Five-Year Street Construction Program for Fiscal years 2019-2023 Copyrighted February 28, 2018 City of Dubuque Action Items # 1. ITEM TITLE: Five-Year Street Construction Program for Fiscal Years 2019-2023 SUMMARY: Engineering Department recommending adoption of the Five-Year Street Construction Program for Fiscal Years 2019-2012 relative to the Fiscal Year 2019 recommended budget. RESOLUTION Adopting the Five-Year Street Construction Program for Fiscal Years 2019-2023 SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt Resolution(s) ATTACHMENTS: Description Type Staff Memo Staff Memo Resolution Resolutions Proposed Five Year Street Program 2019-2023 Supporting Documentation THE CITY OF Dubuque DUB E � �� IUusrr. illi;' Masterpiece on the Mississippi 2067.2012 2013.2017 TO: Michael C. Van Milligen, City Manager.,a... FROM: Gus Psihoyos, City Engineer '9d DATE: February 23, 2018 RE: Five-Year Street Construction Program for Fiscal Years 2019—2023 INTRODUCTION The enclosed resolution provides for the City Council approval of the Annual Five-Year Street Construction Program for Fiscal Years 2019 - 2023. DISCUSSION The Five-Year Street Construction Program for Fiscal Years 2019 - 2023, which is part of the Five-Year Capital Improvement Projects, includes the estimated costs for the street construction work and the anticipated year during which each project will be undertaken. The Five-Year Street Construction Program is considered annually by the City Council as part of the budget process. The Iowa Department of Transportation (IDOT) provides annual projections on the amount of Road Use Tax Funds the City of Dubuque will receive over the next five years based on a per capita amount. The State Road Use Tax Fund consist of revenues from fuel tax, vehicle registration fees, use tax, driver's license fees and other miscellaneous sources and is distributed to cities on a per capita basis. It should be noted that in FY 2010, the Iowa Department of Revenue increased Road Use Tax Funds (RUT) as a result of higher vehicle registration fees passed into law in 2008. The gas tax was increased ten cents beginning in February 2015. The City is estimated to receive $35,137,812 for FY 2019-2023 based on the gas tax increasing ten cents in Fiscal Year 2015. With increases in City DMATS and State Road Use Tax funds, the City will be able to substantially add to the number of street lights, keep the Southwest Arterial project moving forward and continue with major road improvements like North Cascade Road, Central Avenue and White Street. RECOMMENDATION I recommend that the City Council accept the Annual Five-Year Construction Program for Fiscal Years 2019 - 2023. ACTION TO BE TAKEN The City Council is requested to approve this resolution for the acceptance of the Five-Year Construction Program for Fiscal Years 2019 - 2023. GNP/kjb cc: Jenny Larson, Budget Director Alexis Steger, Senior Budget Analyst RESOLUTION NO. 45-18 ADOPTING THE FIVE-YEAR STREET CONSTRUCTION PROGRAM FOR FISCAL YEARS 2019 - 2023 Whereas, a recommended Five-Year Street Construction Program for the Fiscal Year 2019 - 2023 beginning July 1, 2018 and ending June 30, 2023, for the City of Dubuque has been prepared and submitted to the City Council; and Whereas, the Five-Year Street Construction Program: 1) describes specific capital improvement projects; 2) provides estimated costs for those projects; 3) proposes sources of funding; and 4) schedules the fiscal/calendar year during which each project will be undertaken; and Whereas, the capital improvement projects for the first year of such five-year program are included in the Fiscal Year 2019 budget; and Whereas, the adoption of the Five-Year Street Construction Program is a prudent measure to provide continuity of programs and is in the best interest of the City of Dubuque. