:00 ~.m. on September 24, 2009, at
City Hall - Conference Room A, 50 West 13t Street, Dubuque, Iowa, for
consideration by the City Council (Council) at its meeting on October 5, 2009. The
City of Dubuque, Iowa, reserves the right to reject any and all bids.
Time for Commencement and Completion of Work. Work on each improvement
shall be commenced within 10 days after the Notice to Proceed has been issued and
shall be fully completed by November 13, 2009.
Bid Security. Each bidder shall accompany its bid with a bid security as security
that the successful bidder will enter into a contract for the work bid upon and will
furnish after the award of contract a corporate surety bond, acceptable to the
governmental entity, for the faithful performance of the contract, in an amount equal
to one hundred percent of the amount of the contract. The bid security shall be in
the amount of ten percent (10%) of the amount of the contract and shall be in the
form of a cashier's check or certified check drawn on astate-chartered or federally
chartered bank, or a certified share draft drawn on astate-chartered or federally
chartered credit union, or the governmental entity may provide for a bidder's bond
with corporate surety satisfactory to the governmental entity. The bid bond shall
contain no conditions excepted as provided in this section.
Contract Documents. Copies of the construction documents may be obtained at
the Engineering Department, City Hall -Second Floor, 50 West 13th Street,
Dubuque, Iowa 52001. No plan deposit is required.
Preference for Iowa Products and Labor. By virtue of statutory authority,
preference will be given to products and provisions grown and coal produced within
the State of Iowa, and to Iowa domestic labor, to the extent lawfully required under
Iowa statutes.
Sales Tax. The bidder should not include sales tax in its bid. A sales tax exemption
certificate will be available for all material purchased for incorporation in the project.
General Nature of Public Improvement.
Heeb Street Reconstruction Project
CIP 1002086
Engineering is proposing that the project base bid include wall reconstruction with
native Dubuque limestone, with geofoam as a backfill material. This reconstruction
would be similar to the retaining walls at Grove Terrace and St. Mary's Street.
An alternate bid would be installation of an integral, limestone-buff colored concrete
wall that would utilize form liners to simulate native limestone. This type of
installation was done successfully at the Loras College Alumni Center.
In order to reconstruct the retaining wall, most of the street will need to be removed
to accommodate the backfill. Along with this work, the watermain and sanitary sewer
utilities will need to be partially reconstructed and protected to accommodate the
work. The street pavement in the vicinity of the retaining wall repair will be replaced
with 7-inch concrete.
Pre-Bid Construction Conference. Each prospective bidder is encouraged to
attend the Pre-Bid Construction Conference to be held at 3:00 PM on September 15,
2009, at the Conference Room B in City Hall at 50 W. 13th Street, Dubuque, Iowa.
Attendance by all prospective bidders is not mandatory but highly recommended.
Published in the Telegraph Herald, September 11, 2009.
CITY OF DUBUQUE
HEEB STREET RETAINING WALL
ENGINEER'S ESTIMATE
NO. DESCRIPTION QUANTITY UNIT PRICE BID PRICE
1 Mobilization & Miscellaneous LS 1 $12,000.00 $12,000.00
2 Erosion Control LS 1 $1,800.00 $1,800.00
3 Traffic Control LS 1 $2,900.00 $2,900.00
4 Removal of Pavement SY 170 $15.00 $2,550.00
5 Structure Removal LS 1 $12,000.00 $12,000.00
g Excavation (Unclassified) CY 395 $20.00 $7,900.00
7 Limestone SF 720 $60.00 $43,200.00
g Structural Concrete CY 55 $400.00 $22,000.00
g Engineered Fill TON 260 $35.00 $9,100.00
10 Geofoam Fill CY 46.2 $90.00 $4,158.00
11 Drainage Fill TON 45 $25.00 $1,125.00
12 Stone Base TON 70.3 $30.00 $2,109.00
13 Class A Crushed Stone TON 12 $30.00 $360.00
14 2.5' PCC Curb & Gutter LF 72 $30.00 $2,160.00
15 6" HMA Patching SY 125 $45.00 $5,625.00
16 4" Perforated CPE Drain Tile LF 72 $12.00 $864.00
17 Vinyl Coated Chain Link Fence LF 72 $75.00 $5,400.00
Total $135,251.00
Contingency 15% $20,287.65
Total w/ Contingency $155,538.65