John F. Kennedy Road and NW Arterial Right-Turn Lane_Initiate Copyrighted
April 2, 2018
City of Dubuque Items to be set for Public Hearing # 3.
ITEM TITLE: John F. Kennedy Road and NW Arterial Right-Turn Lane
Improvement Project Initiate
SUMMARY: City Manager recommending initiation of the public bidding
procedure through the lowa Department of Transportation
for the Northwest Arterial — JFK Intersection Right-Turn
Lane Improvements Project, and further recommends that
a public hearing be set for April 16, 2018.
RESOLUTION Preliminary approval of plans,
specifications, form of contract, and estimated cost; setting
date of public hearing on plans, specifications, form of
contract, and estimated cost
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s), Set Public Hearing forApril 16, 2018
ATTACHMENTS:
Description Type
NW Arterial JFK Intersection Right Turn Lane City Manager Memo
Improvements-NNM Memo
Staff Memo Staff Memo
Resolution Resolutions
THE CITY OF Dubuque
�
AIFA�erlwGh
UB E '�� III►
Masterpiece on the Mississippi Z°°'�w'2
7A13 2017
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Northwest Arterial — JFK Intersection Right Turn Lane Improvements
CIP No. 3002675, lowa DOT Project No. STP-A-2100 (688)-86-31
DATE: March 21 , 2018
Assistant City Engineer Bob Schiesl recommends initiation of the public bidding
procedure through the lowa Department of Transportation for the Northwest Arterial —
JFK Intersection Right Turn Lane Improvements Project, and further recommends that a
public hearing be set for April 16, 2018.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�L;� 1��, ���,��
Mic ael C. Van Milligen �� �
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Teri Goodmann, Assistant City Manager
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Bob Schiesl, Assistant City Engineer
THE CITY OF Dubuque
�
All-America City
UB E � r
�
Mas terpiece on the Mississippi Zoo,.2012.Zo13
TO: Michael C. Van Milligen, City Manager
Gus Psihoyos, City Engineer
FROM: Robert Schiesl, Assistant City Engineer
DATE: March 21 , 2018
SUBJECT: Northwest Arterial - JFK Intersection Right Turn Lane Improvements
CIP No. 3002675, lowa DOT Project No. STP-A-2100 (688)-86-31
INTRODUCTION
The purpose of this memorandum is to provide the City Council with information related
to the Northwest Arterial - JFK Intersection Right Turn Lane Improvements Project and
request concurrence to initiate the public bidding procedure and establish the date for
the public hearing.
BACKGROUND
The northerly approach driving lane of the JFK Road and Northwest Arterial intersection
has one left turn lane and one shared thru and right turn lane. The thru and right turn
movement to go straight or south is a very heavy traffic movement. Unfortunately, it only
takes one southbound (straight thru) vehicle queued at the light to block all free right
turn movements. Once blocked, this shared lane can rapidly back up with vehicles
stacking to over 400 feet from the intersection.
The City of Dubuque applied for and was awarded an lowa Clean Air Attainment
Program (ICAAP) grant from the lowa DOT in the amount of $198,202 to assist with the
construction of a right turn lane on the north leg of JFK Road with traffic signal
adjustments at NW Arterial and JFK Road intersection.
EXISTING CONDITIONS
Although traffic signal timings at the NW Arterial - JFK intersection are reviewed and
updated throughout the year, the existing shared through - right turn lane does not
efficiently handle right turning traffic movements. ITS improvements have been
implemented at this intersection over the last 10 years to provide the most efficiency
from the existing geometrics. This approach has come to the point where no additional
efficiencies can be achieved without adding traffic lane improvements.
PROPOSED TURN LANE IMPROVEMENT
Based on the current operational and capacity challenges the City is experiencing at the
JFK Road and NW Arterial intersection, the proposed turn lane improvement includes
adding an exclusive 250-foot right turn lane along the existing northerly approach on
JFK Road. The new right turn lane would allow for a dedicated straight thru lane as well
as maintaining the existing dedicated left turn lane. The proposed turn lane
improvement will improve the capacity and efficiency of this intersection.
PROJECT SCHEDULE
The schedule for the project is as follows:
lowa DOT Advertisement for Bids March 21 , 2018
City Initiate Public Bidding Process April 2, 2018
Notice of Public Hearing on Plans & Specifications April 6, 2018
City Public Hearing on Plans & Specifications April 16, 2018
lowa DOT Receipt of Bids (Bid Letting) April 17, 2018
City Award of Contract (Subject to lowa DOT Approval) May 7, 2018
Late Start Date September 4, 2018
Contract Completion Date 20 Working Days
Completed Fall 2018
RECOMMENDATION
I recommend City Council concurrence with initiating the public bidding procedure
through the lowa DOT and set April 16, 2018, as the date for a public hearing on the
Northwest Arterial - JFK Intersection Right Turn Lane Improvements Project.