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That the Five-Year Street Construction Program for Fiscal Years 2019 — 2023 beginning July 1, 2018, set out in the Fiscal Years 2019 — 2023 recommended Capital Improvement Budget, is hereby approved and adopted as the H proposed allocation of City resources for capital improvements as scheduled in the years shown, subject to annual review and revision. Passed, adopted and approved this 28th day of February 2018= ` Roy D. Buol, Mayor Attest: Trish L. Gleason, Assistant City Clerk STREET CONSTRUCTION PROGRAM 2019-2023 SUMMARY THE CITY OF E CALENDAR YEAR 2018/2019 DUB FISCAL YEAR 2019 Masterpiece on the Mississippi Street From To Construction Tvoe Cost Estimate Fundina Assistance Grandview&University Roundabout Grandview&University Intersection Street/Intersection Reconstruction $ 900,000 TSF,ICAAP,STP $ 850,000 East-West Corridor Capacity Improvements University/Pennsylvania University/Loras Property Acquisition $ 578,000 Federal STP Funds $ 160,000 US 52 Rehabilitation Phase 4 Central Avenue-9th Street Central Avenue-21st Street HMA Resurfacing $ 1,923.0Ci 1 Iowa DOT Funding $ 836,500 Jackson Street Reconstruction 11th Street 12th Street Street Reconstruction $ 320,001 i Derby Grange Resurfacing-Partner with Dubuque County JFK Road Derby Grange Golf HMA Resurfacing $ 23,001 i US 20/Swiss Valley Interchange Frontage Road Street Construction $ 400,000 Preliminary Cost Estimate-Annual Street Construction Program M$ 4,144,0001 Total: $ 1,846,500 PROPOSED BUDGET FY 2019 $ 4 144 000 PROGRAM FINANCING: CITY ANNUAL STREET PROGAM $ 2,297,500 FEDERAL GRANT FUNDS $ 1,010,000 IOWA DOT FUNDING $ 836,500 TOTAL STREET PROGRAM FINANCING: $ 4 144 000 ADDITIONAL STREET RELATED IMPROVEMENT PROJECTS Street From To Construction Type Cost Estimate Funding Assistance Street Construction General Repairs General Repairs $ 75,000 Bridge Repairs/Maintenance General Repairs $ 85,000 Guardrail Replacement Guardrail $ 10,000 Pavement Marking Project Pavement Markings $ 135,000 /DOT Funding $ 15,000 TOTAL ADDITIONAL STREET RELATED COSTS: $ 305,000 TOTAL STREET RELATED IMPROVEMENT COSTS: $ 4,449,000 F:IPROJECTSAAnnual Street Program-5 Year1FY2019-2023 Five Year Street ProgramlFive Year Street Program 2019-2023-Proposed.xls STREET CONSTRUCTION PROGRAM 2019-2023 SUMMARY THE CITY OF E CALENDAR YEAR 2019/2020 DUB FISCAL YEAR 2020 Masterpiece on the Mississippi Street From To Construction Time, Cost Estimate Funding Assistance East-West Corridor Capacity Improvements University/Pennsylvania University/Loras Property Acquisition I$ 4,450,000 Federal STP Funds $ 4,000,000 Central Avenue&White Street One-way to Two Way 4th Street 21st Street Street Reconstruction/Realignment $ 200,000 Preliminary Cost Estimate-Annual Street Construction Program i$ 4,650,000 I Total: $ 4,000,000 PROPOSED BUDGET FY 2020 $ 43650,000 PROGRAM FINANCING: CITY ANNUAL STREET PROGAM $ 650,000 FEDERAL GRANT FUNDS $ 4,000,000 IOWA DOT FUNDING TOTAL STREET PROGRAM FINANCING: $ 4,650,000 ADDITIONAL STREET RELATED IMPROVEMENT PROJECTS Street From To Construction Type Cost Estimate Funding Assistance Street Construction General Repairs General Repairs $ 100,000 Bridge Repairs/Maintenance General Repairs $ 95,000 Guardrail Replacement Guardrail $ 10,000 Pavement Marking Project Pavement Markings $ 135,000 'DOT Funding $ 15,000 TOTAL ADDITIONAL STREET RELATED COSTS: $ 340,000 TOTAL STREET RELATED IMPROVEMENT COSTS: $ 4,990,000 F:IPROJECTSAAnnual Street Program-5 Year1FY2019-2023 Five Year Street ProgramlFive Year Street Program 2019-2023-Proposed.xls STREET CONSTRUCTION PROGRAM 2019-2023 SUMMARY THE CITY OF E CALENDAR YEAR 2020/2021 DUB FISCAL YEAR 2021 Masterpiece on the Mississippi Street From To Construction Time, Cost Estimate Fundina Assistance East-West Corridor Capacity Improvements University/Pennsylvania University/Loras Street/Intersection Reconstruction $ 150,000 North Cascade Road Reconstruction Catfish Creek Edval Lane Street Reconstruction $ 1,497,200 Federal STP Funds $ 872,200 Heeb Street Reconstruction 17th Street End of Heeb Street Reconstruction $ 50,000 Preliminary Cost Estimate-Annual Street Construction Program i$ 1,697,200 I Total: $ 872,200 PROPOSED BUDGET FY 2021 $ 1 697 200 PROGRAM FINANCING: CITY ANNUAL STREET PROGAM $ 825,000 FEDERAL GRANT FUNDS $ 872,200 IOWA DOT FUNDING TOTAL STREET PROGRAM FINANCING: $ 1,697,200 ADDITIONAL STREET RELATED IMPROVEMENT PROJECTS Street From To Construction Type Cost Estimate Funding Assistance Street Construction General Repairs General Repairs $ 100,000 Bridge Repairs/Maintenance General Repairs $ 100,000 Guardrail Replacement Guardrail $ 10,000 Pavement Marking Project Pavement Markings $ 85,000 /DOT Funding $ 15,000 Cross-Walk Warning Devices Traffic Signals for Cross-walks $ 31,000 TOTAL ADDITIONAL STREET RELATED COSTS: $ 326,000 TOTAL STREET RELATED IMPROVEMENT COSTS: $ 2,023,200 F:IPROJECTSAAnnual Street Program-5 Year1FY2019-2023 Five Year Street ProgramlFive Year Street Program 2019-2023-Proposed.xls STREET CONSTRUCTION PROGRAM 2019-2023 SUMMARY THE CITY OF E CALENDAR YEAR 2021/2022 DUB FISCAL YEAR 2022 Masterpiece on the Mississippi Street From To Construction Tvne Cost Estimate Funding Assistance East-West Corridor Capacity Improvements University/Pennsylvania University/Loras Street/Intersection Reconstruction $ 4,150,000 FederaVState Funds $ 4,100,000 Heeb Street Reconstruction 17th Street End of Heeb Street Reconstruction $ 200,000 Special Assessments $ 20,000 Preliminary Cost Estimate-Annual Street Construction Program i$ 4,350,000 II Total: $ 4,120,000 PROPOSED BUDGET FY 2022 $ 4,350,000 PROGRAM FINANCING: CITY ANNUAL STREET PROGAM $ 230,000 FEDERAL GRANT FUNDS $ 4,100,000 SPECIAL ASSESSMENTS $ 20,000 TOTAL STREET PROGRAM FINANCING: $ 4,350,000 ADDITIONAL STREET RELATED IMPROVEMENT PROJECTS Street From To Construction Type Cost Estimate Funding Assistance Street Construction General Repairs General Repairs $ 100,000 Bridge Repairs/Maintenance General Repairs $ 100,000 Guardrail Replacement Guardrail $ 10,000 Pavement Marking Project Pavement Markings $ 135,000 IDOT Funding $ 15,000 TOTAL ADDITIONAL STREET RELATED COSTS: $ 345,000 TOTAL STREET RELATED IMPROVEMENT COSTS: $ 4,695,000 F:IPROJECTSAAnnual Street Program-5 Year1FY2019-2023 Five Year Street Program\Five Year Street Program 2019-2023-Proposed.xls STREET CONSTRUCTION PROGRAM 2019-2023 SUMMARY THE CITY OF E CALENDAR YEAR 2021/2022 DUB FISCAL YEAR 2023 Masterpiece on the Mississippi Street From To Construction Tvoe Cost Estimate Funding Assistance 7th Street Extension 7th Street Pine Street Street Construction $ 70,000 Bies Drive Reconstruction Pennsylvania Avenue Century Drive Street Reconstruction $ 250,000 Bennet Street Reconstruction N.Grandview Avenue McCormick Street Street Reconstruction $ 80,001 i Sylvan Drive Reconstruction Pennsylvania Avenue Century Drive Street Reconstruction $ 35,001 i Seippel Road Reconstruction Pennsylvania Avenue 13310 Seippel Road Street Reconstruction $ 280,000 Century Drive Reconstruction Bies Drive US20 Street Reconstruction $ 200,01 ii i Preliminary Cost Estimate-Annual Street Construction Program M$ 915,000A Total: $ - PROPOSED BUDGET FY 2022 $ 915 000 PROGRAM FINANCING: CITY ANNUAL STREET PROGAM $ 915,000 FEDERAL GRANT FUNDS IOWA DOT FUNDING TOTAL STREET PROGRAM FINANCING: $ 915 000 ADDITIONAL STREET RELATED IMPROVEMENT PROJECTS Street From To Construction Type Cost Estimate Fundina Assistance Street Construction General Repairs General Repairs $ 100,000 Bridge Repairs/Maintenance General Repairs $ 108,000 Guardrail Replacement Guardrail $ 10,000 Pavement Marking Project Pavement Markings $ 135,000 'DOT Funding $ 15,000 TOTAL ADDITIONAL STREET RELATED COSTS: $ 353,000 TOTAL STREET RELATED IMPROVEMENT COSTS: $ 1,268,000 F:IPROJECTSAAnnual Street Program-5 Year1FY2019-2023 Five Year Street ProgramlFive Year Street Program 2019-2023-Proposed.xls