Acceptance of Veteran's Park Pickle Ball Courts Project Copyrighted
December 3, 2018
City of Dubuque Consent Items # 17.
ITEM TITLE: Acceptance of Veteran's Park Pickle Ball Courts Project
SUMMARY: City Manager recommending acceptance of the
construction contract for the Veteran's Park Pickle Ball
Courts Project, as completed by Midwest Concrete, Inc.
RESOLUTION Accepting the Veteran's Park Pickle Ball
Courts Project and authorizing the payment to the
contractor
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s)
ATTACHMENTS:
Description Type
Veteran's Park Pickle Ball Courts-NNM Memo City Manager Memo
Staff Memo Staff Memo
Resolution Resolutions
Engineer's Cert Supporting Documentation
THE CITY OF Dubuque
�
AIFA�erlwGh
UB E '�� III►
Masterpiece on the Mississippi Z°°'�w'2
7A13 2017
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Veteran's Park Pickle Ball Courts Project
DATE: November 28, 2018
City Engineer Gus Psihoyos is recommending acceptance of the construction contract
for the Veteran's Park Pickle Ball Courts Project, as completed by Midwest Concrete,
Inc., in the final contract amount of$69,795.60, which is a 14°k increase from the
original contract in the amount of$61 ,177.25. The increase in construction costs was
due to additional granular subbase and topsoil.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�� �� ���
Mic ael C. Van Milligen �� �
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Teri Goodmann, Assistant City Manager
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
THE CITY OF Dubuque
�
� V L L AN•1�c�cit�
i�` j.r
��!
Masterpiece on the M�ssissippi 2007��°��
2613•2017
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer � -
r .�,
DATE: November 26, 2018
RE: Veteran's Park Pickle Ball Courts Project
INTRODUCTION
The enclosed resolution provides for the acceptance of the construction contract for the
Veteran's Park Pickle Ball Courts Project.
BACKGROUND
The Veteran's Park Pickle Ball Courts Project provided for the addition of new asphalt
surFacing over existing asphalt tennis courts for the creation of nine (9) pickle ball courts.
The project included the laying of four inches of granular material over the existing asphalt
courts with the placement of four inches of hot mix asphalt to create the new pickle ball
surface. Removal of existing tennis court posts and basketball posts with placement of
imported topsoil and hydraulic seeding completed the project.
DISCUSSION
The Veteran's Park Pickle Ball Courts Project was completed by Midwest Concrete, Inc.
of Peosta, lowa, in the final contract amount of $69,795.60, which is a 14% increase from
the original contract in the amount of $61,177.25. The increase in construction costs were
due to additional granular subbase and topsoil.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment of
the contract amount of$69,795.60 to Midwest Concrete, Inc. for the Veteran's Park Pickle
Ball Courts Project.
BUDGETIMPACT
The project cost summary for the Veteran's Park Pickle Ball Courts Project is as follows:
Description Estimate Award Final
Construction Contract $ 52,415.00 $ 61,177.25 $ 69,795.60
Contingency 5,241.50 5,241.50 0.00
Contract Admin / Construction Engineering 8,648.48 8,648.48 6,979.56
Total Project Cost ���. $ 75,067.23 7 15
The K�rc�j�ct funding sumn�ary is �s follows;
CIP Fundinq Source Amount
3502290 ResurFacing Tennis Caurts $ 7Ei,775.15
Total Project Funding 76 775 15
ACTION TO BE TAKEN
ThP City Council is r�questec! to adopt fihe attached rEsolution to accept th�
improvements and to authorize tti� payment af thE, contract �mUunt of $69,795.60 to
Mic�wesfi Concr�te, Inc,. for th� Veter�n's Park Pickle Ball Courts Proj�ct.
GNP:kb
Attacriments
cc: Jenny Larson, Budget Director
Jon Diensl, Civil Engineer
Marie W�re, L�is�are Services Manager
Stephen Fehsal, Park Divi�ion Manager
2
RESOLUTION NO. 357-18
ACCEPTING THE VETERAN'S PARK PICKLE BALL COURTS PROJECT AND
AUTHORIZING THE PAYMENT TO THE CONTRACTOR
WHEREAS, the public improvement contract for the Veteran's Park Pickle Ball
Courts Project (the Project) has been completed by the Contractor, Midwest Concrete,
Inc. (Contractor), the City Engineer has examined the work and recommends that the
Project be accepted; and
WHEREAS, the final contract amount for the Project is $69,795.60; and
WHEREAS, the Contractor has previously been paid $66,305.82, leaving a balance
of $3,489.78; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved, and the Project is
hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of $3,489.78 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa
Code chapter 26.13.
Passed, approved and adopted this 3rd day of December 20184
Attest:
fS
Kn S. Firnsfahl, City Clerk
Roy D. Buoi, Mayor
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE VETERAN'S
PARK PICKLE BALL COURTS PROJECT �
�
The undersigned City Engineer of the City of Dubuque, lowa, hereby certifies that �
he has inspected the Veteran's Park Pickle Ball Courts Project, and that said Project i
has been performed in compliance with the terms of the Public Improvement Contract,
and that the total cost of the completed work is $76,775.15. '
�.
,;
��
Dated this�day of 2018. !'
'�
�
FGus si oyos, City Engineer
�
I'
Filed in the office of the City Clerk on th���i� day of ,2018. I
.�,. �- �
��,�" I
�-' i
Ke�n . Firnstahl, C� C, City Clerk i�
