John F. Kennedy Road and NW Arterial Right-Turn Lane Improvements_Hearing Copyrighted
April 16, 2018
City of Dubuque Public Hearings # 9.
ITEM TITLE: John F. Kennedy Road and NW Arterial Right-Turn Lane
Improvement Project Initiate
SUMMARY: Proof of Publication on notice of public hearing to approve
the plans, specifications, form of contract and estimated
cost for the Northwest Arterial —J FK I ntersection Right
Turn Lane Improvements Project and City Manager
recommending approval.
RESOLUTION Approval of Plans, Specifications, Form of
Contract, and Estimated Cost for the Northwest Arterial -
JFK Intersection Right Turn Lane Improvements lowa DOT
Project No. Stp-A-2100 (688)--86-31
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s)
ATTACHMENTS:
Description Type
NW Arterial and JFK Intersection Right Turn Lane City Manager Memo
Improvements-NNM Memo
Staff Memo Staff Memo
Resolution Resolutions
THE CITY OF Dubuque
�
AIFA�erlwGh
UB E '�� III►
Masterpiece on the Mississippi Z°°'�w'2
7A13 2017
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Northwest Arterial — JFK Intersection Right Turn Lane Improvements
CIP No. 3002675, lowa DOT Project No. STP-A-2100 (688)-86-31
DATE: April 4, 2018
Assistant City Engineer Bob Schiesl recommends City Council approval of the plans,
specifications, form of contract and estimated cost of$177,100 for the Northwest
Arterial — JFK Intersection Right Turn Lane Improvements Project. The City has
received $123,200 in an lowa Department of Transportation Clean Air Attainment Grant
towards the cost of this project.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�� �� ���
Mic ael C. Van Milligen �� �
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Teri Goodmann, Assistant City Manager
Cori Burbach, Assistant City Manager
Robert Schiesl, Assistant City Engineer
Gus Psihoyos, City Engineer
THE CITY OF Dubuque
�
All-America City
UB E � r
�
Mas terpiece on the Mississippi Zoo,.2012.Zo13
TO: Michael C. Van Milligen, City Manager
Gus Psihoyos, City Engineer
FROM: Robert Schiesl, Assistant City Engineer
DATE: April 4, 2018
SUBJECT: Northwest Arterial - JFK Intersection Right Turn Lane Improvements
CIP No. 3002675, lowa DOT Project No. STP-A-2100 (688)-86-31
INTRODUCTION
The purpose of this memorandum is to provide the City Council with information related
to the public hearing for the Northwest Arterial - JFK Intersection Right Turn Lane
Improvements Project.
BACKGROUND
The northerly approach driving lane of the JFK Road and Northwest Arterial intersection
has one left turn lane and one shared thru and right turn lane. The thru and right turn
movement to go straight or south is a very heavy traffic movement. Unfortunately, it only
takes one southbound (straight thru) vehicle queued at the light to block all free right
turn movements. Once blocked, this shared lane can rapidly back up with vehicles
stacking to over 400 feet from the intersection.
The City of Dubuque applied for and was awarded an lowa Clean Air Attainment
Program (ICAAP) grant from the lowa DOT in the amount of $198,202 to assist with the
construction of a right turn lane on the north leg of JFK Road with traffic signal
adjustments at NW Arterial and JFK Road intersection.
EXISTING CONDITIONS
Although traffic signal timings at the NW Arterial - JFK intersection are reviewed and
updated throughout the year, the existing shared through - right turn lane does not
efficiently handle right turning traffic movements. ITS improvements have been
implemented at this intersection over the last 10 years to provide the most efficiency
from the existing geometrics. This approach has come to the point where no additional
efficiencies can be achieved without adding traffic lane improvements.
PROPOSED TURN LANE IMPROVEMENT
Based on the current operational and capacity challenges the City is experiencing at the
JFK Road and NW Arterial intersection, the proposed turn lane improvement includes
adding an exclusive 250-foot right turn lane along the existing northerly approach on
JFK Road. The new right turn lane would allow for a dedicated straight thru lane as well
as maintaining the existing dedicated left turn lane. The proposed turn lane
improvement will improve the capacity and efficiency of this intersection.
PROJECT SCHEDULE
The schedule for the project is as follows:
lowa DOT Advertisement for Bids March 21 , 2018
City Initiate Public Bidding Process April 2, 2018
Notice of Public Hearing on Plans & Specifications April 6, 2018
City Public Hearing on Plans & Specifications April 16, 2018
lowa DOT Receipt of Bids (Bid Letting) April 17, 2018
City Award of Contract (Subject to lowa DOT Approval) May 7, 2018
Late Start Date September 4, 2018
Contract Completion Date 20 Working Days
Completed Fall 2018
RECOMMENDATION
I recommend that the City Council approve the plans, specifications, form of contract
and estimated cost for the Northwest Arterial - JFK Intersection Right Turn Lane
Improvements Project.