BUDGETIMPACT
The estimate of probable cost for the recommended turn lane improvements are
summarized in the following table:
Description Cost Estimate
Construction — JFK New Right Turn Lane $ 140,000.00
Contingency (10°k) 14,000.00
Engineering Design and Administration (15°k) 23,100.00
Total Construction Cost Estimate $ 177,100.00
The proposed project funding is summarized as follows:
CIP No. Fund Description Fund Amount
3002675 ICAAP Grant (80°k) $ 112,000.00
3002675 NW Arterial Road Right Turn Lane Improvements 65,100.00
Total Project Funding $ 177,100.00
The grant funding agreement between the lowa DOT and the City provides for the
utilization of ICAAP Grant Funds for eligible construction costs for the construction of a
new right turn lane. The portion of the eligible construction costs reimbursed by ICAAP
funds shall be limited to a maximum of 80°k of eligible participating costs. All other
costs, such as preliminary engineering (PE), Final Engineering (FE), and construction
engineering (CE) will be funded solely with City funding.
ACTION TO BE TAKEN
The City Council is requested to concur with initiating the public bidding procedure
through the lowa DOT and set the date for a public hearing on the Northwest Arterial -
JFK Intersection Right Turn Lane Improvements Project through adoption of the
enclosed resolution.
cc: Jenny Larson, Budget Director
Jon Dienst, Civil Engineer
Greg Doeden, Civil Engineer
Kent Ellis, lowa DOT
RESOLUTION NO. 86-18
NORTHWEST ARTERIAL - JFK INTERSECTION
RIGHT TURN LANE IMPROVEMENTS
IOWA DOT PROJECT NO. STP -A-2100 (688)--86-31
PRELIMINARY APPROVAL OF PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST; SETTING DATE OF PUBLIC HEARING
ON PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED
COST
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
The proposed plans, specifications, form of contract and estimated cost
for the Northwest Arterial / JFK Intersection Right Turn Lane Improvements in the
estimated amount $177,100.00, are hereby preliminarily approved and ordered
filed in the office of the City Clerk for public inspection.
A public hearing will be held on the 16th day of April, 2018, at 6:00 p.m. in
the Historic Federal Building Council Chambers (second floor) 350 W. 6th Street,
Dubuque, Iowa, at which time interested persons may appear and be heard for or
against the proposed plans and specifications, form of contract and estimated
cost of said Project, and the City Clerk be and is hereby directed to cause the
attached notice of the time and place of such hearing to be published in a
newspaper having general circulation in the City of Dubuque, Iowa, which notice
shall be published not less than four days nor more than twenty days prior to the
date of such hearing. At the hearing, any interested person may appear and file
objections to the proposed plans, specifications, form of contract, or estimated
cost of the Project.
Attest:
Passed, adopted and approved this the 2nd day of April, 2
Kevj Firnst I, CMC, City Clerk
D. Buol, Mayor
NOTICE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST FOR THE NORTHWEST ARTERIAL -
JFK INTERSECTION RIGHT TURN LANE IMPROVEMENTS
NOTICE IS HEREBY GIVEN: The City Council of the City of Dubuque,
lowa will hold a public hearing on the proposed plans, specifications, form of
contract and estimated cost for the Northwest Arterial - JFK Intersection Right
Turn Lane Improvements Project, lowa DOT Project No. STP-A-2100 (688)--86-
31 in accordance with the provisions of Chapter 26, Code of lowa, at 6:00 p.m.,
on the 16�h day of April, 2018, in the Historic Federal Building Council Chambers
(second floor), 350 West 6�h Street, Dubuque, lowa. Said proposed plans,
specifications, form of contract and estimated cost are now on file in the office of
the City Clerk. At said hearing any interested person may appear and file
objections thereto.
The scope of the Project is as follows:
• 635 SY of 9" PCC Doweled Pavement
• Minor storm sewer work, 3 manholes and 4 intakes
• 550 Ton 3" Breaker
Any visual or hearing-impaired persons needing special assistance or
persons with special accessibility needs should contact the City Clerk's office at
(563) 589-4120 or TDD at (563) 690-6678 at least 48 hours prior to the meeting.
Published by order of the City Council given on the 2"d day of April ' 2018.
Kevin S. Firnstahl, CMC, City Clerk