TO: Michael C. Van Milligen, City Manager
FROM: Don Vogt, Public Works Director ld
~~/''"~
SUBJECT: Floodwall Levee Slope Stabiliza ontl'" Project (CIP #1002042)
DATE: October 9, 2009
INTRODUCTION
The purposes of this memorandum are to provide information and recommend a course
of action regarding the attached change order for the Floodwall Levee Slope
Stabilization Project (CIP #1002042).
BACKGROUND
$295,000 was budgeted in FY09 for this project. Bid proposals were solicited in
February and a contract awarded to the low bidder, Eastern Iowa Excavating and
Concrete LLC, that same month in the amount of $183,087.50. After retaining an
additional $14,032 for engineering costs and another $18,308.75 for contingency funds,
the remaining budgeted monies were transferred to our department's FY09 snow and
ice control operating budget to cover the deficit due to last winter's above average
snowfall. Actual project work was delayed by the Mississippi River's high water levels
this spring. As a result of those high water levels, the project's first change order
extended the project's completion date -but did not provide for monetary changes.
DISCUSSION
The attached change order (#2) does provide for additional funds ($41,530.41) to be
paid to the contractor. These funds are needed to cover the costs of the additional rip-
rap (+1,629.86sy), bedding stone (+40.31sy), and engineering fabric (+1,070sy)
required to repair a longer section of shoreline than originally planned and specified.
This larger repair project was due to the shoreline erosion being exacerbated by high
water events subsequent to the project's original design. Given the $183,087.50 bid
award amount plus the $18,308.75 contingency, the final contractor's cost to complete
the project of $224,617.91 equals an overage of $23,221.66. Also, the additional
engineering design and inspection needed to address the larger project exceeded the
original engineering allowance by $5,006.50. In total, the project, now completed,
exceeded its authorized award allowance of $215,428.25 by $28,228.16 -but still was
more than $50,000 under the original project appropriation of $295,000.
In recognition that almost $80,000 of the original $295,000 was transferred to the Public
Works Department's snow and ice control operating budget last winter, Street and
Sewer Maintenance Supervisor John Klostermann, by his attached memorandum, is
recommending that the total project overage of $28,228.16 be addressed through the
$44,723.02 unencumbered balance remaining in CIP #3501445 - Floodwall Post-Flood
Repairs.
ACTION STEP
concur with John's recommendation and request that you sign the attached copies (3)
of the project's second and final change order.
CC: Jenny Larson, Budget Director
Attachments
THE CITY OF ^~~ Dubuque
TTTT
~VB
E
1 1
Masterpiece on the Mississippi
2007
TO: Don Vogt, Public Works Director
FROM: John Klostermann, Street/Sewer Maintenance SupervisorQ,~~
SUBJECT: Floodwall Levee Slope Stabilization Project~t-`
Capital Improvement Project #1002042
DATE: October 8, 2009
Introduction
Attached change order number 2 provides for a contract adjustment for measured
quantities related to the Floodwall Levee Slope Stabilization Project.
Discussion
Two change orders have been issued for the project. Change order number 1 changed
the completion date of the project from April 15, 2009 to June 1, 2009. This was
necessary due to high water this spring which delayed the start of the project.
Change order number 2 establishes the final construction contract price at $224,617.91.
The increased cost of the project is due to the differences between the original contract
quantities and the final installed quantities.
Budget Impact
A summary of the project is as follows:
Construction Contract $224,617.91
Engineering 19,038.50
Total $243,656.41
am proposing that the project be funded in the following way:
CIP No. Fund Description Amount
1002042 Floodwall Levee Slope Stabilization Project $215,428.25
3501445 Floodwall Post Flood Repair Project $ 28,228.16
$243,656.41
Action Requested
I am requesting that the City Manager sign the attached change order which establishes
the final construction contract price at $224,617.91.
CHANGE ORDER
Change Order No: 2 FINAL
Date: October 2, 2009
Agreement Date: February 20, 2009
Owner: City of Dubuque
Project: Floodwall Levee Slope Stabilization No. 08215-01
Contractor: Eastern Iowa Excavating & Concrete, LLC
Description of Change:
• Contract adjustment based on measured quantities (see attached sheet).
Justification for Change:
• Field measurement of installed quantities.
Change in Contract Price: ADDITION
Forty one thousand five hundred thirty dollars and forty one cents $41,530.41
Adjustment in Amount of Contract:
1. Amount of Original Contract
2. Net (Addition) (Reduction) due to all previous change orders
3. Amount of contract not including this change order
4. Addition to contract due to this change order
5. Amount of contract including this change order
Change Order Conditions:
$183,087.50
$0.00
$183,087.50
$41,530.41
$224,617.91
The contract completion period established by the original contract and previous change orders will be
INCREASED. The final completion date, prior to this change order, was April 15, 2009. The final
completion date as affected by this change order will be June 1, 2009.
Work performed under this change order will be subject to all the requirements as stated herein and in the
contract documents and all change orders.
The Contractor expressly agrees that he will place under coverage of his Contractor's Improvement Bond
and insurance all work covered by this change order.
All work performed under this change order shall be performed in accordance with the requirements of
this change order, the plans, the specifications, and the contract documents.
I-1
Change Order 2 FINAL
Page 2
Recommended for Acceptance:
Accepted and/or Requested:
Attest:
BY r,~c~`1
Signature
NAME LPv~2.tE (~,~}a
Type or Print
TITLE ~~
Approved and/or Requested:
Attest:
BY
Signature
NAME
Type or Print
TITLE
IIW ENGINEERS & SURVEYORS, P.C.
-
Signature
~
NAME ~ ~~,~ /~y v5 T~ .~
Type or Print
TITLE J~~ssi~.., EnS~.,~»1-
DATE ~a o R
O /
,~C
T CTO
Easter Iowa xcavating & on rete, LLC
BY ~' '~
Signature
NAME (may-,~4Tj L~r,,, ytC~2
Type or Print
TITLE (?~urr~..e.+~'
DATE rl}--Lc -O
OWNER
City of Dubu ue, Iowa
BY /~~
Signature
NAME Michael C. Van Milli~en
Type or Print
TITLE City Manager
DATE 1 ~ ~ 3~(j`
I-2
ti CITY OF DUBUQUE
FLOODWALL LEVEE SLOPE STABILIZATION
IIW PROJECT NO.: 08215-03
CONTRACT CHANGES
A. Contract adjustment based on measured quantities
ITEM ORIGINAL FINAL QUANTITY UNIT
NO. ITEM UNIT QUANT QUANT DIFF. PRICE
1 Mobilzation & Miscellaneous SY 1 1 0 $10,000.00
2 Rip Rap SY 5110 6739.86 1629.86 $23.50
3 Bedding Stone SY 1191 1231.31 40.31 $20.00
4 Engineering Fabric SY 1750 2820 1070 $2.25
5 Excavation CY 3366 3368 2 $7.50
TOTALS
Contract addition due to measurement of installed quantities $41,530.41
INCREASE DECREASE
$0.00 $0.00
$38,301.71 $0.00
$806.20 $0.00
$2,407.50 $0.00
$15.00 $0.00
$41,530.41 $O.GO
TOTAL CHANGE ORDER NO. 2 FINAL $41,530.41
CONTRACT SUMMARY
Original Contract Amount 183,087.50
Modifications due to Change Order 1 0.00
Modifications due to Change Order 2 Final 41,530.41
FINAL CONTRACT AMOUNT $224,617.91