BUDGETIMPACT
The estimate of probable cost for the recommended turn lane improvements are
summarized in the following table:
Description Cost Estimate
Construction — JFK New Right Turn Lane $ 140,000.00
Contingency (10°k) 14,000.00
Engineering Design and Administration (15°k) 23,100.00
Total Construction Cost Estimate $ 177,100.00
The proposed project funding is summarized as follows:
CIP No. Fund Description Fund Amount
3002675 ICAAP Grant (80°k) $ 123,200.00
3002675 NW Arterial Road Right Turn Lane Improvements 53,900.00
Total Project Funding $ 177,100.00
The grant funding agreement between the lowa DOT and the City provides for the
utilization of ICAAP Grant Funds for eligible construction costs for the construction of a
new right turn lane. The portion of the eligible construction costs reimbursed by ICAAP
funds shall be limited to a maximum of 80°k of eligible participating costs. All other
costs, such as preliminary engineering (PE), Final Engineering (FE), and construction
engineering (CE) will be funded solely with City funding.
ACTION TO BE TAKEN
The City Council is requested to approve the plans, specifications, form of contract and
estimated cost for the Northwest Arterial - JFK Intersection Right Turn Lane
Improvements Project through adoption of the enclosed resolution.
cc: Jenny Larson, Budget Director
Jon Dienst, Civil Engineer
Greg Doeden, Civil Engineer
Kent Ellis, lowa DOT
F:\PROJECTS\ICAAP- NW ARTERIAL JFK TURN LANE\Council and Staff Documents\Public Hearing
RESOLUTION NO. 113-18
APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND
ESTIMATED COST FOR THE NORTHWEST ARTERIAL - JFK INTERSECTION
RIGHT TURN LANE IMPROVEMENTS IOWA DOT PROJECT NO. STP -A-2100 (688)-
-86-31
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the proposed plans, specifications, form of contract and estimated cost for
the Northwest Arterial / JFK Intersection Right Turn Lane Improvements Project, in the
estimated amount $140,000.00, are hereby approved.
Attest:
Passed, adopted and approved this 16th day of April 2018.
D -avid T. Resnic(C, Mayor Pro -Tem
Ke in S. Firnstahl, CMC, City Clerk
STATE OF IOWA {SS:
DUBUQUE COUNTY
CERTIFICATION OF PUBLICATION
I, Suzanne Pike, a Billing Clerk for Woodward Communications, Inc., an Iowa corporation, publisher
of the Telegraph Herald,a newspaper of general circulation published in the City of Dubuque, County
of Dubuque and State of Iowa; hereby certify that the attached notice was published in said newspaper
on the following dates: April 6, 2018, and for which the charge is $23.17.
ES' ae2,___
Subscribed to before me, a Notary Public in and for Dubuque County, Iowa,
this /del day of , 20 /f
Notary Public in and for Dubuque County, Iowa.
K WE$ i-ERM.YER
y r•.o-^. Pi , b$r 158B5
r,inri3Otar, En. Feb. 1, 2020
CITY OF DUBUQUE,
IOWA
OFFICIAL NOTICE
NOTICE OF PUBLIC
HEARING ON PLANS,
SPECIFICATIONS,
FORM: OF CONTRACT,
AND ESTIMATED
COST FOR ` THE
NORTHWEST: ARTER-
IAL -, JFK INTERSEC-
TION RIGHT ; ; TURN
LANE IMPROVEMENTS,'
NOTICE IS HEREBY
GIVEN: The City
Council of tilO City of
Dubuque, Iowa; will
hold a public hearing
oh the proposed plans,
specifications, form of
contract and estimated
cost for the NorthweStj
Arterial JFK ;;Inter
section Right Turn
Lane ,' Improvements
Project, = Iowa DOT
Project? No: STP -A-2100
(688),-86-31 in accor-
dance with the ;:provi-
sions of Chapter 26,
Code of Iowa, at 6:00
p.m., on the 16th day of.
April, 2018, in the
Historic Federal Build-
ing Council Chambers
(second " floor), 350
West 6th Street,
Dubuque, Iowa.' Said
proposed plans, speci-
fications, form of
contract and estimated
costare now on file in
the Office of the City
Clerk, `,City Hall, 50 W.
13th`St.Dubuque,','
Iowa, and;may be
viewed during normal
working hours. At said
hearing any interested
person may appear
and file objections
thereto.
The scope of the
Project is as follows:
• 635 SY of 9' PCC,
Doweled Pavement
• Minor storm sewer
work, 3 manholes and 4
intakes
• 550 Ton 3" Breaker
Any visual or hearing-
impaired persons need-
ing special
eeding"special assistance
orpersons with special
accessibility needs
should contact the City
Clerk's Office at (563)
589-4100 or TDD at
(563) 690-6678 at least
48 hours prior to the
meeting.
Published by order of
the City Council given
on the 2nd day of April,
2018.
Kevin S.Firnstahl,
CMQ, City_Clerk