TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Salt Dome Conveyor Project - CIP #2502153
DATE: October 12, 2009
Sealed bids were received for the Salt Dome Conveyor Project. Public Works Director
Don Vogt recommends award of the contract to the low bidder, Conlon Construction, in
the amount of $128,400.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Mic ael C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Don Vogt, Public Works Director
TO: Michael C. Van Milligen, City Managie'r
FROM: Don Vogt, Public Works Director ~(~J
SUBJECT: Salt Dome Conveyor Project -CIP# 2502153
DATE: September 9, 2009
INTRODUCTION
The attached resolution authorizes the award of contract for the Salt Dome Conveyor
Project (CIP #2502153).
BACKGROUND
In the fiscal year 2010 Capital Improvement Project budget, funds are allotted for the
purchase and installation of a conveyor system in the salt storage dome at the
Municipal Services Center. At the City Council's September 8t" meeting, it approved the
initiation of the public bidding process for the Salt Dome Conveyor Project. The City
Council also set the public hearing date for said project for September 21St. The public
hearing was subsequently held on September 21St and no objections were received.
DISCUSSION
Engineering plans and specifications for this project were prepared by Kueny Architects
L.L.C of Pleasant Prairie, Wisconsin. Kueny is the firm that designed the Municipal
Services Center and the salt storage dome earlier this decade. This project will include
the construction of a conveyor pit, installation of a salt conveyor system, modifications
to the electrical system, and modifications to the roof panels of the storage dome.
Completion of this project will provide for quicker and safer dome-loading operations,
and allow full use of the building's design capacity.
BID RESULTS
Sealed bids for the Salt Dome Conveyor Project were opened at 2:00 p.m. on October
6, 2009. Three bids were received for this project. Listed below is a tabulation of the
bids received:
Conlon Construction $128 400.00
Dome Corporation of North America $149,650.00
Tricon Construction $168 000.00
BUDGET IMPACT
Estimate Bid Award
Construction Contract $ 141,135 $128,400
Contingency $ 16,000 $ 16,000
Engineering 2 865 2 865
Estimated Total Project Cost $ 160,000 $147,265
This project will be funded with monies budgeted specifically for the Salt Dome
Conveyor Project in the Public Works Department's FY 2010 Capital Improvement
Project budget: CIP# - 2502153 $160,000.00
RECOMMENDATION
I recommend that the City Council award the construction contract for the Salt Dome Conveyor
Project to the low bidder, Conlon Construction of Dubuque, Iowa, in the amount of
$128,400.00. This bid is 9.02% below the construction estimate of probable cost.
ACTION REQUIRED
The City Council is requested to approve the attached resolution awarding the Salt Dome
Conveyor Project to the low bidder, Conlon Construction of Dubuque, Iowa, in the amount of
$128,400.00.
Attachment
RESOLUTION NO. 425-09
AWARDING PUBLIC IMPROVEMENT CONTRACT FOR THE SALT DOME
CONVEYOR PROJECT
whereas, sealed proposals have been submitted by contractors for the Salt
Dome Conveyor Project (the Project) pursuant to Resolution Number 333-09 and Notice
to Bidders published in the city of Dubuque, Iowa on the 11t" day of September, 2009.
Whereas, said sealed proposals were opened and read on the 6t" day of
October, 2009 and it has been determined that Conlon Construction Company of
Dubuque, Iowa with a bid in the amount of $128,400.00 is the lowest, responsive,
responsible bidder for the Project.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the Public Improvement Contract for the Project is hereby awarded to
Conlon Construction Company and the City Manager is hereby directed to execute a
Public Improvement Contract on behalf of the City of Dubuque for the Project.
Passed, adopted and approved this 19th day of
Attest:
~-~ ~/~ /
Jeanne F. Schneider, CMC, City Clerk
October ,2009.
~,
~~ ~,~°
Roy D ~Buol, Mayor