Twin Ridge Lift Station Abandonment Project Award Copyrighted
September 4, 2018
City of Dubuque Consent Items # 9.
ITEM TITLE: Twin Ridge Lift Station Abandonment Project Award
SUMMARY: City Manager recommending award of the construction
contract for the Twin Ridge Lift Station Abandonment
Project to the low bidder Gansen Excavating, Inc.
RESOLUTION Awarding Public Improvement Project for
the Twin Ridge Lift Station Abandonment Project
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s)
ATTACHMENTS:
Description Type
Twin Ridge Lift Station Abandonment Project-NNM City Manager Memo
Memo
Staff Memo Staff Memo
Resolution Resolutions
THE CITY OF Dubuque
�
AIFA�erlwGh
UB E '�� III►
Masterpiece on the Mississippi Z°°'�w'2
7A13 2017
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Twin Ridge Lift Station Abandonment
DATE: August 28, 2018
Sealed bids were received for the Twin Ridge Lift Station Abandonment Project. City
Engineer Gus Psihoyos recommends award of the construction contract to the low
bidder, Gansen Excavating, Inc., in the amount of$105,976.17, which is 4.64°k under
the estimate of probable cost.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�� �� ���
Mic ael C. Van Milligen �� �
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Teri Goodmann, Assistant City Manager
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
TH E CI'CY OF �ll V AC�Uf
DUB E °°.�
Maeterpiece mi the Mississippi � � � � � �
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: Twin Ridge Lift Station Abandonment
DATE: Aug 24, 2018
INTRODUCTION
The enclosed resolution authorizes the award of the construction contract for the Twin
Ridge Lift Station Abandonment project.
BACKGROUND
In 2015, the city purchased the sanitary sewer collection and water distribution systems,
serving Twin Ridge subdivision, from Twin Ridge Water Corporation. The sanitary
sewer collection system is comprised of the gravity collection system, a lift station and a
lagoon treatment facility. Also, in 2015, the City constructed a new lift station on Lake
Eleanor road. The Lake Eleanor road lift station was designed to serve the area
between Key West Drive and U.S. highway 151/61, north of Lake Eleanor road, along
with the ability to serve an additional 24 properties within Twin Ridge subdivision.
DISCUSSION
With the adoption of the FY2019 Five Year Capital Improvement Program Budget, there
is funding in the amount of $175,000 to abandon the existing lift station and connect a
portion (24 properties) of the Twin Ridge subdivision to the City's sanitary sewer
collection system. Connecting these properties will reduce the flow entering the existing
lagoon treatment facility located within the subdivision.
A future project, included in the adoption of the FY2019 Five Year Capital Improvement
Program Budget, will abandon the lagoon treatment facility and connect the remaining
portion of the Twin Ridge subdivision to the City of Dubuque sanitary sewer collection
system. This project is planned for FY2021.
BID RESULTS
Sealed bids were received on the project on August 23, 2018. Gansen Excavating, Inc.
of Dubuque, lowa submitted the low bid in the amount of $105,976.17. This amount is
4.64°k under the estimate of probable cost. A summary of the bid proposals is as
follows:
Contractor Total Bid
Gansen Excavatin , Inc $ 105,976.17
Connoll Construction, Inc $ 116,033.40
Horsfield Construction, Inc. $ 129,434.75
MDE LLC dba McDermott Exc. $ 140,227.00
Tschi frie Excavatin $ 157,915.74
RECOMMENDATION
I recommend that the contract for the Twin Ridge Lift Station Abandonment project be
awarded to Gansen Excavating, Inc. of Dubuque, lowa in the base amount of
$105,976.17.
BUDGETIMPACT
The summary of cost for the Twin Ridge Lift Station Abandonment project is
summarized as follows:
Descri tion Estimate Award
Construction $ 111 ,136.00 $ 105,976.17
Contin enc 11 ,113.60 11 ,113.60
En ineerin Desi n, Administration & Ins ection 18 337.4 18 337.4
Total Pro�ect Cost 140 587.04 135 427.21
FUNDING SOURCE
The project funding summary is as follows:
CIP No. Fund Description Fund Amount
7102754 Twin Ridge Lift Station Abandonment $175,000.00
Total Project Funding $ 175,000.00
ACTION TO BE TAKEN
The City Council is requested to award the contract for the Twin Ridge Lift Station
Abandonment project to Gansen Excavating, Inc. of Dubuque, through the adoption of
the enclosed resolution.
2
Prepared by Todd Irwin
cc: Jenny Larson, Budget Director
William O'Brien, Water Pollution Control Manager
John Klostermann, Public Works Director
Todd Irwin, Engineering Technician
3
RESOLUTION NO. 260-18
AWARDING PUBLIC IMPROVEMENT CONTRACT FOR THE TWIN RIDGE LIFT
STATION ABANDONMENT PROJECT
Whereas, sealed proposals have been submitted by contractors for-the Twin-Ridge
Lift Station Abandonment project, (the Project) pursuant to Resolution No. 234-18 and
Notice to Bidders published on the City of Dubuque, Iowa website and plan-room -
service with statewide circulation on the 3th day of August 2018; and
Whereas, said sealed proposals were opened and read on the 23rd day of August
2018 and it has been determined that Gansen Excavating, Inc. of Dubuque, Iowa,
submitted the low bid amount of $105,976.17, and is the lowest responsive, responsible
bidder for the Project.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
That a Public Improvement Contract for the Project is hereby awarded to Gansen
Excavating, Inc and the City Manager is hereby directed to execute a Public
Improvement Contract on behalf of the City of Dubuque for the Project.